MRP study materials
MRP study resources

MRP flashcards

MRP · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Dependent demand
Demand for components derived from the demand for parent end items through the bill of materials, so it is calculated rather than forecast independently.
Master production schedule
A time-phased statement of the quantities of end items to be produced in each period, which drives material requirements planning and must reflect buildable configurations.
Available-to-promise
Scheduled MPS receipts minus customer orders already committed; the first period also subtracts beginning inventory, showing quantity still available to promise to new orders.
Time fence
A boundary in the planning horizon separating frozen, slushy, and liquid zones, controlling how much the master schedule may change within each period.
Forecast consumption
The practice of netting customer orders against forecast within a defined window so that demand is not counted twice in the master schedule.
Planning bill
A super bill or percentage-blend BOM that translates product-family forecasts into option-level or component-level master schedule quantities for configure-to-order products.
Low-level code
The deepest level at which an item appears in any product structure, used so MRP explodes an item only after all parent requirements are known.
Phantom item
An assembly that is exploded through rather than stocked; it carries no inventory and no planned orders, and only its children are planned.
Where-used report
An implosion listing every parent assembly that consumes a given component, used for engineering change impact analysis and quality containment.
BOM effectivity
Date ranges on a bill of materials line that determine when a component is valid, so MRP plans it only for orders falling inside the range.
Cumulative lead time
The longest total of lead times along any path from the lowest purchased component through all levels to the finished end item.
Safety lead time
A buffer applied to order due dates rather than quantities, protecting the plan against timing variability in supply or operations.
Cycle counting
Counting inventory in small scheduled increments rather than one annual physical count, measuring record accuracy against tolerances set by item classification.
Planning scrap
A percentage carried in the item master that increases component requirements, calculated as order quantity times scrap percent, rather than reducing available supply.
Net requirement
Gross requirement plus safety stock minus projected available balance and scheduled receipts; a negative result is treated as zero.
Lot-for-lot sizing
A lot-sizing rule that orders exactly the net requirement in each period, minimizing inventory while maximizing order count and setup cost.
Economic order quantity
The order size that minimizes total setup plus holding cost, calculated as the square root of two times annual demand times setup cost divided by holding cost per unit.
Period order quantity
A lot-sizing rule that sets the order cycle to economic order quantity divided by average periodic demand, ordering enough to cover an integer number of periods.
Pegging
The capability to trace a component requirement back to the end item and customer order that generated it, supporting order promising and change impact analysis.
Net change MRP
A processing mode that recalculates only the items affected by a change, in contrast to regenerative MRP which recalculates the entire plan.
Rough-cut capacity planning
A capacity check on the master production schedule using product-family load factors or resource profiles, performed before the MPS is released to MRP.
Capacity requirements planning
The detailed capacity check that converts planned and released orders into work-center load using routings, standard times, and order dates.
Infinite loading
A capacity technique that assumes unlimited capacity and shows pure demand by work center and period, without producing a feasible sequence.
Input/output control
A work-center monitoring technique comparing actual throughput against planned input and output, where a growing queue signals a capacity shortfall.
Reschedule-in message
An action message recommending that an existing scheduled receipt be moved to an earlier date so material arrives in time for its requirement.
Firm planned order
A planned order protected from change by MRP regeneration, used to stabilize the near-term plan and protect committed supply.
Nervousness
Excessive plan change caused by small demand changes, dampened by time fences, firm planned orders, and stable lot-sizing rules.
Exception message
An MRP output flagging a condition needing planner attention, such as a late order or negative inventory, prioritized by action date and severity.
Release message
An action message indicating that a planned order's start date has arrived and the order should be converted to a production or purchase order.
Conference room pilot
A pre-go-live ERP test in which users run real business processes end to end in the configured system to validate data and process fit.
Inventory turns
Cost of goods sold divided by average inventory value, measuring how many times inventory is replenished and consumed over a period.
Perfect order rate
The percentage of orders delivered complete, on time, damage-free, and with correct documentation, a composite measure of delivery performance.