Cut-slope instability on a gravel road upgrade in Mulanje
Engineers are upgrading 2.4 km of gravel road in Mulanje District. The new alignment requires a 9 m cut into weathered granite. Foliation dips about 35° toward the road, and a 20–30 cm clay-rich seam runs along the cut face. In the past 48 hours the area received 210 mm of rain; the last 6 hours brought 70 mm. Inspectors see tension cracks 15–30 m upslope, seepage at the toe, and bulging of the lower slope. Fourteen households and a primary school for 300 pupils lie downslope. The road is the only all-weather route to the clinic, 11 km away. The contractor wants to reopen the road tomorrow after clearing fallen debris. The district engineer must decide whether to allow traffic, evacuate residents, or order temporary closure, and what stabilisation to require before the next rainy season.
1. Using the evidence, explain the processes that make a large failure more likely than small surface erosion.
Read the worked answer
The cut is not merely suffering surface wash. Rainfall of 210 mm, including 70 mm in six hours, raises pore-water pressure in the weathered granite. This reduces effective stress and suction, so the material loses apparent cohesion. The clay-rich seam absorbs water, softens and becomes a low-friction plane. Because foliation dips 35° toward the road, the failure surface can daylight in the cut; the slope is undercut at its toe, removing support. Tension cracks upslope show that tensile failure has begun and give water a direct route into the mass. Seepage at the toe shows groundwater is flowing along the seam. Bulging indicates slow downslope movement before collapse. The combination of a persistent clay layer, adverse dip, high rainfall and toe removal makes a deep translational slide more likely than small surface erosion. The cracks also mean that even moderate further rain could trigger rapid failure. The school and houses are in the run-out area, so the consequence is high even if probability is uncertain.
2. Recommend whether the district engineer should close the road and evacuate the 14 households now. Justify under uncertainty.
Read the worked answer
Closure and evacuation are justified on a precautionary basis. The evidence already meets common triggers for instability: tension cracks, seepage, bulging and a clay seam dipping out of the slope. With 70 mm in six hours and more rain possible, the slope may move without warning. The road is the only all-weather route to the clinic, so closure has a cost, but a vehicle trapped under a slide would be worse. The 14 households directly downslope should be evacuated first, especially at night; the school should be closed or moved if it lies in the likely run-out path. Traffic should be stopped at both ends, not just near the cut. The engineer should set a rainfall threshold and visual monitoring, and allow reopening only after inspection, drainage and toe support. Because uncertainty is high and evacuation is reversible, the safer error is to evacuate and close. The decision should be recorded and communicated with a clear review time.
3. Outline a stabilisation and monitoring package for the site, ranking measures by urgency.
Read the worked answer
Rank by urgency. Immediately: close the road, evacuate downslope residents, seal cracks with compacted clay, and cut interception drains above the crest to divert runoff. Install toe drains and a temporary rock buttress at the seepage zone. Short term: bench the slope, reduce the cut angle, and place a graded rockfill or gabion toe support; do not rely on vegetation alone. Medium term: a proper retaining structure or reinforced soil wall designed for the clay seam, plus subsurface drainage. Monitor with piezometers, surface movement pins and crack gauges; set rainfall and movement thresholds linked to community warnings. Revegetate only after drainage works. Rank: life safety and water control first, structural support second, monitoring throughout. The cheapest measure, drainage, addresses the main process, but it must be maintained. Any reopening should be conditional on a completed drainage and support design, not on clearing debris alone.