Rated Capacity

The maximum load a crane is permitted to lift under a specific configuration, as stated in the manufacturer's load chart for that boom length, radius, and counterweight setup.

Related: Load Chart, Working Radius, Gross Load
Load Chart

A manufacturer-supplied table or graph showing the allowable capacity of a crane at various radii, boom lengths, and configurations, with deductions for attachments and reeving.

Related: Rated Capacity, Working Radius, Net Capacity
Working Radius

The horizontal distance from the crane's center of rotation to the center of gravity of the suspended load, measured with the boom at the given load chart condition.

Related: Rated Capacity, Load Moment
Gross Load

The total weight being handled, including the load itself plus rigging, slings, shackles, spreader beams, and any other below-the-hook equipment attached to the hook.

Related: Net Capacity, Rated Capacity
Net Capacity

The usable lifting capacity remaining after all deductions, such as the weight of the hook block, rigging, and optional attachments, are subtracted from the chart value.

Related: Gross Load, Rated Capacity
Load Moment

The product of a load's weight and its horizontal distance from the tipping axis or center of rotation, used to evaluate stability and to compare against the crane's rated moment limits.

Related: Working Radius, Load Moment Indicator
Load Moment Indicator

An instrument system that senses boom angle, length, and load to display the percentage of rated capacity used and warn the operator before an overload condition occurs.

Related: Load Moment, Rated Capacity
Sling Angle Factor

A multiplier applied to a sling's vertical load to account for the increased tension created when the sling legs are inclined from vertical rather than hanging straight down.

Related: Tension, Sling Leg
Sling Leg

One individual segment of a sling assembly running from the master link or hook to the attachment point on the load, each carrying a share of the total load.

Related: Sling Angle Factor, Master Link
Tension

The pulling force carried within a sling leg or rope, which increases as the angle between the leg and vertical increases for a given vertical load.

Related: Sling Angle Factor, Sling Leg
Shackle

A U-shaped metal fitting with a pin or bolt used to connect slings, hooks, and lifting eyes, rated for a specific working load limit and marked accordingly.

Related: Working Load Limit, Master Link
Master Link

The large ring at the top of a multi-leg sling assembly that gathers all the sling legs and attaches to the crane hook, distributing load evenly among the legs.

Related: Sling Leg, Shackle
Working Load Limit

The maximum mass or force a rigging component is authorized to support in a specific service, assigned by the manufacturer and typically stamped or tagged on the item.

Related: Shackle, Rated Capacity
Center of Gravity

The point in an object where its weight is considered concentrated, critical for determining where the hook must be placed to keep the load level and stable.

Related: Sling Leg, Load Moment
Pre-Operational Inspection

A documented check performed before each shift covering wire rope, hooks, brakes, controls, safety devices, fluid levels, and structural components to confirm the crane is fit for service.

Related: Wire Rope, Frequent Inspection
Wire Rope

A lifting and hoisting line made of strands of steel wires laid around a core, used for boom hoist, load hoist, and pendants, subject to wear and discard criteria.

Related: Broken Wire, Pre-Operational Inspection
Broken Wire

An individual wire in a rope strand that has fractured, counted during inspection and compared against removal criteria based on the number found in a specified length.

Related: Wire Rope, Rope Lay
Rope Lay

The pattern in which wires and strands are twisted together, such as regular lay or lang lay, which affects abrasion resistance, flexibility, and how broken wires are counted.

Related: Wire Rope, Broken Wire
Frequent Inspection

A periodic inspection performed at intervals determined by the crane's service and environment, covering wear items and safety devices more thoroughly than a daily check.

Related: Pre-Operational Inspection, Periodic Inspection
Periodic Inspection

A comprehensive inspection at longer intervals, often annual, that includes disassembly or detailed examination of components not accessible during routine frequent inspections.

Related: Frequent Inspection, Pre-Operational Inspection
Outrigger

A retractable beam extending from the crane chassis to widen the support base, usually fitted with a float or pad, to increase stability during lifting operations.

Related: Outrigger Float, Ground Bearing Pressure
Outrigger Float

A pad or plate placed under an outrigger to spread the load over a larger ground area, reducing bearing pressure and preventing the outrigger from sinking.

Related: Outrigger, Ground Bearing Pressure
Ground Bearing Pressure

The force per unit area that a crane's outrigger or track imposes on the supporting surface, which must not exceed the ground's capacity to avoid settlement or collapse.

Related: Outrigger Float, Outrigger
Counterweight

Mass mounted on the rear of the crane's rotating upper structure to offset load moment and improve stability, installed in the amount specified by the load chart.

Related: Load Moment, Rated Capacity
Boom

The main structural member that extends from the crane to support the load at a working radius, available in telescopic, lattice, or articulated configurations.

Related: Working Radius, Boom Angle
Boom Angle

The angle between the boom centerline and horizontal, used with boom length to determine working radius and to select the correct load chart capacity.

Related: Boom, Working Radius
Anti-Two-Block Device

A safety system that detects when the hook block approaches the boom tip and stops hoisting or lowering to prevent the two from colliding and damaging the rope.

Related: Hook Block, Limit Switch
Hook Block

An assembly containing a hook and one or more sheaves that reeve the load line, allowing multiple parts of line to increase lifting capacity and control load descent.

Related: Anti-Two-Block Device, Parts of Line
Parts of Line

The number of rope segments running between the boom tip and the hook block, which multiplies the line pull and determines the available lifting capacity.

Related: Hook Block, Rated Capacity
Standard Hand Signals

A set of agreed arm and hand motions used by a signalperson to direct crane movements, ensuring clear communication when voice or radio contact is unreliable.

Related: Signalperson, Radio Communication
Signalperson

A designated individual responsible for directing the crane operator using standard signals, positioned where both the operator and the load are visible.

Related: Standard Hand Signals, Radio Communication
Radio Communication

Two-way voice contact between the operator and signalperson or riggers, used when distance or obstruction prevents visual signals, with agreed channels and emergency words.

Related: Signalperson, Standard Hand Signals
Minimum Approach Distance

The closest distance a crane, load, or rigging may come to an energized power line, set by voltage and regulation to prevent electrical arcing and contact.

Related: Power Line, Spotter
Power Line

An overhead or underground electrical conductor that presents an electrocution hazard, requiring de-energizing, isolation, or strict clearance control before crane operation nearby.

Related: Minimum Approach Distance, Spotter
Spotter

A person assigned to watch clearances and ground conditions around the crane and to warn the operator, especially near power lines or when visibility is restricted.

Related: Minimum Approach Distance, Signalperson
Wind Speed Limit

The maximum wind velocity at which a crane may operate or continue lifting, specified by the manufacturer and affected by boom length and load sail area.

Related: Load Chart, Rated Capacity
Competent Person

An individual who, by training and experience, can identify hazards and has authority to take corrective action, often required for inspections and rigging decisions.

Related: Qualified Person, Pre-Operational Inspection
Qualified Person

A person who by possession of a recognized degree, certificate, or professional standing, or by extensive experience, can design, evaluate, or approve crane-related work.

Related: Competent Person, Load Chart
Operator Responsibility

The duty of the crane operator to verify load charts, inspect equipment, refuse unsafe lifts, follow signals, and stop work when conditions become hazardous.

Related: Competent Person, Pre-Operational Inspection