MT General Contractor study materials
MT General Contractor study resources

MT General Contractor: Lien Law, Payment, and Risk Management

MT General Contractor · Work through your exam, one topic at a time.

All guide sections

Lien Law, Payment, and Risk Management

What this domain tests

Montana mechanic's liens, payment, retainage, bonds, insurance, indemnity, and risk transfer.

Core rules

  • Montana lien law is MCA Title 71, chapter 3. A claimant not in direct contract with the owner generally must give the owner a written Notice of Right to Claim Lien within 20 days after first furnishing; the lien must be recorded within 90 days after last furnishing. Verify current deadlines before relying.
  • Lien waivers: conditional vs unconditional, progress vs final. Never sign a final unconditional waiver before funds clear.
  • Public work: payment bonds substitute for lien rights; bond notice deadlines apply.
  • Retainage: follow the contract and Montana public-works rules; release at substantial or final completion.
  • Risk: CGL, umbrella, builders risk, workers' comp, professional liability; indemnity and additional-insured endorsements; surety bonds.

Worked example

A supplier first delivers April 1 and last delivers June 1. It should send the owner the 20-day notice by April 21 and record the lien by August 30. Waiting until September likely destroys the lien, leaving only a contract or bond claim.

Traps

Assuming the prime must send the 20-day notice; signing unconditional waivers; missing bond notice; relying on liens on public work; letting insurance lapse.