DPLI Screening key terms
DPLI Screening · Get comfortable with the vocabulary.
- Pressure vessel
- Related: Maximum allowable working pressure, Hydrostatic test
A closed container designed to hold liquids or gases at a pressure different from ambient, built and stamped to a recognized construction code and subject to periodic inspection over its service life.
- Maximum allowable working pressure (MAWP)
- Related: Pressure vessel, Relief valve, Hydrostatic test
The highest internal pressure a vessel or system is permitted to operate at under its design conditions, established by the designer and confirmed by code calculations and testing.
- Relief valve
- Related: Set pressure, Maximum allowable working pressure
An automatic device that opens at a preset pressure to discharge fluid and protect equipment from overpressure, then recloses as pressure falls back below the set point.
- Set pressure
- Related: Relief valve, Calibration
The inlet pressure at which a relief device is adjusted to begin opening, recorded on the device tag and verified during bench or in-place testing.
- Hydrostatic test
- Related: Pneumatic test, Pressure vessel, Maximum allowable working pressure
A pressure test using water or another liquid to verify strength and leak tightness, typically held at a specified multiple of design pressure for a defined time while surfaces are examined.
- Pneumatic test
- Related: Hydrostatic test, Lockout/tagout
A pressure test using air or gas, requiring greater exclusion zones and stored-energy controls than liquid testing because a failure releases far more energy and can fragment the test item.
- Non-destructive examination (NDE)
- Related: Ultrasonic thickness measurement, Visual inspection
Inspection methods such as radiography, ultrasonic, magnetic particle, dye penetrant, and visual testing that reveal surface or internal flaws without damaging the component being examined.
- Ultrasonic thickness measurement
- Related: Non-destructive examination (NDE), Corrosion allowance
A technique using high-frequency sound pulses to measure remaining wall thickness from one accessible surface, commonly applied to piping and tanks subject to corrosion or erosion.
- Corrosion allowance
- Related: Ultrasonic thickness measurement, Remaining life assessment
Extra wall thickness built into a component beyond that needed for structural strength, intended to be consumed by expected corrosion before the item reaches its retirement limit.
- Remaining life assessment
- Related: Corrosion allowance, Fitness-for-service
A structured evaluation of current condition, measured thickness, operating history, and corrosion rate to estimate how long a component can safely stay in service before repair or replacement.
- Fitness-for-service
- Related: Remaining life assessment, Non-destructive examination (NDE)
A documented engineering judgment that a component containing a known flaw or wall loss is still safe to operate under defined conditions, often with monitoring or reduced limits.
- Visual inspection
- Related: Non-destructive examination (NDE)
Direct or aided observation of equipment for leaks, cracks, corrosion, misalignment, missing guards, or housekeeping problems, forming the first line of most inspection programs.
- Calibration
- Related: Set pressure, Calibration certificate, Traceability
Comparing an instrument's reading against a traceable reference and adjusting it as needed, with results recorded so the instrument's accuracy can be demonstrated at any time.
- Calibration certificate
- Related: Calibration, Traceability
A record identifying the instrument tested, the reference standard used, environmental conditions, before-and-after readings, the technician, and the date of the calibration.
- Traceability
- Related: Calibration, Calibration certificate
The documented chain linking a measurement or test result back to a national or international standard through an unbroken series of calibrations.
- Lockout/tagout
- Related: Permit to work, Confined space entry
A procedure for isolating hazardous energy sources and attaching locks and tags so equipment cannot be re-energized or started while inspection, maintenance, or repair work is underway.
- Permit to work
- Related: Lockout/tagout, Confined space entry, Job safety analysis
A formal written authorization that defines the scope, hazards, precautions, and responsible persons for a specific high-risk task before work begins.
- Confined space entry
- Related: Permit to work, Atmospheric testing, Lockout/tagout
Entering an enclosed or partially enclosed area with limited access and poor ventilation, requiring atmospheric testing, an attendant, rescue arrangements, and an entry permit.
