SPM PQS 5227: Scope and requirements management

SPM PQS 5227 · Work through your exam, one topic at a time.

All guide sections

Scope and requirements management

Scope and requirements management

This domain tests how scope is defined, decomposed, baselined and protected.

Core rules

  • Capture requirements through interviews, workshops, observation and document analysis; separate functional from non-functional requirements.
  • Prioritise with MoSCoW (must, should, could, won't) or similar; musts define the minimum usable subset.
  • Build a WBS that is deliverable-oriented; the lowest level is a work package with acceptance criteria.
  • Establish a scope baseline (scope statement, WBS, WBS dictionary) and control changes through integrated change control.
  • Trace requirements to design, build and test to prevent omission.

Worked example

A CRM replacement has a must requirement: 'sales staff can see customer history in one screen'. A should requirement is: 'manager dashboard refreshes hourly'. The WBS decomposes 'customer history view' into data model, API, UI and test work packages. A later request for a mobile app is not in the baseline; it goes to change control with impact on schedule and cost. Reasoning: priority and traceability let the team protect the minimum scope while assessing additions formally.

Traps

  • Confusing scope creep with legitimate change: both need control, but creep is uncontrolled.
  • Writing requirements as solutions ('use PostgreSQL') rather than needs.
  • Missing non-functional requirements such as performance, security or accessibility.
  • No acceptance criteria, so 'done' is disputed.
  • Gold-plating by the team without approval.