Fast-Track Library and the 14% Overrun

AARE · Put your knowledge to work in context.

All case studies

Fast-Track Library and the 14% Overrun

A library board has a $12.0 million total construction budget for a new 45,000 sf library. The architect is at 60% design development and has just received a contractor’s estimate of $13.7 million. The board wants to use construction manager at risk (CM at risk) and asks the architect to help solicit a guaranteed maximum price (GMP) immediately, before CDs are complete. The architect’s fee is 6% of construction cost. The board also asks the architect to “find $1.7 million in value engineering” without changing the program, and suggests the architect reduce the contingency in the estimate to make the budget appear balanced. The project is in a competitive market with 8% annual escalation.

1. Evaluate the proposed delivery method and timing of the GMP. What should the architect recommend?

Read the worked answer

CM at risk can be appropriate, but a GMP taken at 60% DD is premature. At 60% DD, the documents lack enough detail for a reliable GMP; the contractor would either add a large contingency or exclude scope, and the owner would get false comfort. The architect should recommend bringing the CM on for preconstruction services now, but setting the GMP after 90–100% CDs, with a shared contingency and a clear allowance schedule. If the board needs an earlier cost ceiling, a design-build competition with bridged criteria is another option, but it shifts design control. The 8% escalation must be included explicitly. The architect should explain that the $13.7 million estimate is a design-phase estimate, not a bid, and that value engineering should be a structured process with program priorities, not a last-minute cut list.

2. What is the architect’s scope and fee position if the board demands redesign to hit $12.0 million?

Read the worked answer

Redesign to meet a reduced budget is additional services unless the original agreement included a stated budget and a defined number of redesign cycles. The architect should review the contract’s budget provision. If the owner changes the program or requires repeated value-engineering cycles beyond the agreed scope, the architect should issue a written additional-services proposal with hours and reimbursables. The 6% fee is based on construction cost; if construction cost drops, the fee may drop unless the contract has a minimum or a cost-of-work adjustment. The architect should not absorb unlimited redesign to protect the fee. A practical approach is a defined VE workshop, owner decisions on program reductions, and a fixed additional-services fee for redesign. The architect should also warn that cutting contingency to balance the budget transfers risk to the owner and contractor.

3. The board asks the architect to certify that the project can be built for $12.0 million. How should the architect respond ethically and professionally?

Read the worked answer

The architect cannot certify a construction cost that the current design and market data do not support. Certification would misrepresent the estimate and could harm the owner and contractors. The architect should state clearly that the $13.7 million estimate is the best available information, identify the assumptions and escalation, and explain what would be required to reach $12.0 million: program reduction, site changes, phased construction, or additional funding. The architect may provide a professional opinion of probable cost, but not a guarantee. If the owner insists on a budget number, the architect should document the request and the architect’s response. The ethical duty is to give the owner accurate information, even when it is unwelcome, and to avoid a false budget that leads to bid failure or unsafe value engineering.