- Atmospheric testing
- Related: Confined space entry
Measuring oxygen content, flammable gases, and toxic gases in a space before and during entry to confirm conditions are safe and remain safe for workers.
- Job safety analysis
- Related: Permit to work, Hazard identification
A step-by-step breakdown of a task that identifies hazards at each step and states the controls needed to reduce risk before the job starts.
- Hazard identification
- Related: Job safety analysis, Risk assessment
The systematic process of recognizing conditions, actions, or materials that could cause harm, so that controls can be selected and applied before an incident occurs.
- Risk assessment
- Related: Hazard identification, Job safety analysis
A structured evaluation of the likelihood and severity of harm from identified hazards, used to rank risks and decide which controls are appropriate.
- Hierarchy of controls
- Related: Risk assessment, Personal protective equipment
The preferred order of risk reduction: eliminate the hazard, substitute something safer, use engineering controls, then administrative controls, with personal protective equipment last.
- Personal protective equipment (PPE)
- Related: Hierarchy of controls
Wearable gear such as helmets, gloves, eye protection, and respirators that reduces exposure to hazards but does not remove the hazard itself.
- Management of change (MOC)
- Related: Pre-startup safety review, As-built drawing
A controlled process for reviewing and approving modifications to equipment, processes, or procedures before implementation, ensuring hazards and documentation are updated.
- Pre-startup safety review
- Related: Management of change (MOC)
A check performed before new or modified equipment is placed in service to confirm construction matches design, procedures are in place, and training is complete.
- Inspection and test plan (ITP)
- Related: Hold point, Witness point, Inspection record
A document listing the inspections and tests required for an item, the acceptance criteria, who performs and witnesses each activity, and the records to be produced.
- Hold point
- Related: Inspection and test plan (ITP), Witness point
A stage in an inspection and test plan where work cannot continue until a designated party has performed the required inspection and recorded approval.
- Witness point
- Related: Inspection and test plan (ITP), Hold point
A stage in an inspection and test plan that a designated party is notified of and may observe, but which does not stop work if that party does not attend.
- Inspection record
- Related: Inspection and test plan (ITP), Nonconformance report
A completed document capturing what was inspected, when, by whom, the method and criteria used, the results found, and any corrective action taken.
- Nonconformance report
- Related: Corrective action, Inspection record
A record describing a failure to meet a specified requirement, the evidence found, the immediate containment, and the disposition or corrective action agreed.
- Corrective action
- Related: Nonconformance report, Root cause analysis
Steps taken to remove the cause of a detected problem so it does not recur, as distinct from simply repairing or reworking the affected item.
- Root cause analysis
- Related: Corrective action
A method for tracing a failure or nonconformance back to its underlying cause rather than its immediate symptom, so that effective corrective action can be chosen.
- As-built drawing
- Related: Management of change (MOC)
A drawing updated to show the actual installed configuration of equipment, piping, and components after construction or modification, including field changes.
- Equipment register
- Related: Inspection record, Inspection interval
A controlled list of equipment items with unique identifiers, design data, location, and inspection status, used to plan and track inspection activity.
- Inspection interval
- Related: Equipment register, Remaining life assessment
The maximum time allowed between inspections of a given item, set by code, risk, condition, and service history, and tracked so no item runs overdue.
- Code of ethics
- Related: Conflict of interest, Falsification of records
A set of principles governing professional behavior, including honesty, competence, confidentiality, avoidance of conflicts of interest, and protection of public safety.
- Conflict of interest
- Related: Code of ethics, Independence
A situation where personal, financial, or other interests could improperly influence professional judgment, requiring disclosure and often removal from the affected decision.
- Independence
- Related: Conflict of interest, Code of ethics
The condition in which an inspector or reviewer has no reporting, financial, or personal tie to the work being judged that could compromise an objective conclusion.
- Falsification of records
- Related: Inspection record, Code of ethics
Entering, altering, or signing data that does not reflect what was actually observed or performed, a serious integrity breach that can invalidate inspections and endanger the public.