Quick reference

Health, Safety and Site Practice

  • Personal protective equipment (PPE) hierarchy on site: helmet, safety boots, high-visibility vest, eye protection, hearing protection, gloves, dust mask; PPE is the last line of defence after elimination and engineering controls.

  • Scaffold rules: working platform fully boarded, minimum 600 mm wide, toe boards at least 150 mm high, guardrails at 1 m and 0.5 m, tied to the structure, inspected before first use and at least every 7 days.

  • Excavation safety: support or batter sides of trenches deeper than 1.2 m; keep spoil and materials at least 1 m from the edge; provide a ladder within 7.5 m of any worker; test for gas before entry.

  • Ladder angle rule: 1 in 4 (about 75 degrees) - 1 unit out for every 4 units up; ladders extend at least 1 m above the landing point when used for access to a roof.

  • Manual handling limit guide: two-person lift for loads above about 25 kg; keep load close to the body, back straight, lift with legs, no twisting while loaded.

  • Site fire precautions: extinguishers selected by class (water for Class A, foam for flammable liquids, CO2 for electrical), hot-work permit, fire assembly point, escape routes kept clear.

  • Electrical safety on site: 230 V reduced to 110 V centre-tapped earth for portable tools; RCD protection; inspect leads for damage; no trailing cables across walkways.

  • Accident reporting: record all injuries in the accident book; report fatalities, major injuries and dangerous occurrences to the labour/health authority without delay.

  • Housekeeping rules: clear walkways, stack materials safely at a stable height, remove waste daily, and barricade openings and voids immediately.

Quick reference

Building Drawing

  • Scale is drawing size : real size. 1:100 means 1 mm on paper = 100 mm on site; 1:50 shows twice the detail of 1:100; site plans are commonly 1:500 or 1:1250.

  • Standard line types: continuous thick for outlines, continuous thin for dimensions and hatching, dashed for hidden detail, chain dotted for centrelines and grid lines.

  • Orthographic projection: first-angle places the plan below the elevation; third-angle places the plan above the elevation. State the convention used.

  • A floor plan is a horizontal section cut about 1.2 m above floor level, looking down; it shows walls, openings, fittings and room labels.

  • Elevations show external faces with finished ground level (FGL), roof pitch, window and door positions, and levels in metres above a datum.

  • Section drawings show construction build-up (foundation, floor, wall, roof) with hatching codes for concrete, brickwork, timber and insulation.

  • Dimensioning rules: dimension lines outside the drawing, projection lines from the feature, all dimensions in millimetres unless stated, no repeated dimensions.

  • A title block records project name, drawing number, scale, date, revision letter and author; a revision cloud marks changed areas.

  • A schedule of works or door/window schedule lists each item with a type code, size and material so quantities can be taken off the drawing.

Quick reference

Plans and Specifications

  • A specification states quality and workmanship (materials, standards, testing); the drawing states quantity and geometry - both are needed for a complete contract.

  • Types of specification: performance specification (states required outcome), prescriptive specification (states exact product and method), and proprietary specification (names a manufacturer's product).

  • A bill of quantities (BQ) is measured from drawings and specifications; it lists items with description, unit and quantity, and forms the basis for tendering.

  • Units of measurement: cubic metres for excavation and concrete, square metres for plastering and roofing, linear metres for skirting and gutters, number (nr) for doors and fittings.

  • Preliminaries cover site establishment, insurance, supervision, temporary works and water/electricity - items not fixed to the building itself.

  • A contract must identify the parties, scope, price, time for completion, payment terms, retention and dispute procedure.

  • Retention is a percentage (commonly 5–10%) held from each payment as security for defects; released in part at practical completion and the balance after the defects liability period.

  • A variation is a written instruction changing the scope; it must be valued before or after execution and recorded so the contract sum can be adjusted.

  • Approved drawings are stamped and dated; only the latest revision is used on site, and superseded copies are withdrawn to avoid building to outdated information.

Quick reference

Setting Out and Site Preparation

  • The 3-4-5 method sets a right angle: measure 3 units along one line, 4 units along the other, and adjust until the diagonal reads 5 units (Pythagoras: 3² + 4² = 5²).

  • Profile boards are set beyond the excavation line and carry nails marking wall centre lines, faces and foundation width; strings stretched between profiles guide excavation.

  • The building line is fixed from the site boundary or a permanent reference; a datum peg or benchmark transfers level to the works.

  • Levelling with a dumpy or automatic level: set up midway, take a backsight on the benchmark, height of collimation = benchmark level + backsight; reduced level = collimation − foresight.

