It is Tuesday, 7:55 a.m. Six requests are in your queue and you are the only maintenance tech on site until 3 p.m.

  • Unit 318: water dripping from the bathroom ceiling light; the resident has turned the light off.
  • Unit 214: A/C not cooling. The resident is 82 years old with COPD; forecast high is 96°F, heat index 104.
  • Unit 108: kitchen faucet drips; the request was submitted 15 days ago and has been rescheduled twice.
  • Building B rear stairwell: the top handrail bracket has pulled loose from the wall; this stair is the only egress from floors 3 and 4.
  • Unit 305: an outlet "popped and sparked" when a vacuum was plugged in; the outlet is now dead.
  • Unit 402: resident wants the vertical blinds replaced because she dislikes the color.

You hold one licensed electrician slot at 1:00 p.m. and one plumber slot at 4:00 p.m.

1. Rank all six requests and state the first action you take at each stop before any repair begins.

Read the worked answer

Ranking logic: imminent danger to people first, then active property damage, then habitability, then routine, then non-maintenance requests.

  1. Unit 318 (water at a ceiling light). Water plus energized wiring is a shock and fire risk and the leak is active. First action: shut off the bathroom circuit at the panel, kill the water at the unit or riser if the drip is steady, place a bucket and poly sheeting, and meter the ceiling to map the wet area. Then find the source above before touching drywall.
  2. Unit 305 (sparking outlet). A spark-and-die event is a candidate arcing fault. First action: de-energize that circuit at the panel, tag it, and remove the device from service. Do not re-energize to "see if it works."
  3. Unit 214 (no A/C, vulnerable resident). Heat illness risk is a medical priority even though nothing is being damaged. First action: verify the unit is actually running, then set up interim cooling (portable unit, fan, access to a cooled common room) and give the resident a check-back time.
  4. Building B stairwell (loose handrail). Egress component and a fall hazard for everyone in the building. First action: block or cone the top flight, or make a temporary secure with clamps/lag bolts, and post a notice until it is properly anchored into framing.
  5. Unit 108 (dripping faucet). Habitability nuisance with low damage potential, but it is overdue. First action: confirm the leak is at the spout and not under the cabinet, then schedule.
  6. Unit 402 (blinds color). Not a maintenance defect. First action: route to management as a cosmetic/upgrade request and reply to the resident the same day.

Documentation for every stop: arrival and departure time, what you found, what you de-energized or isolated, and what remains open. A 15-day-old work order that has slipped twice is a service-record problem as much as a plumbing problem.

2. Write the call you make to the resident in Unit 214 and describe the interim mitigation you will arrange.

Read the worked answer

Call script (under 90 seconds):

"Mrs. ___, this is ___ from maintenance. I have your A/C work order and I take the heat seriously given your breathing condition. I can't be in your unit before noon because I'm handling a water leak into a light fixture and an outlet that arced this morning, but here is what I'm doing right now: I'm bringing you a portable cooling unit and a fan within the next 30 minutes, and I'll show you how to keep the blinds closed on the sunny side and run the fan to pull air through. Please drink water and stay in the coolest room. If you feel dizzy, short of breath, or stop sweating, call 911 first and then call me. I will knock on your door at ___ and again at ___ to check on you, and if the repair isn't done by then I will tell you exactly when it will be."

Interim mitigation: portable A/C or at minimum a box fan with a window cracked on the shaded side, access to a cooled common room, a written check-back schedule, and a welfare check logged in the file.

Why this framing: you are not promising a time you cannot keep, you are giving the resident a concrete action and a human checkpoint, and you are creating a record that shows the vulnerability was recognized. If the unit truly cannot be cooled, that becomes a habitability decision for management, and your job is to escalate it in writing today, not to absorb the risk silently.

3. Which requests go to the 1:00 p.m. electrician and the 4:00 p.m. plumber, what scope do you hand each vendor, and what do you do about Unit 402?

Read the worked answer

Electrician (1:00 p.m.): assign both Unit 305 and Unit 318.

  • Unit 305: investigate the arcing outlet, inspect the full circuit for damaged conductors and back-stabbed connections, replace devices, and megger or at minimum visually inspect the run.
  • Unit 318: once the water source is controlled, open the ceiling, dry the cavity, and evaluate the fixture box and conductors for water intrusion before re-energizing.
  • Same trade, same visit - batching these two saves the slot for a real emergency later in the week.

Plumber (4:00 p.m.): Unit 108. It is overdue and low-risk, but it is the only plumbing item that genuinely needs a licensed trade today. Scope: rebuild or replace the faucet cartridge, inspect the stop valves and supply lines, and check under the cabinet for swelling.

Unit 402: do not send a trade and do not order blinds. Reply in writing the same day, acknowledge the request, explain that the blinds are in serviceable condition and replacement for appearance is a management decision, and log the request as a cosmetic upgrade. Send it to the property manager with a recommendation. Ignoring it is what turns a color complaint into a fair-housing or retaliation allegation later.

Principle: vendors are a scarce resource. Group by trade, send them to safety and habitability work, and keep cosmetic decisions out of the maintenance queue where they compete with real hazards.