PKMC Module I study materials
PKMC Module I study resources

PKMC Module I cheat sheet

PKMC Module I · Keep the key ideas within reach.

Quick reference

Project Management Fundamentals and Organizational Context

  • Project: temporary endeavor producing a unique product, service, or result; operations are ongoing and repetitive. Temporary means the endeavor has a defined start and end, not that the deliverable is short-lived.

  • Project life cycle vs. product life cycle: the project life cycle spans initiation through closure; the product life cycle continues through operation, growth, and retirement after the project ends.

  • Organizational structures: functional (PM authority low, staff in one department), weak matrix (PM limited), balanced matrix (shared authority), strong matrix (PM moderate-to-high, dedicated project staff), projectized (PM near-total authority, staff co-located).

  • PMO types: supportive (templates, training, low control), controlling (compliance with frameworks, moderate control), directive (PMs report to PMO, high control over projects).

  • Project vs. program vs. portfolio: a program is a group of related projects managed together for synergistic benefit; a portfolio is projects, programs, and operations grouped to meet strategic objectives.

  • Project and product life cycles may be predictive (plan-driven, single delivery), iterative (repeated cycles refining scope), incremental (deliveries adding functionality), or agile (adaptive, value-driven).

  • Enterprise environmental factors (EEFs) are conditions not under team control (culture, market, regulations, IT systems); organizational process assets (OPAs) are internal assets the team can use or update (templates, lessons learned, procedures).

Quick reference

Project Initiation, Chartering, and Stakeholder Identification

  • Business case documents the economic justification (cost-benefit, ROI, payback) for the project; benefits management plan defines how and when benefits will be measured and realized.

  • Project charter is issued by the sponsor, formally authorizes the project, names the project manager, and typically records high-level scope, objectives, success criteria, milestones, budget, and key risks; it does not contain a detailed schedule or WBS.

  • The charter gives the PM authority to apply organizational resources; without it, the PM has no formal mandate to plan or execute.

  • Project statement of work (SOW) describes the products or services to be delivered; for external projects it is derived from the contract.

  • Stakeholder register records identification information, assessment information (interest, influence, expectations), and classification; it is a living document updated throughout the project.

  • Power/interest grid classifies stakeholders: high power-high interest = manage closely; high power-low interest = keep satisfied; low power-high interest = keep informed; low power-low interest = monitor.

  • Stakeholder analysis also uses power/influence, impact/influence, and salience models (power, legitimacy, urgency) to prioritize engagement.

  • Assumption log captures assumptions (believed true but unproven) and constraints (limits such as fixed budget, date, or regulatory requirements).

Quick reference

Scope Planning, Requirements, and Work Breakdown Structure

  • Scope management plan defines how scope will be defined, validated, and controlled, including the process for accepting deliverables and handling change requests.

  • Requirements categories include business, stakeholder, solution, functional, and nonfunctional requirements; requirements traceability matrix links each requirement to its source and to WBS deliverables.

  • Project scope statement includes product scope description, deliverables, acceptance criteria, exclusions, constraints, and assumptions; exclusions prevent scope creep by documenting what is out of scope.

  • WBS is a hierarchical decomposition of total project scope into work packages, the lowest level at which cost and duration can be reliably estimated and managed.

  • WBS rules: 100% rule (children sum to the parent's full scope), mutually exclusive branches, 8-80 rule (work packages typically 8 to 80 hours), and no work package spanning more than one reporting period.

  • Work package vs. activity: a work package is a WBS deliverable element; activities are schedule components that decompose work packages for estimating and scheduling.

  • Scope baseline = project scope statement + WBS + WBS dictionary; it is the reference for measuring scope performance and evaluating change requests.

  • Scope creep is uncontrolled expansion of scope without approved changes; gold plating is adding unrequested functionality. Both are controlled through integrated change control and formal scope validation.

Quick reference

Schedule Development and Critical Path Management

  • Critical path is the longest path through the network; it determines the shortest possible project duration. Total float on the critical path is zero (or negative if the project is behind).

  • Float formulas: total float = LS − ES = LF − EF; free float = ES of successor − EF of current activity.

  • Forward pass computes earliest start (ES) and earliest finish (EF = ES + duration); backward pass computes latest finish (LF) and latest start (LS = LF − duration).

  • Total float is the amount an activity can slip without delaying the project finish; free float is the amount it can slip without delaying any successor's early start.

  • Dependencies: mandatory (hard, contract/technical), discretionary (soft, preferred practice), external (outside project control), internal (within project control).