  • Rise and fall method checks: sum of backsights − sum of foresights = last reduced level − first reduced level.

  • Site clearance sequence: remove vegetation and topsoil, strip and stockpile topsoil separately, demolish obstructions, then reduce level to formation.

  • Setting out a simple rectangular building: establish one corner and two lines, use the 3-4-5 method at each corner, and check both diagonals are equal.

  • Grid lines for larger buildings are set from a baseline and referenced to permanent marks outside the excavation so they survive groundworks.

Quick reference

Foundations and Groundwork

  • Function of a foundation: transfer building loads to the ground without exceeding the soil's safe bearing capacity and without excessive settlement.

  • Strip foundation rule of thumb: width at least three times the wall thickness, thickness at least equal to the projection beyond the wall; depth below ground at least 1 m or below frost line.

  • Trench fill is economic where concrete is cheap and labour dear; it uses more concrete but less excavation and formwork than a strip footing.

  • Pad foundations carry isolated columns; raft foundations spread load over the whole footprint where soil is weak or settlement must be minimised.

  • Pile foundations pass load through weak upper soil to a firm stratum by end bearing or friction; used on soft clay, made ground or where water is present.

  • Concrete grades: a common foundation mix is 1:3:6 (cement:sand:aggregate) or strength class C15/C20; a lean concrete blinding layer about 50 mm is placed under footings.

  • Damp-proof course (DPC) is laid at least 150 mm above external ground level to stop rising damp; damp-proof membrane (DPM) under a ground floor slab.

  • Concrete curing: keep damp for at least 7 days (longer in cold weather); do not strip formwork from sides of foundations before the concrete has gained strength.

Quick reference

Walls, Masonry and Concrete Construction

  • Standard brick dimensions (Southern Africa) are 222 × 106 × 73 mm; with a 10 mm joint a module of 235 × 120 × 85 mm is used for setting out.

  • Bonding rules: a half-brick wall uses stretchers only; a one-brick wall uses English bond (alternate stretcher and header courses) or Flemish bond (header and stretcher alternating in each course).

  • Mortar mix by volume: 1:3 for high-strength/exposed work, 1:4 to 1:6 for general walling; lime or plasticiser improves workability.

  • Cavity walls: two leaves separated by a 50–75 mm cavity, tied with wall ties at about 900 mm horizontally and 450 mm vertically; the cavity is kept clear of mortar droppings.

  • Concrete mix designations: nominal mixes 1:3:6 (C15), 1:2½:3½ (C20), 1:2:4 (C25), 1:1½:3 (C30); water-cement ratio controls strength and durability.

  • Reinforcement: main bars carry tensile force, links/stirrups resist shear and hold bars in position; cover to reinforcement protects against corrosion and fire (typically 25–40 mm).

  • Compaction of concrete by poker vibrator removes air voids; over-vibration causes segregation, under-vibration causes honeycombing.

  • Blockwork uses concrete blocks (commonly 390 × 190 × 190 mm) laid in stretcher bond; hollow blocks may be grouted and reinforced for strength.

Quick reference

Floors

  • Ground floor types: solid concrete slab on hardcore with DPM, or suspended timber floor with sleeper walls, wall plates, joists and floor boards.

  • Hardcore bed is 100–150 mm of compacted broken stone blinded with sand; the DPM laps over the damp-proof course in the wall to form a continuous barrier.

  • Concrete ground slab thickness typically 100–150 mm, often with a mesh fabric reinforcement (e.g. A142) to control cracking.

  • Suspended timber floor joists: size chosen from span tables, spaced at 400 or 600 mm centres, with ventilation openings in the sleeper walls and air bricks in the external wall.

  • Upper floors: timber joists with herringbone strutting between them, or a reinforced concrete slab; trimming joists and trimmers form openings for stairs and chimneys.

  • Floor finishes: screed (sand-cement 1:3 to 1:4) laid 40–75 mm thick over concrete; tiles, timber or vinyl laid over the screed after curing.

  • Sound and thermal insulation: resilient quilt between joists or rigid insulation under screed reduces impact and airborne noise.

  • Slope to falls: bathroom and shower floors fall about 1:60 to 1:80 to a floor gully; external paving falls 1:60 to 1:80 away from the building.

Quick reference

Roofs and Carpentry

  • Roof pitch = rise ÷ run (tangent of the angle); a roof rising 1 m over a 2 m run has a pitch of 1:2, about 26.5 degrees.

  • Common timber sizes: rafters 38 × 150 mm or 50 × 150 mm; ceiling joists 38 × 100 mm; purlins and binders sized from span tables.

