NSSCO Building Studies 6186 study materials
NSSCO Building Studies 6186 study resources

NSSCO Building Studies 6186: Entrepreneurship, Costing and Project Management

NSSCO Building Studies 6186 · Work through your exam, one topic at a time.

All guide sections

Entrepreneurship, Costing and Project Management

What the domain tests

Entrepreneurship, Costing and Project Management tests estimating, tendering, bill of quantities, preliminaries, overheads, profit, cash flow, programmes, contracts and VAT.

Core rules

  • Direct costs include labour, materials, plant and subcontractors.
  • Preliminaries cover site establishment, supervision, insurance, temporary works and similar project-wide costs.
  • Overheads are business costs not tied to one project; profit is the return for risk and enterprise; contingency covers the unexpected.
  • Build the tender price in a clear order and add VAT where applicable. Namibian VAT is 15%.
  • A programme may use a Gantt chart or critical path; cash flow must match payments and expenses.
  • Understand payment certificates, retention and contract instructions.

Worked example

Direct cost = 250,000. Preliminaries 10% = 25,000, giving 275,000. Overheads 8% = 22,000, giving 297,000. Profit 12% = 35,640, giving 332,640. Contingency 5% = 16,632, giving 349,272. VAT 15% = 52,391, giving a tender price of 401,663. Reasoning: percentages are applied sequentially to the increasing base, with VAT last.

Traps

  • Confusing markup with margin.
  • Forgetting preliminaries and overheads.
  • Adding VAT before profit and contingency.
  • Ignoring cash-flow timing.
  • Pricing from an old or incomplete bill of quantities.