MRP · Keep the key ideas within reach.

Quick reference

MRP Fundamentals and the Manufacturing Planning Hierarchy

  • Hierarchy levels top-down: strategic business plan (annual, units and dollars) → sales and operations planning (monthly, product families) → master production schedule (weekly, end items) → material requirements planning (daily/weekly, components) → production activity control (daily, orders).

  • MRP answers three questions: what components are needed, how many, and when; it is a time-phased dependent-demand calculation, not a scheduling or execution system.

  • Independent demand is forecast-driven for end items; dependent demand is calculated from parent item requirements via the BOM, so it does not need separate forecasting.

  • MRP inputs: master production schedule, bill of materials, inventory records (on-hand, scheduled receipts, lead times, lot-sizing data). MRP outputs: planned orders, released order recommendations, action/exception messages.

  • Time buckets are normally weekly in MRP but daily in repetitive and JIT environments; bucketless (time-phased) systems place orders on exact due dates rather than bucket boundaries.

  • Planning horizon must exceed the longest cumulative lead time of any end item, otherwise the plan cannot react to changes before the first order must be released.

  • MRP II extends MRP with capacity planning, costing, and financial integration; ERP extends MRP II across the enterprise and supply chain.

  • Closed-loop MRP feeds capacity results and execution feedback back into the plan, so the MPS is revised when capacity is infeasible.

Quick reference

Master Production Schedule and Demand Management

  • MPS states, per end item and per time bucket, the quantity planned to be produced; it drives MRP and must be stated in actual buildable configurations, not product-family aggregates.

  • Available-to-promise (ATP) = scheduled MPS receipts minus already-committed customer orders; the first-period ATP subtracts beginning inventory as well.

  • Projected available balance = prior balance + MPS receipts − max(forecast, actual demand) when forecast and orders are combined by the larger-value rule; otherwise subtract their sum.

  • MPS should be frozen for the cumulative lead time (firm zone), then slushy (trading zone) where limited changes are allowed, then liquid (free zone) where changes are routine.

  • Forecast consumption prevents double counting: customer orders consume forecast within a period or backward over a consumption window before the forecast is treated as demand.

  • Time fences define the boundaries between frozen, slushy, and liquid zones and are the mechanism for controlling nervousness in the MPS.

  • Planning bill (super bill) or percentage-blend BOMs translate family-level forecasts into option-level MPS quantities for configure-to-order products.

  • Rough-cut capacity planning should validate the MPS before it is released to MRP; an unvalidated MPS generates infeasible component plans.

Quick reference

Bill of Materials Structure and Explosion

  • BOM is a hierarchical listing of components, quantities per parent, and effectivity; each parent-component pair is one BOM line with its own scrap and effectivity dates.

  • Low-level coding places each item at its deepest level in the product structure so MRP explodes it only after all parent requirements are known.

  • Single-level explosion: component requirement = parent planned order release × quantity per × (1 + scrap %).

  • Multi-level explosion applies the single-level calculation level by level, top to bottom, using low-level codes; cumulative lead time is the sum of lead times along the longest path.

  • Phantom (blow-through) items are assemblies that are exploded through rather than stocked; they have no inventory and no planned orders, only their children are planned.

  • Where-used (implosion) reports list every parent that consumes an item; they are essential for engineering change impact analysis and recall/quality containment.

  • BOM effectivity dates and engineering change control ensure that a component is only planned for orders whose dates fall inside its effective range.

  • Modular (planning) BOMs and option classes support configure-to-order: the 100% BOM is assembled from selected options at order entry, then exploded by MRP.

Quick reference

Inventory Records, Lead Times, and Item Master Data

  • Item master fields that drive MRP: item number, description, unit of measure, item type (make/buy/phantom), planner, low-level code, lead time, safety stock, lot-sizing rule, and scrap percentage.

  • Lead time components: queue, setup, run, move, wait, and inspection; cumulative lead time runs from purchase of the longest-lead component to final assembly.

  • Planned order release date = planned order due date − lead time; if lead time is longer than the remaining horizon, the order is released immediately and flagged.

  • Safety stock covers demand and supply variability; safety lead time covers timing variability and shifts the due date rather than the quantity.