  • Roof members: ridge board at the apex, rafters from wall plate to ridge, purlins supporting rafters, ceiling joists tying the feet, collar or binder restraining the rafters.

  • Wall plate is bedded level on the wall and strapped down; it distributes rafter loads and is anchored against wind uplift.

  • Pitch limits: corrugated iron sheets work down to about 5–10 degrees with end laps; concrete or clay tiles need steeper pitches (about 17.5–22.5 degrees minimum depending on type).

  • Roof covering laps: side lap one corrugation, end lap at least 150 mm for sheeting; tiles are double-lapped and fixed with nails or clips.

  • Carpentry joints: halving joint for crossing timbers, mortise and tenon for framing, dovetail for drawer corners, housing joint for shelving, scarf joint for lengthening.

  • Underlay (building paper or membrane) is laid under the covering to shed any wind-driven rain that passes the sheets; eave ventilation keeps the roof space dry.

Quick reference

Building Services (Plumbing, Electrical, Drainage)

  • Cold water supply: mains → water meter → stop valve → storage tank or direct to fittings; a float valve controls tank filling and an overflow pipe discharges safely.

  • Hot water: geyser/cylinder with thermostat set about 55–60 °C to control Legionella; a temperature-and-pressure relief valve and expansion control are required.

  • Pipe materials: copper, PEX and PVC/UPVC for water; UPVC or PVC for soil and waste; falls for drainage pipes are typically 1:40 to 1:60 (about 18–25 mm per metre for 100 mm pipe).

  • Soil stack carries WC discharge and terminates above roof level for ventilation; a trap (P-trap or bottle trap) holds a water seal of about 50 mm to stop sewer gas entering.

  • Drainage: inspection chamber at changes of direction, at junctions and at intervals (commonly every 45 m for straight runs); rodding eyes allow clearing blockages.

  • Electrical circuit basics: Ohm's law V = I × R; power P = V × I; cable size is chosen for current-carrying capacity, volt drop and disconnection time.

  • Earthing and bonding connect exposed metalwork to earth; an RCD (residual current device) trips at 30 mA for socket circuits in wet areas.

  • Lighting circuits are wired in loop-in or radial configuration; socket circuits are ring or radial; all connections are made in enclosures, never buried in plaster without protection.

Quick reference

Materials

  • Concrete constituents: cement, fine aggregate (sand), coarse aggregate (stone), water, and admixtures; aggregate should be clean, hard and graded.

  • Cement types: ordinary Portland (OPC) for general use, rapid-hardening for early strength, sulphate-resisting for aggressive ground or marine conditions.

  • Water-cement ratio rule: lower ratio gives higher strength and durability; excess water increases workability but reduces strength by about 5% per 0.01 increase in ratio.

  • Timber: softwoods (pine) for general carpentry, hardwoods for joinery and exposed work; timber is seasoned to reduce shrinkage and movement.

  • Timber defects: knots, shakes, splits and sapwood reduce strength; wood-boring insects need treated timber in contact with ground or masonry.

  • Steel reinforcement: high-yield bars (e.g. 8, 10, 12, 16, 20, 25 mm) with ribbed surface for bond; mild steel is used for links.

  • Masonry units: clay bricks (durable, good in wet conditions), calcium silicate bricks, concrete blocks (cheap, good thermal mass, need careful damp protection).

  • Paint systems: primer, undercoat and finish coat; exterior wood needs preservative treatment and a flexible paint to accommodate movement.

Quick reference

Tools and Equipment

  • Setting-out and measuring: steel tape, chalk line, spirit level, plumb bob, dumpy/automatic level and staff, laser level, builder's square.

  • Masonry tools: bricklayer's trowel, bolster and club hammer for cutting, cold chisel, pointing trowel, jointing/ironing tool, brick line and corner blocks.

  • Carpentry hand tools: claw hammer, saws (rip, crosscut, tenon), chisels, plane, try square, marking gauge, brace and bits.

  • Power tools: circular saw, jigsaw, hammer drill, angle grinder, concrete mixer, poker vibrator, plate compactor; each requires guarding, correct blade/bit, and PPE.

  • Concrete equipment: mixer (drum or pan), wheelbarrow, vibrator, screed board, float and trowel; mix by volume on site, measure accurately.

  • Earthmoving: spade, pick, crowbar, wheelbarrow, plate compactor for hardcore; excavator for bulk work with banksman control.

  • Tool maintenance: keep cutting edges sharp, oil metal parts, store tools dry, inspect electrical leads and plugs before use, and never use a damaged tool.

  • Safety with power tools: use the correct voltage (110 V on site), check guards, do not remove the earth pin, and switch off before changing blades or bits.

