NABCEP PV study materials
NABCEP PV study resources

NABCEP PV flashcards

NABCEP PV · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Solar window
The unobstructed period, typically 9 a.m. to 3 p.m. solar time, when shade-free sun is most valuable; design arrays to avoid shading in this window.
Magnetic declination
The angle between true north and magnetic north at a location; correct compass readings by this angle when setting array azimuth for design.
Latitude tilt rule
For year-round output, set fixed-tilt arrays near site latitude; latitude minus 15 degrees favors summer production, while latitude plus 15 degrees favors winter production.
Roof load allowance
Rooftop PV typically adds two to four pounds per square foot for rack-mounted systems; confirm structural capacity and use ballasted or elevated racking when required.
STC rating
Standard Test Conditions use 1000 W/m² irradiance, 25°C cell temperature, and AM 1.5 spectrum; module nameplate power is rated at STC.
Cold-temperature Voc
Open-circuit voltage increases as cell temperature falls; calculate maximum string voltage at the coldest expected cell temperature to remain below equipment voltage ratings.
DC/AC ratio
The ratio of array DC nameplate power to inverter AC output; typical designs fall between 1.0 and 1.3, with clipping accepted when energy gain exceeds losses.
Voltage drop target
A design limit for conductor voltage loss, commonly about 2 percent on DC circuits and 3 percent on AC circuits, for a total near 5 percent.
Clamping zone
The manufacturer-approved area on a module frame where mounting clamps may be placed; clamping outside these zones can damage the module or void warranty.
Flashing
A weatherproofing detail that seals roof penetrations, typically using flashed standoffs and sealant; sealant alone is not a primary waterproofing method.
Equipment grounding conductor
The conductor that bonds non-current-carrying metal parts together and to the grounding electrode; size it per NEC Table 250.122 based on the overcurrent device rating.
Conduit expansion fitting
A fitting that permits conduit movement during thermal expansion and contraction; it prevents buckling or pulled terminations on long straight runs.
Insulation resistance test
A commissioning test that applies high DC voltage between conductors and ground; a reading of at least one megohm generally indicates acceptable insulation.
I-V curve trace
A plot of current versus voltage for a module or string; comparing the measured curve with the expected shape reveals shading, mismatch, or bypass-diode failures.
Anti-islanding test
A commissioning check confirming that the inverter stops exporting power when the utility grid is disconnected, protecting line workers during outages.
As-built documentation
Final drawings, equipment serial numbers, test results, and labeling records delivered at commissioning; they support maintenance, warranty claims, and future inspections.
Thermal imaging
Infrared scanning of modules and connections under load; hotspots reveal cell cracks, failed bypass diodes, or loose terminations that reduce production.
Ground fault
An unintended current path from a PV conductor to ground; isolate the fault with an insulation tester and do not re-energize until repaired.
Performance ratio
Actual energy output divided by theoretical output based on irradiance and nameplate rating; it normalizes production comparisons across weather and site conditions.
String fuse failure
A blown fuse often indicates reverse polarity, a short circuit, or excessive reverse current; compare string currents with a clamp meter before replacing it.
PV live in light
PV modules produce voltage whenever illuminated, so DC conductors remain energized even when the inverter or AC disconnect is off; treat them as live.
Fall protection trigger
OSHA generally requires fall protection when working six feet or more above a lower level; use guardrails, personal fall arrest, or nets.
Lockout tagout
An energy-isolation procedure using locks and tags; on PV systems the AC disconnect stops export, but module-side DC remains energized.
Arc flash PPE
Personal protective equipment rated for the calculated incident energy; PV DC arcs do not self-extinguish, so use insulated tools and appropriate gear.
120 percent rule
An NEC allowance permitting the main breaker plus the PV breaker to total up to 120 percent of the busbar rating in a center-fed panel.
Rapid shutdown
An NEC 690.12 requirement to reduce conductor voltage at the array boundary to a safe level within a specified time for emergency responders.
PV source circuit ampacity
PV source conductors must carry 125 percent of short-circuit current per NEC 690.8, with additional adjustment for temperature and conduit fill.
Interconnection label
A permanent plaque identifying the PV system, disconnect location, and maximum output; required by code and utility for safe operation.
Change order
A written contract amendment describing added or removed work, price, and schedule; obtain customer signature before performing the changed work.
Investment tax credit
A federal tax credit equal to a percentage of eligible PV system costs; verify current rates and eligibility because the schedule changes by year.
Net metering
A utility billing arrangement that credits exported solar energy against consumption; check the tariff for credit rates, caps, and true-up rules.
Workmanship warranty
A contractor guarantee covering installation defects for a stated period, commonly five to ten years; it is separate from manufacturer equipment warranties.