  • Inventory record accuracy is measured by cycle counting; a common tolerance is ±0.2% of inventory value for A items and ±5% for C items, with 95%+ record accuracy as an MRP prerequisite.

  • Shrinkage, scrap, and yield must be carried in the item master; planning scrap = order quantity × scrap % and is added to the component requirement, not subtracted from supply.

  • Item status codes (active, inactive, obsolete, pending) prevent MRP from planning superseded parts while preserving history for where-used analysis.

  • Fixed, variable, and lot-for-lot lead times: fixed lead time applies per order, variable lead time scales with quantity, and lot-for-lot ignores quantity effects.

Quick reference

Lot Sizing and Netting Logic

  • Net requirement = gross requirement + safety stock − projected available balance − scheduled receipts; if negative, it is zero.

  • Lot-for-lot (L4L) orders exactly the net requirement each period; it minimizes inventory but maximizes order count and setup cost.

  • Fixed order quantity orders a constant lot size and may generate planned orders larger than the net requirement, creating residual inventory.

  • Economic order quantity EOQ = √(2DS/H), where D = annual demand, S = ordering/setup cost per order, H = annual holding cost per unit.

  • Period order quantity (POQ) sets the order cycle to EOQ / average periodic demand, ordering to cover an integer number of periods.

  • Least total cost compares setup cost against holding cost across candidate coverage periods and selects the coverage where the two are closest to equal.

  • Least unit cost divides total setup plus holding cost by the units ordered and selects the coverage period with the lowest cost per unit.

  • Net change MRP recalculates only items affected by a change; regenerative MRP recalculates the entire plan, typically on a fixed cycle.

  • Pegging traces a component requirement back to the end item and customer order that generated it, which is essential for order promising and change impact analysis.

Quick reference

Capacity Requirements Planning and Rough-Cut Capacity Planning

  • RCCP validates the MPS using capacity bills, resource profiles, or rough-cut capacity planning by work center; it uses product-family load factors rather than detailed routings.

  • Capacity requirements planning (CRP) converts planned and released orders into work-center load using routings, standard times, and order dates; it is the capacity check for MRP.

  • Load profile per work center per period = Σ (order quantity × run time per unit + setup time) for all orders assigned to that period.

  • Available capacity = work center hours per shift × shifts × days in period × utilization × efficiency, less planned downtime and maintenance.

  • Load percentage = required hours / available hours; above 100% indicates a capacity constraint, below a threshold (commonly 70–80%) indicates underutilization.

  • Infinite loading assumes unlimited capacity and shows pure demand; finite loading schedules within capacity and produces a feasible sequence.

  • Capacity is adjusted by overtime, extra shifts, subcontracting, alternate routings, or moving load to another period; load is adjusted by lot splitting, order release timing, or rescheduling.

  • Input/output control monitors actual work-center throughput against planned input and output; a growing queue indicates capacity shortfall or upstream release problems.

Quick reference

MRP Outputs, Action Messages, and Exception Management

  • MRP outputs: planned orders (release, reschedule in, reschedule out, cancel), scheduled receipts, action messages, exception reports, and pegging reports.

  • Release message means the planned order's start date has arrived and the order should be converted to a production or purchase order.

  • Reschedule-in moves an existing scheduled receipt earlier; reschedule-out moves it later; cancel recommends deleting a receipt no longer needed.

  • Exception messages are prioritized by planner action date and severity; a common rule is to work the highest-severity messages first and never let the exception queue age past a defined threshold.

  • Nervousness is excessive plan change caused by small demand changes; it is dampened by time fences, firm planned orders, and lot-sizing stability.

  • Firm planned orders are not changed by MRP regeneration; they are used to protect committed supply and to stabilize the near-term plan.

  • Exception categories typically include late orders, past-due receipts, negative inventory, orders beyond the planning horizon, and orders with no routing or BOM.

  • Planner should review action messages by exception, not by scanning every order; the message is a recommendation and requires planner judgment before execution.

Quick reference

ERP Integration, System Implementation, and Performance Metrics

  • ERP integrates MRP with finance, purchasing, sales, and shop-floor execution; a single item master and BOM is the shared source of truth across modules.

  • Implementation phases: readiness assessment, data cleansing and conversion, conference room pilot, cutover, go-live, and post-go-live stabilization.