Quick reference

Finishing

  • Plaster mix: 1:3 to 1:4 sand-cement for backing coats, with a finishing coat of finer mix or gypsum plaster; thickness about 10–15 mm in two coats.

  • Rendering: external sand-cement render 1:4 with a water-repellent additive; provide bell-mouth drip at the base and movement joints in large areas.

  • Screeds: sand-cement screed 1:3 to 1:4, 40–75 mm thick; cure and allow to dry before laying tiles or vinyl, and check moisture before covering.

  • Tiling: bed tiles on adhesive or mortar with even joints; floor falls to gully in wet areas; grout after adhesive has set; use spacers for consistent joints.

  • Painting sequence: prepare surface (clean, fill, sand), prime, undercoat, then two finish coats; allow drying time between coats and protect from dust.

  • Wood finishing: sand with progressively finer paper, apply wood filler, stain, then varnish or seal; exterior wood needs a preservative base.

  • Suspended ceilings: grid of main runners and cross tees at 600 mm centres, tiles laid in, level checked with a laser or string line.

  • Defects in plaster: crazing from too-rich mix, shrinkage cracks from rapid drying, and blowouts from unsound background - cure causes, not just symptoms.

Quick reference

Maintenance and Repair

  • Maintenance types: planned preventive (scheduled inspections and servicing), reactive (repair after failure), and condition-based (act on inspection findings).

  • Damp diagnosis: rising damp (no DPC or bridged DPC, tide mark at about 1 m), penetrating damp (defective render, joints or roof), condensation (cold surfaces, poor ventilation).

  • Crack classification: hairline cracks (settlement or shrinkage) are usually cosmetic; cracks wider than about 5 mm or stepped diagonal cracks in masonry indicate structural movement and need investigation.

  • Roof maintenance: clear gutters and downpipes of leaves, replace slipped or broken tiles, check flashings at chimney and wall junctions, re-fix loose sheeting.

  • Concrete repair: remove loose and carbonated concrete, clean reinforcement, apply rust inhibitor, then patch with repair mortar or polymer-modified concrete.

  • Timber repair: cut out rot to sound wood, treat with preservative, splice or scarf new timber, and eliminate the water source.

  • Repointing: rake out defective mortar to about twice the joint width, wet the joint, and press in new mortar of similar strength to the original.

  • Plumbing repair: isolate the supply at the stop valve first, drain the pipe, replace washers or fittings, then test under pressure before boxing in.

Quick reference

Entrepreneurship

  • A business plan for a building contractor covers the market, services offered, pricing method, cash-flow forecast, equipment list, staffing and legal registration.

  • Cost categories: fixed costs (rent, insurance, licences) do not change with output; variable costs (materials, labour, fuel) change with each job.

  • Break-even point in units = fixed costs ÷ (selling price per unit − variable cost per unit).

  • Mark-up is added to cost to give price: price = cost × (1 + mark-up %); margin is profit as a percentage of price, not cost.

  • Cash flow is the timing of money in and out; a profitable job can still fail a business if payments arrive after wages and material bills are due.

  • Tendering: read the documents, take off quantities, price labour, material, plant and overheads, add risk and profit, then submit on time in the required format.

  • Record keeping: keep invoices, delivery notes, wage sheets and a job file for each contract; these support claims, tax returns and dispute resolution.

  • Client relations: confirm instructions in writing, agree variations before doing the work, and keep a site diary recording weather, labour and delays.

Quick reference

Costing and Project Management

  • Labour constant is hours per unit of work; labour cost = quantity × labour constant × hourly rate.

  • Material cost = quantity × unit rate, plus a wastage allowance (commonly 5–10% for bricks and tiles, less for sheet materials).

  • Unit rates for masonry: bricks per square metre of half-brick wall = 1 ÷ (module length × module height) ≈ 60 bricks/m² for a 222 × 106 × 73 mm brick with 10 mm joints.

  • Mortar volume for brickwork is roughly 0.02–0.03 m³ per m² of half-brick wall; order sand and cement from the measured wall area.

  • Programme tools: bar chart (Gantt) shows activities against time; critical path method (CPM) identifies the longest sequence of dependent activities that sets the project duration.

  • Float (slack) is the time an activity can be delayed without delaying the project; critical activities have zero float.

  • Valuation and payment: measure work executed at intervals, apply contract rates, deduct retention, and issue an interim certificate for payment.

  • Cost control: compare actual cost against budget for each work package; investigate variances in labour hours, material wastage and plant standing time.

  • Delay and disruption: record the event, notify the client within the contract period, and quantify the effect on time and cost separately.