SPM PQS 5227 study materials
SPM PQS 5227 study resources

SPM PQS 5227 flashcards

SPM PQS 5227 · Build recall with a focused review session.

36 cards. Read the term and the definition here. The deck at the top of this page is optional.

Definition of a project
A temporary endeavour undertaken to create a unique product, service or result, with defined start and finish dates, resources and objectives.
Programme definition
A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.
Portfolio definition
A collection of projects, programmes and other work grouped together to facilitate effective management and meet strategic business objectives.
PESTLE analysis
External context tool assessing Political, Economic, Social, Technological, Legal and Environmental factors that may affect the project or programme.
Business case purpose
The document justifying investment by setting out reasons, options, costs, benefits, risks and timescales; it is reviewed at each gate.
Power-interest grid
Stakeholder classification mapping influence against interest to select engagement strategy: manage closely, keep satisfied, keep informed or monitor.
Stakeholder engagement levels
Five levels used to compare current and desired engagement: unaware, resistant, neutral, supportive and leading.
Communication channel formula
For n stakeholders the number of possible two-way channels is n(n−1)/2, so channel complexity grows much faster than headcount.
Communication model elements
Sender, encoding, medium, decoding, receiver and noise; feedback and acknowledgement confirm that the message was understood as intended.
Scope baseline components
The approved scope statement, the work breakdown structure and the WBS dictionary, used as the reference for measuring and controlling change.
WBS 100% rule
The WBS captures all work in the parent scope and nothing more; decomposition must not omit or add work at any level.
MoSCoW prioritisation
Requirements ranked as Must have, Should have, Could have or Won't have this time; Must-haves must remain deliverable if effort is cut.
Requirements traceability matrix
A table linking each requirement to its source, design, build component, test case and acceptance criteria in both directions.
Scope creep versus gold plating
Scope creep is uncontrolled addition of requested work without change control; gold plating is unrequested extra scope added by the delivery team.
Critical path
The longest path through the schedule network; it sets the shortest achievable project duration and carries zero total float.
Total float formula
Total float equals late finish minus early finish, or late start minus early start; it is the time an activity can slip without delaying the project.
PERT expected duration
Three-point estimate calculated as (optimistic + 4 × most likely + pessimistic) divided by 6, weighting the most likely value most heavily.
Crashing versus fast tracking
Crashing adds resources to critical-path work, usually raising cost; fast tracking overlaps activities that were sequential, raising risk.
Resource levelling
Resolving resource over-allocation, often by delaying work within available float; it may extend the schedule where float is insufficient.
Cost baseline definition
The approved, time-phased project budget excluding management reserve; it is the benchmark against which cost performance is measured.
Contingency versus management reserve
Contingency reserve covers identified known-unknown risks and sits within the cost baseline; management reserve covers unknown-unknowns above the baseline.
Cost variance formula
Cost variance equals earned value minus actual cost; a negative result indicates spending more than the value of work performed.
Cost performance index
CPI equals earned value divided by actual cost; a value below 1.0 means each unit of work is costing more than planned.
Estimate at completion forecast
EAC equals BAC divided by CPI when current cost performance is expected to continue; ETC is then EAC minus actual cost.
Residual and secondary risk
Residual risk remains after a response is applied; secondary risk is a new risk created by implementing the response itself.
Expected monetary value
EMV equals probability multiplied by financial impact; summing EMVs across identified risks helps size the contingency reserve.
Threat response strategies
Avoid, transfer, mitigate and accept, with escalation where the risk sits outside the project's authority; each response needs an owner.
Risk appetite versus tolerance
Risk appetite is how much risk the organisation is willing to seek or retain; tolerance is the measurable variation accepted around objectives.
Cost of quality
Total cost of conformance (prevention and appraisal) plus cost of non-conformance (internal and external failure, rework, warranty).
Benefit profile contents
A record of each benefit's description, owner, baseline and target value, measurement method, timing and dependencies on other benefits.
Fixed-price contract risk
The seller bears cost-overrun risk because the price is agreed in advance; buyers usually pay a premium for that risk transfer.
Contract variation control
No work outside the agreed contract scope should proceed without a formal instruction or variation confirmed in writing and priced.
Tolerance definition
The permissible deviation from the agreed plan before the matter must be escalated to the next level of authority.
Change control process
Request, log, assess impact on scope, cost, schedule, risk and quality, decide at the authorised level, implement, verify and close.
Assurance versus review
Assurance is independent scrutiny giving confidence to the sponsor and board; management reviews are internal checks by the delivery team.
Conflict of interest duty
Declare any personal or financial interest that could bias judgement, and withdraw from the related decision or evaluation.