SPM PQS 5227: Risk and opportunity management

SPM PQS 5227 · Work through your exam, one topic at a time.

All guide sections

Risk and opportunity management

Risk and opportunity management

This domain tests a disciplined risk process that includes threats and opportunities.

Core rules

  • Process: identify, analyse probability and impact, plan responses, implement, monitor and review.
  • Threat responses: avoid, reduce, transfer, accept. Opportunity responses: exploit, enhance, share, accept.
  • Record in a risk register: cause, event, effect, owner, rating, response and residual risk.
  • Distinguish risk (uncertain future) from issue (already happened).
  • Risk appetite and tolerance are set by governance; escalate above tolerance.

Worked example

A supplier may miss a delivery date. Probability is 4/5 and impact is 4/5, giving a score of 16 (high). The response transfers part of the risk through a liquidated-damages clause and reduces it by qualifying a second supplier. Residual score is 8 (medium). The owner is the procurement lead. Reasoning: response selection depends on appetite and cost-effectiveness; transferring does not eliminate the risk.

Traps

  • Treating opportunities as threats with negative responses.
  • Assigning a risk owner who has no authority.
  • Confusing cause and effect in the register.
  • Ignoring secondary risks created by the response.
  • Leaving risks un-reviewed at stage gates.