  • Leads and lags: a lag is a waiting time added between activities (e.g., finish-to-start + 5 days cure time); a lead is an overlap (negative lag) allowing a successor to start before its predecessor finishes.

  • Schedule compression: crashing adds resources to critical-path activities to shorten duration, usually increasing cost and risk; fast tracking overlaps activities, usually increasing rework risk.

  • Resource leveling changes start/finish dates to resolve resource over-allocation and may extend the critical path; resource smoothing adjusts activities only within their float and does not change the critical path.

Quick reference

Cost Estimating, Budgeting, and Earned Value Management

  • Estimate types by accuracy: rough order of magnitude (−25% to +75%), budgetary (−10% to +25%), definitive (−5% to +10%); accuracy improves as the project progresses.

  • Cost estimating techniques: analogous (top-down, based on similar past projects, fast but less accurate), parametric (statistical relationship such as cost per unit), bottom-up (detailed, most accurate, most time-consuming), and three-point (PERT).

  • PERT three-point estimate: expected value = (O + 4M + P) / 6; standard deviation = (P − O) / 6; variance = ((P − O) / 6)².

  • Cost baseline = approved time-phased budget excluding management reserves; it is used to measure cost performance.

  • Contingency reserve covers identified risks (known-unknowns) and is part of the cost baseline; management reserve covers unidentified risks (unknown-unknowns) and is outside the baseline but inside the project budget.

  • Earned value core formulas: CV = EV − AC; SV = EV − PV; CPI = EV / AC; SPI = EV / PV. Negative CV or SV means over budget or behind schedule.

  • Forecast formulas: EAC = BAC / CPI (typical variance continues); EAC = AC + (BAC − EV) (atypical variance); EAC = AC + bottom-up ETC; ETC = EAC − AC; VAC = BAC − EAC.

  • TCPI = (BAC − EV) / (BAC − AC) for the remaining work to meet BAC; TCPI = (BAC − EV) / (EAC − AC) when management approves a new EAC.

  • To-complete performance index and variance analysis: a TCPI greater than 1 means remaining work must be performed more efficiently than planned; a CPI or SPI of 1.0 means exactly on plan.

Quick reference

Quality Planning, Assurance, and Control

  • Quality management plan defines quality standards, objectives, roles, and the processes for quality assurance and control; it is a subsidiary of the project management plan.

  • Prevention over inspection: quality is planned and built in; inspection detects defects after the fact and is generally more costly than prevention.

  • Cost of quality: cost of conformance (prevention: training, process design; appraisal: testing, inspections) vs. cost of nonconformance (internal failure: rework, scrap; external failure: warranty, liability, lost business).

  • Quality assurance (manage quality) is process-focused: audits and process analysis verify that the team is following the defined processes; quality control is product-focused: inspection and testing verify deliverables meet requirements.

  • Control chart: monitors process stability over time; a process is out of control when a point exceeds a control limit or shows a nonrandom pattern (seven consecutive points on one side of the mean).

  • Pareto chart: 80/20 principle - a small number of causes produce most defects; used to prioritize corrective action.

  • Cause-and-effect (fishbone/Ishikawa) diagram identifies root causes across categories such as people, process, equipment, materials, and environment.

  • Seven basic quality tools: cause-and-effect diagram, flowchart, check sheet, Pareto chart, histogram, control chart, and scatter diagram.

  • Quality vs. grade: quality is the degree to which requirements are fulfilled; grade is a category of technical characteristics. Low grade can be acceptable; low quality is always a problem.

Quick reference

Resource and Team Management, Leadership, and Conflict Resolution

  • Tuckman ladder of team development: forming (orientation, dependence), storming (conflict over roles), norming (cohesion and agreed norms), performing (high productivity), adjourning (disbanding).

  • Motivation theories: Maslow's hierarchy (physiological, safety, social, esteem, self-actualization); Herzberg's two-factor (hygiene factors prevent dissatisfaction; motivators drive satisfaction); McGregor's Theory X (authoritarian) vs. Theory Y (participative).

  • Acquiring resources uses pre-assignment, negotiation with functional managers, virtual teams, and multi-criteria decision analysis; resource calendars show availability.

  • RACI matrix: Responsible (does the work), Accountable (owns the outcome, exactly one per task), Consulted (two-way input), Informed (one-way updates).

  • Conflict resolution methods ranked by durability: collaborating/problem solving (win-win, best), compromising (lose-lose), smoothing/accommodating (temporary), forcing (win-lose, short-term), withdrawing/avoiding (retreat).

