NABCEP ESIP study plan
NABCEP ESIP · Give each week a clear focus.
8 weeks · About 6 hours per week
Design of Energy Storage (BESS) Systems
Calculate daily and peak energy requirements from a load profile and size usable BESS capacity after applying depth-of-discharge and round-trip efficiency derates
Distinguish power (kW) sizing from energy (kWh) sizing and identify which loads drive each in a given scenario
Map the major BESS subsystems (cells, modules, racks, BMS, PCS/inverter, transformer, HVAC, fire suppression, controls) and state the function of each
Identify the primary NEC and code articles governing ESS siting, sizing, and labeling and note which edition applies in your jurisdiction
Your checkpoint
A one-page sizing worksheet showing load profile inputs, DoD/efficiency derates, and the resulting kW/kWh selection with assumptions listed
Design of Energy Storage (BESS) Systems
Compare lithium-ion chemistries (LFP vs NMC) on thermal stability, cycle life, energy density, and typical application fit
Evaluate siting constraints including clearance to walls, egress paths, flood zones, temperature exposure, and ventilation requirements
Size conductor, overcurrent protection, and disconnect ratings for a DC-to-AC BESS interconnection
Explain how inverter clipping, AC coupling vs DC coupling, and backfeed rules affect design decisions
Your checkpoint
A design review memo for a hypothetical 250 kW / 500 kWh commercial BESS covering chemistry choice, siting, and electrical ratings with justifications
Installation of Energy Storage (BESS) Systems
Sequence a BESS installation from site prep and anchoring through rack placement, DC cabling, AC interconnection, and controls wiring
Apply torque specifications and manufacturer sequence requirements for DC busbar and terminal connections
Identify PPE, arc-flash boundaries, and lockout/tagout steps required before energizing any circuit
Specify handling and lifting requirements for battery modules including weight limits and two-person or mechanical lift rules
Your checkpoint
A step-by-step installation sequence checklist for a containerized or cabinet BESS with hold points and inspection gates marked
Installation of Energy Storage (BESS) Systems & Commissioning of Energy Storage (BESS) Systems
Write the pre-commissioning inspection list covering grounding, clearances, labeling, ventilation, and fire detection
Verify polarity, insulation resistance, and continuity checks before first energization
Perform and document BMS cell voltage and temperature baseline readings at the module and rack level
Explain the purpose of a functional performance test and how to record pass/fail criteria against the design intent
Your checkpoint
A completed mock commissioning test pack with pre-energization checks, baseline BMS readings, and pass/fail sign-off lines
Commissioning of Energy Storage (BESS) Systems
Execute a controlled energization and verify inverter/PCS startup, grid synchronization, and communication to the monitoring platform
Test protective functions including over/under voltage, over/under frequency, and anti-islanding response and record trip settings
Validate SOC calibration, charge/discharge setpoints, and demand-response or peak-shaving control logic
Compile an as-built and O&M handoff package including schematics, setpoint records, and warranty documents
Your checkpoint
A commissioning report template populated with test results, trip settings, and control setpoints for a sample system
Operations & Maintenance of Energy Storage (BESS) Systems
Build a preventive maintenance schedule keyed to manufacturer intervals for thermal management, filters, torque checks, and firmware updates
Interpret BMS and inverter alarms and classify them by severity and required response time
Diagnose common capacity-fade and imbalance causes using trend data and cell-level voltage spread
Plan a safe response to a thermal event including isolation, ventilation, and fire service coordination
Your checkpoint
A 12-month preventive maintenance calendar plus an alarm-response decision table with severity tiers
Operations & Maintenance of Energy Storage (BESS) Systems & Design of Energy Storage (BESS) Systems
Analyze a year of performance data to compute round-trip efficiency, availability, and capacity retention against warranty thresholds
Identify when measured degradation triggers a warranty claim and assemble the supporting evidence
Produce a corrective action for a recurring fault using root-cause analysis rather than part replacement alone
Re-check design assumptions against as-operated data and flag sizing or thermal gaps
Your checkpoint
A performance analysis report with efficiency, availability, and degradation metrics plus one root-cause finding and corrective action
Design of Energy Storage (BESS) Systems & Installation of Energy Storage (BESS) Systems & Commissioning of Energy Storage (BESS) Systems & Operations & Maintenance of Energy Storage (BESS) Systems
Complete timed practice sets across all four domains and score each domain separately to find weak areas
Review missed items by tracing the underlying code article, calculation, or procedure rather than memorizing the answer
Rehearse explaining a full BESS lifecycle from design through O&M in a concise walkthrough
Confirm exam-day logistics including allowed references, calculator policy, and appointment scheduling
Your checkpoint
A scored full-length practice result with a per-domain breakdown and a written list of the three weakest areas plus a remediation plan
Milestones
Week 2: Can size a BESS from a load profile and justify chemistry, siting, and electrical ratings without notes
Week 4: Installation checklist and pre-commissioning test pack are complete enough that another technician could execute them
Week 6: Can classify any BMS or inverter alarm by severity and name the correct first response
Week 8: Practice scores show no domain below 70 percent and the weakest-area remediation plan is written