SPM PQS 5227: Cost estimating and budget control

SPM PQS 5227 · Work through your exam, one topic at a time.

All guide sections

Cost estimating and budget control

Cost estimating and budget control

This domain tests estimating methods, contingency, and earned value management.

Core rules

  • Estimating methods: analogous (top-down, historical), parametric (unit rates), bottom-up (WBS-based), three-point (optimistic, most likely, pessimistic).
  • Budget = cost baseline + contingency for identified risks + management reserve for unknown unknowns, controlled by the sponsor.
  • Earned value: PV is planned value, EV is earned value, AC is actual cost. CV = EV - AC; SV = EV - PV; CPI = EV/AC; SPI = EV/PV.
  • Forecast EAC = BAC/CPI when current performance continues; ETC = EAC - AC.
  • Control changes to the cost baseline through change control.

Worked example

BAC is 100k. At month 4, PV = 40k, EV = 36k and AC = 39k. CV = -3k, so over budget; SV = -4k, so behind schedule; CPI = 0.923; SPI = 0.9. EAC = 100/0.923 = 108.3k. Reasoning: negative variances show poor performance, and EAC assumes the same efficiency continues. Management reserve is not used unless the sponsor approves.

Traps

  • Mixing contingency and management reserve, or letting the project manager spend reserve freely.
  • Using SPI on a critical-path activity as if it predicts completion.
  • Forgetting that EV must be based on accepted deliverables, not effort.
  • Re-baselining without authority to hide overruns.
  • Ignoring escalation and currency in estimates.