  • Sources of conflict are typically schedule, priorities, resources, technical opinions, and administrative procedures; schedule is often cited as the most common.

  • Servant leadership (agile) shifts focus to removing impediments and enabling the team; situational leadership adapts style (directing, coaching, supporting, delegating) to team maturity.

  • Team performance assessment and recognition: recognition should be based on specific, verifiable performance, and rewards should be within the team's control to avoid demotivation.

Quick reference

Communications and Stakeholder Engagement

  • Communication model: sender encodes → message travels through a medium → receiver decodes → feedback confirms understanding; noise is any interference that distorts the message.

  • Channels formula: number of communication channels = n(n − 1) / 2, where n is the number of stakeholders; adding one stakeholder adds n channels.

  • Communication methods: interactive (meetings, calls - most effective for complex topics), push (email, reports - one-way), pull (intranet, repositories - recipient retrieves).

  • Communication dimensions: formal vs. informal, internal vs. external, vertical vs. horizontal, official vs. unofficial, and written vs. oral.

  • Communication management plan specifies who needs what information, when, in what format, via which channel, and who is responsible for sending it.

  • Stakeholder engagement plan describes strategies to promote productive involvement; engagement levels are unaware, resistant, neutral, supportive, and leading.

  • Communication blockers and effective listening: active listening, paraphrasing, and confirming understanding reduce miscommunication; nonverbal cues carry significant meaning in face-to-face interaction.

  • Information management systems and reporting: work performance data (raw) → work performance information (analyzed) → work performance reports (formatted for stakeholders).

Quick reference

Risk Identification, Analysis, and Response Planning

  • Risk is an uncertain event that, if it occurs, has a positive (opportunity) or negative (threat) effect on project objectives; a risk has a cause, an event, and an effect.

  • Risk management plan defines methodology, roles, risk appetite and thresholds, and the probability/impact scales; it does not list individual risks.

  • Risk identification tools: brainstorming, Delphi (anonymous expert consensus), interviews, root-cause analysis, assumption analysis, SWOT, and prompt lists (e.g., risk breakdown structure).

  • Qualitative analysis: probability/impact matrix, risk data quality assessment, urgency, and risk categorization; it prioritizes risks for further analysis.

  • Quantitative analysis: expected monetary value (EMV = probability × impact), decision tree analysis, Monte Carlo simulation, and sensitivity analysis (tornado diagram).

  • Risk register records identified risks, causes, triggers, owners, probability, impact, response strategies, and status; it is updated throughout the project.

  • Threat responses: escalate (outside project authority), avoid (eliminate the cause), transfer (shift financial impact, e.g., insurance, fixed-price contract), mitigate (reduce probability or impact), accept (active: reserve; passive: acknowledge).

  • Opportunity responses: escalate, exploit (ensure the opportunity occurs), share (allocate to a third party), enhance (increase probability or impact), accept.

  • Residual risk is what remains after responses are applied; secondary risk is a new risk created by a response. Contingency reserves cover residual risks; management reserves cover unknown-unknowns.

Quick reference

Procurement, Contracts, and Vendor Management

  • Make-or-buy analysis determines whether to produce internally or procure externally; it weighs direct and indirect costs, capacity, and strategic factors.

  • Fixed-price contracts (FP, FFP, FP-EPA) place cost risk mainly on the seller and are suitable when scope is well defined; FP-EPA adjusts for economic price changes.

  • Cost-reimbursable contracts (CPFF, CPIF, CPAF) place cost risk mainly on the buyer and suit evolving scope; CPIF shares savings/overruns through a formula.

  • Time and materials (T&M) contracts pay per hour and materials, often with a not-to-exceed cap; they are suited to small, well-bounded, or staff-augmentation work.

  • Contract types by risk to buyer (lowest to highest): FFP, FP-EPA, FP, T&M, CPIF, CPFF, CPAF; the seller's risk runs in the reverse order.

  • Procurement documents include RFP (request for proposal), RFQ (request for quotation), and IFB (invitation for bid); the SOW is a key input to all of them.

  • Source selection uses weighted scoring, screening, and seller rating systems; negotiation typically covers price, schedule, scope, and terms, aiming for a fair and reasonable outcome.

  • Control procurements: contract change control system, procurement performance reviews, inspections and audits, and claims administration; the buyer manages seller performance against the contract.

  • Close procurements: verify all deliverables are accepted, settle claims, and formally close the contract; procurement audits and negotiated settlements may be used. Records are archived for lessons learned.