  • Critical success factors: executive sponsorship, accurate item/BOM/inventory data, user training, process ownership, and a defined cutover and rollback plan.

  • Common failure causes: poor data accuracy, scope creep, unrealistic timelines, insufficient testing, and treating the project as IT-only rather than a business change.

  • Delivery performance is measured by on-time delivery, order fill rate, and perfect order rate; plan stability by the percentage of orders rescheduled per period.

  • Inventory metrics: inventory turns = cost of goods sold / average inventory value; days of supply = average inventory / average daily usage.

  • MRP effectiveness metrics include forecast accuracy (MAPE), schedule adherence, capacity utilization, exception message volume, and record accuracy.

  • Integration testing must verify that transactions flow correctly across modules: a purchase order receipt must update inventory, MRP, and the general ledger consistently.

Quick reference

MRP Fundamentals and the Manufacturing Planning Hierarchy

  • The planning hierarchy flows from the strategic business plan down to production activity control, with each level covering a shorter horizon and finer granularity than the one above it.

  • MRP is a time-phased dependent-demand system: it calculates component requirements from the MPS and BOM rather than forecasting them independently.

  • The four core MRP inputs are the master production schedule, bill of materials, inventory records, and item master data such as lead times and lot-sizing rules.

  • MRP outputs include planned orders, action messages, exception reports, and pegging information used to trace requirements back to their source.

  • The planning horizon must cover the longest cumulative lead time so the system can release orders early enough to meet the end-item schedule.

  • MRP II adds capacity planning, costing, and financial integration to basic MRP; ERP extends the same logic across the whole enterprise.

  • Closed-loop MRP feeds capacity and execution results back into the plan, so the MPS is revised when the plan proves infeasible.

  • Time buckets are typically weekly in MRP and daily in repetitive or JIT environments; bucketless systems schedule orders on exact dates.

Quick reference

Master Production Schedule and Demand Management

  • The MPS states, per end item and per time bucket, the quantity planned to be produced; it drives MRP and should reflect buildable configurations.

  • Available-to-promise (ATP) = scheduled MPS receipts minus committed customer orders; the first period also subtracts beginning inventory.

  • Projected available balance = prior balance + MPS receipts − demand, where demand is the forecast or actual orders per the combining rule in use.

  • Time fences divide the horizon into frozen, slushy, and liquid zones, controlling how much the MPS may change in each period.

  • Forecast consumption prevents double counting by netting customer orders against forecast before the forecast is treated as demand.

  • Planning bills translate product-family forecasts into option-level MPS quantities for configure-to-order product lines.

  • Rough-cut capacity planning should validate the MPS before it is released to MRP, so component plans are not built on infeasible schedules.

  • A frozen zone typically extends for the cumulative lead time, protecting committed supply from plan changes.

Quick reference

Bill of Materials Structure and Explosion

  • A BOM lists each parent-component pair with quantity per, scrap percentage, and effectivity dates; each pair is one BOM line.

  • Low-level coding places each item at its deepest level in the product structure so MRP explodes it only after all parent requirements are known.

  • Single-level explosion: component requirement = parent planned order release × quantity per × (1 + scrap %).

  • Multi-level explosion applies the single-level calculation level by level, top to bottom, using low-level codes.

  • Phantom items are exploded through rather than stocked; they have no inventory and no planned orders, only their children are planned.

  • Where-used (implosion) reports list every parent consuming an item and are essential for engineering change impact analysis.

  • Effectivity dates ensure a component is only planned for orders whose dates fall inside its effective range.

  • Modular and planning BOMs support configure-to-order by assembling a 100% BOM from selected options at order entry.

Quick reference

Inventory Records, Lead Times, and Item Master Data

  • Item master fields that drive MRP include item number, unit of measure, item type, planner, low-level code, lead time, safety stock, lot-sizing rule, and scrap percentage.

  • Lead time components are queue, setup, run, move, wait, and inspection; cumulative lead time runs along the longest path to final assembly.

  • Planned order release date = planned order due date − lead time; orders whose release date has passed are flagged for immediate action.

  • Safety stock covers quantity variability; safety lead time covers timing variability by shifting due dates rather than quantities.

  • Cycle counting measures inventory record accuracy, with tighter tolerances for A items than for C items; high accuracy is an MRP prerequisite.

