SPM PQS 5227: Quality and benefits management

SPM PQS 5227 · Work through your exam, one topic at a time.

All guide sections

Quality and benefits management

Quality and benefits management

This domain tests quality planning, assurance, control and benefit realisation.

Core rules

  • Quality planning defines standards and acceptance criteria; quality assurance checks processes are followed; quality control inspects outputs against criteria.
  • Prevention usually costs less than correction; use inspection, testing and sampling in control.
  • Benefits are measurable improvements for stakeholders; map each to an owner, metric, baseline and realisation date.
  • Benefits may accrue after the project closes; the programme or business owns realisation.
  • Record dis-benefits and dependencies between benefits, and review benefits at gate reviews.

Worked example

A training project aims to cut invoice error rate from 8% to 3% within six months. Metric: error rate per 1,000 invoices. Baseline: 8%. Owner: finance operations manager. The project delivers training as an output; the benefit depends on staff applying it as an outcome. Reasoning: the benefit is not 'training delivered' but the measured error reduction.

Traps

  • Calling delivery of outputs a benefit.
  • Confusing quality assurance with quality control.
  • No baseline or owner for benefits.
  • Ignoring dis-benefits and unintended consequences.
  • Assuming benefits appear automatically at go-live.