- Building drain definition
- The lowest piping of a drainage system that receives waste from inside the building and connects to the building sewer at a point 2 feet outside the building wall.
- Fixture unit
- A unit of measure expressing the probable load a fixture places on the drainage or water supply system; one fixture unit equals about 1 cubic foot per minute of flow.
- Minimum drainage slope
- Horizontal drainage pipe 2-1/2 inches and smaller must slope at 1/4 inch per foot; pipe 3 inches and larger may slope at 1/8 inch per foot.
- Vent stack height
- A vent stack must extend at least 6 inches above the roof and be sized according to the drainage stack it serves, with terminals kept away from windows and intakes.
- Trap seal depth
- A fixture trap must maintain a liquid seal of 2 to 4 inches; the seal prevents sewer gas from entering the building and must be protected by venting.
- Grease interceptor purpose
- A device installed in a commercial kitchen drain line that separates and retains fats, oils, and grease so they do not clog the building sewer or public system.
- Water heater T&P valve
- A temperature and pressure relief valve rated for the heater's input that discharges to a safe location, typically terminating 6 to 24 inches above the floor.
- Shower valve requirement
- Shower valves must be pressure-balancing or thermostatic anti-scald type to limit temperature fluctuation and prevent sudden hot or cold water discharge.
- Water closet clearance
- A water closet requires at least 15 inches from its centerline to a side wall and 21 inches of clear space from the front of the fixture to an obstruction.
- Pressure-reducing valve
- A device installed on the water service when street pressure exceeds 80 psi, reducing pressure to a typical 50 to 60 psi to protect fixtures and piping.
- Water supply test pressure
- The water distribution system must be tested at working pressure for at least one hour; hydrostatic test pressure is typically 100 psi or the system working pressure.
- Water-sewer separation
- A water main must be at least 10 feet horizontally from a building sewer, or 18 inches below it when crossing, to prevent contamination of potable water.
- Air gap backflow protection
- The only absolute method of backflow prevention; a physical separation between the water supply outlet and the flood-level rim of a receiving vessel.
- RPZ assembly
- A reduced pressure zone backflow preventer used for high-hazard connections; it must be tested annually by a certified tester and be accessible for maintenance.
- Backflow definition
- The reversal of flow in a water system caused by backpressure or backsiphonage, which can allow contaminants to enter the potable water supply.
- Roof drain sizing
- Roof drains and leaders are sized by roof area and design rainfall intensity in inches per hour, using code tables that relate area to pipe diameter.
- Secondary roof drainage
- An overflow system such as scuppers or secondary drains required where the primary roof drainage could be blocked, discharging to a visible location.
- Sediment trap
- A drip leg installed at the appliance connection on a gas line to catch debris and prevent it from entering the appliance controls.
- Gas appliance shutoff
- A shutoff valve required within 6 feet of each gas appliance, accessible for service, with a union or flanged connection at the appliance.
- Gas piping test
- Gas piping must be tested at 1.5 times working pressure but not less than 3 psi for 10 minutes on low-pressure systems, per the gas code.
- Permit requirement
- A permit must be obtained before installing, altering, or replacing a plumbing system; minor repairs such as clearing stoppages are generally exempt.
- Rough-in inspection
- An inspection of concealed piping before it is covered; water and drainage systems must be tested and approved before concealment.
- Licensed plumber scope
- Plumbing work must be performed by a licensed master or journeyman plumber, or by an apprentice under direct supervision of a licensed plumber.
- Cleanout location
- Cleanouts are required at the base of each stack, at the building drain near the sewer, and at changes of direction greater than 45 degrees.
- Isometric drawing
- A three-dimensional drawing using 30-degree angles to show width, height, and depth; pipe lengths are calculated from true lengths of runs.
- 45-degree offset multiplier
- The length of a 45-degree offset equals the offset distance times 1.414; a 22-1/2 degree offset uses a multiplier of 2.613.
- Developed length
- The total length of pipe plus fittings measured along the centerline, used to size water supply piping and to order material.
- Water softener operation
- A water conditioner using ion exchange to remove hardness minerals; it must have a bypass and discharge regeneration waste to an approved location.
- Combustion air requirement
- Gas appliances must have combustion air provided per manufacturer instructions and the gas code, often through two permanent openings to an interior space.
- Storm and sanitary separation
- Storm drainage must be kept separate from sanitary drainage; combined systems are allowed only where the public sewer is combined and approved.
- Trap arm vent distance
- The horizontal distance from a trap to its vent is limited by pipe size, typically 5 feet for 1-1/2 inch, 6 feet for 2 inch, and 8 feet for 3 inch.
- Thermal expansion tank
- A tank installed on a closed water system to absorb the increased volume caused by heating water, preventing excessive pressure and relief valve discharge.