  • Planning scrap adds to component requirements as order quantity × scrap %, increasing the quantity planned rather than reducing supply.

  • Item status codes (active, inactive, obsolete, pending) prevent MRP from planning superseded parts while preserving history.

  • Lead times may be fixed per order, variable with quantity, or lot-for-lot, depending on the item's setup and run characteristics.

Quick reference

Lot Sizing and Netting Logic

  • Net requirement = gross requirement + safety stock − projected available balance − scheduled receipts; a negative result is set to zero.

  • Lot-for-lot orders exactly the net requirement each period, minimizing inventory but maximizing order count and setup cost.

  • Fixed order quantity orders a constant lot size and may create residual inventory when the lot exceeds the net requirement.

  • Economic order quantity EOQ = √(2DS/H), where D is annual demand, S is ordering or setup cost per order, and H is annual holding cost per unit.

  • Period order quantity sets the order cycle to EOQ divided by average periodic demand, ordering to cover an integer number of periods.

  • Least total cost compares setup cost against holding cost across candidate coverage periods and selects where the two are closest to equal.

  • Least unit cost divides total setup plus holding cost by the units ordered and selects the coverage with the lowest cost per unit.

  • Pegging traces a component requirement back to the end item and customer order that generated it, supporting order promising and change impact analysis.

Quick reference

Capacity Requirements Planning and Rough-Cut Capacity Planning

  • RCCP validates the MPS using capacity bills, resource profiles, or work-center load factors from product families rather than detailed routings.

  • Capacity requirements planning converts planned and released orders into work-center load using routings, standard times, and order dates.

  • Load per work center per period = Σ (order quantity × run time per unit + setup time) for all orders assigned to that period.

  • Available capacity = hours per shift × shifts × working days × utilization × efficiency, less planned downtime and maintenance.

  • Load percentage = required hours / available hours; above 100% signals a capacity constraint, well below 100% signals underutilization.

  • Infinite loading assumes unlimited capacity and shows pure demand; finite loading schedules within capacity and produces a feasible sequence.

  • Capacity is adjusted by overtime, extra shifts, subcontracting, alternate routings, or moving load to another period.

  • Input/output control compares actual work-center throughput against planned input and output; a growing queue signals capacity shortfall.

Quick reference

MRP Outputs, Action Messages, and Exception Management

  • MRP outputs include planned orders, scheduled receipts, action messages, exception reports, and pegging reports.

  • Release message means the planned order's start date has arrived and the order should be converted to a production or purchase order.

  • Reschedule-in moves an existing scheduled receipt earlier; reschedule-out moves it later; cancel recommends deleting a receipt no longer needed.

  • Exception messages are prioritized by planner action date and severity, and the highest-severity messages are worked first.

  • Nervousness is excessive plan change caused by small demand changes; time fences, firm planned orders, and lot-sizing stability dampen it.

  • Firm planned orders are not changed by MRP regeneration and are used to protect committed supply and stabilize the near-term plan.

  • Exception categories include late orders, past-due receipts, negative inventory, orders beyond the horizon, and orders lacking a routing or BOM.

  • Action messages are recommendations requiring planner judgment; they are reviewed by exception rather than by scanning every order.

Quick reference

ERP Integration, System Implementation, and Performance Metrics

  • ERP integrates MRP with finance, purchasing, sales, and shop-floor execution; a single item master and BOM is the shared source of truth.

  • Implementation phases include readiness assessment, data cleansing and conversion, conference room pilot, cutover, go-live, and post-go-live stabilization.

  • Critical success factors include executive sponsorship, accurate item/BOM/inventory data, user training, process ownership, and a cutover and rollback plan.

  • Common failure causes include poor data accuracy, scope creep, unrealistic timelines, insufficient testing, and treating the project as IT-only.

  • Delivery performance is measured by on-time delivery, order fill rate, and perfect order rate; plan stability by the percentage of orders rescheduled per period.

  • Inventory turns = cost of goods sold / average inventory value; days of supply = average inventory / average daily usage.

  • MRP effectiveness metrics include forecast accuracy (MAPE), schedule adherence, capacity utilization, exception message volume, and record accuracy.

  • Integration testing must verify transactions flow consistently across modules, such as a purchase order receipt updating inventory, MRP, and the general ledger.