You are the client-side project manager for a £14m bus priority and cycle corridor scheme being built by a county council along 2.4 km of a suburban high street. Construction started eight weeks ago and has 14 months to run. The communications plan agreed at outline business case consists of a monthly email newsletter, a project web page, and a notice letter to each address two weeks before works reach it. In the last fortnight a traders' association has delivered a petition with 3,100 signatures; its chair says shopkeepers learned about the loss of 22 parking bays from the contractor's barriers rather than from the council. A disability access group has written to a councillor pointing out that the consultation drawings showed no tactile paving at two new crossings and that diversion routes are over 400 m. The bus operator has told you it may suspend the route if dwell times increase, which would remove the scheme's main benefit. A utility company has found an unmapped 1960s gas main in the trench line. The programme director's response is to increase the newsletter to fortnightly and set up a Facebook page.

1. Diagnose why stakeholder management is failing on this scheme, and explain why more frequent broadcasting will not fix it.

Read the worked answer

The plan is a broadcast, not an engagement. A newsletter, a web page and a statutory notice letter push information out; none of them was designed to hear anything back, and none reaches people before the decisions that affect them are taken. Sending the same message more often will increase the volume of complaint, not reduce it.

The four failures

  1. No analysis. There is no segmentation by interest, influence, impact or attitude, so the project cannot distinguish a shopkeeper losing 22 parking bays from a cyclist gaining a lane.
  2. Timing. Consultation happened at outline business case, before the layout was fixed. Traders are reacting to a decision they had no chance to influence, and they found out from a contractor's barrier - the most damaging possible channel.
  3. Relevance. A generic monthly email cannot answer 'how do my deliveries get in on Thursday?'. Affected parties need contact with a person, not a publication.
  4. No feedback loop. Nothing in the plan commits anyone to log, answer or act on what stakeholders say, so even the complaints received have gone nowhere.

What to say to the director. The petition is not a communications problem. It is evidence that the scheme's impact on traders was under-assessed and that the accessibility design is deficient. A Facebook page invites a public argument the project is not resourced to manage, and it will be used to campaign. Fix the engagement model first, then choose channels to suit each audience.

2. Set out how you would re-plan stakeholder engagement for the next three months. Be specific about the groups and what you would escalate.

Read the worked answer

Analyse, then differentiate. Map each group on influence and interest, and separately record actual impact - who is affected, how, and when the works reach them.

Traders (high impact, high interest, currently hostile)

  • Stand up a traders' liaison forum chaired by the council, meeting monthly on the high street, with a named liaison officer and a direct phone number.
  • Reopen the parking decision with evidence: a loading and delivery plan, timed bays, a business support package, and a clear statement of what cannot change and why.
  • Give every business a one-page timeline showing exactly which weeks affect its frontage.

Disability access group (high legitimacy, low power, high impact)

  • This is not a communications issue. Missing tactile paving and 400 m diversion routes are design and compliance problems, potentially a breach of equality duties.
  • Meet the group, commission an accessibility audit against the relevant standard, and raise a formal change request so the fix is designed, priced and approved.
  • Co-design the crossings and diversion routes rather than presenting finished drawings.

Bus operator (high power, commercial dependency)

  • Agree a schedule and performance interface: dwell-time modelling, temporary stops, and a joint review of benefit realisation.

Utility company. Agree a programme interface, permit sequence and diversion dates; record the unmapped main as a risk with schedule impact.

Escalate the accessibility deficiency and the parking decision to the programme board as decisions with cost and legal implications, not as communications actions.

3. The programme director insists on a fortnightly newsletter and a Facebook page. What is your advice, and how would you measure whether engagement is working?

Read the worked answer

Advise that these are channels, not a strategy. A fortnightly newsletter and a Facebook page change how often the project speaks, not whether anyone is heard. They also carry real risks.

Why they will not work on their own

  • A newsletter to 3,100 signatories is still one-way. It answers none of the questions people are actually asking.
  • Social media creates an expectation of dialogue and rapid response. If nobody is resourced to answer within hours, the page becomes a public record of unanswered complaints and a platform for the campaign.
  • Neither channel reaches the businesses whose trade is being lost now.

What to propose instead

  • A channel matrix: face-to-face for affected traders, briefings for councillors and the MP, technical fora for the operator and utility, accessible formats and easy-read material for disabled residents, and digital only for general awareness.
  • A single point of contact and a published service standard for responding to enquiries.
  • A commitment tracker: every issue logged, owned, dated and reported back to the person who raised it.
  • A monthly engagement report to the board.

Test of success. The measures are whether complaints fall, whether the traders' association re-engages, and whether issues are closed within the service standard - not newsletter open rates or page likes. If the director insists on social media, accept it only with a moderation and response resource attached.