NABCEP ESIP study materials
NABCEP ESIP study resources

NABCEP ESIP flashcards

NABCEP ESIP · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Usable energy
Nameplate energy multiplied by allowable depth of discharge and by the end-of-life capacity retention factor; this is the energy the system can actually deliver at the end of its warranty period.
Round-trip efficiency
Ratio of AC energy discharged to AC energy required to recharge over a full cycle, including inverter, transformer, and auxiliary losses. Design loads must be grossed up by its inverse.
C-rate
Charge or discharge power in kW divided by energy capacity in kWh. A 100 kWh pack discharged at 50 kW operates at C/2, a two-hour rate.
Depth of discharge
Fraction of rated capacity removed during a discharge cycle. Deeper cycles yield more usable energy per cycle but generally reduce cycle life.
State of charge
Remaining energy in the battery expressed as a percentage of current usable capacity. It is an estimate derived from voltage, current integration, and BMS algorithms.
Continuous load factor
Code rule requiring conductors and overcurrent devices serving continuous loads to be sized at 125% of the continuous current, applied to inverter AC output and battery DC circuits.
Voltage window check
Verification that series string voltage stays within inverter battery input limits from full charge to low-voltage cutoff, accounting for cold-temperature voltage rise and line drop.
DC short-circuit current rating
Maximum fault current the battery and its protection can safely interrupt at system voltage. Disconnects and fuses must have an interrupting rating at least equal to it.
Autonomy days
Number of days a standalone storage system must serve the load without recharge. Nameplate energy equals daily load times autonomy days divided by usable-energy factor.
Torque verification
Tightening DC lugs and busbar hardware to the manufacturer's published value with a calibrated wrench, then recording values. Loose terminations cause heating and fire risk.
Polarity check
Confirming positive and negative conductors are correct at each string and at the inverter before energizing, preventing reverse-current damage on shared DC buses.
Shielded communication cable
Twisted-pair cable with a shield used for CAN or RS-485 links between BMS, inverter, and gateway. Shield is terminated at one end to prevent ground loops.
Working space clearance
Code-required depth of accessible and illuminated space in front of electrical equipment, kept clear of battery cabinets and other obstructions for safe servicing.
Equipment grounding conductor
Conductor bonding non-current-carrying metal parts of racks, enclosures, and cabinets to the grounding system, establishing a low-impedance fault return path.
Insulation resistance test
Measurement of DC circuit insulation to ground before energizing, typically required to exceed one megohm at the manufacturer's specified test voltage.
Low-temperature charging limit
Minimum cell temperature at which charging is permitted. Charging below it causes lithium plating, permanent capacity loss, and possible internal short circuits.
Rapid shutdown
Function that reduces DC conductor voltage at the array or battery to a safe level for responders. Required locations and labeling depend on code edition and jurisdiction.
Commissioning sequence
Ordered process: inspection, torque and insulation checks, firmware verification, then functional and performance testing, with every result recorded as the baseline.
Closed-transition transfer
Brief paralleling of inverter output with the grid during transfer so the load sees no interruption. Testing confirms no unintended export and correct anti-islanding behavior.
Capacity performance test
Controlled discharge at a defined C-rate to cutoff, measuring delivered AC energy and round-trip efficiency, then comparing results with expected usable energy.
Voltage and frequency trip settings
Protection thresholds and clearing times programmed per the applicable interconnection standard, verified during commissioning along with ride-through and reconnect delays.
Communications chain test
End-to-end verification that BMS, inverter, gateway, and monitoring portal exchange data, with telemetry, alarms, and state-of-charge readings matching local values.
Commissioning baseline record
Documented torque logs, insulation values, firmware versions, setpoints, and test results captured at startup, used later to detect degradation or unauthorized changes.
Emergency shutdown test
Verification that actuating the emergency stop opens battery contactors, disables the inverter, and places the system in a safe state without relying on software alone.
Top-of-charge balancing
Holding cells at full charge so the BMS can equalize series cell voltages. Persistent imbalance at commissioning predicts reduced capacity and warranty claims.
State of health
Current capacity divided by initial capacity, expressed as a percentage. Warranties commonly guarantee 70 to 80 percent retained energy at a stated cycle count.
Calendar aging
Capacity and resistance degradation that occurs over time regardless of cycling, accelerated by elevated average cell temperature and high state of charge.
Cell voltage spread
Difference between highest and lowest series cell voltages under the same conditions. A widening spread indicates imbalance or an incipient cell failure.
Thermal management inspection
Scheduled check that fans, coolant loops, filters, and temperature sensors operate within specification, keeping cells in the range that preserves design life.
Alarm log trending
Reviewing historical fault and warning records for patterns such as repeated over-temperature or over-voltage trips, which point to airflow, setpoint, or degradation problems.
DC arc flash hazard
Danger of sustained DC arcing from energized battery circuits even when the AC side is off. Lockout/tagout and DC-rated PPE are required for maintenance work.
Firmware change log
Record of version, date, and reason for each software or setpoint update. Undocumented changes invalidate performance baselines and may void manufacturer warranties.