NABCEP PVDS flashcards
NABCEP PVDS · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- STC definition
- Standard Test Conditions: 1000 W/m² irradiance, 25 °C cell temperature, and AM 1.5 spectrum. Module nameplate ratings are given at STC.
- 1.25 × 1.25 factor
- PV source and output circuits use Isc × 1.25 for continuous current, then conductor ampacity must be ≥ 1.25 × that value, giving 1.5625 × Isc total.
- Cold-temperature Voc correction
- Voc at the lowest expected ambient equals Voc(STC) × [1 + βVoc × (Tmin − 25 °C)], where βVoc is negative. Use record low ambient to check maximum system voltage.
- Maximum series fuse rating
- The largest overcurrent device the module manufacturer lists for string protection. The string OCPD must be at least 1.25 × Isc and no greater than this rating.
- Rapid shutdown threshold
- NEC 690.12 requires conductors within 1 ft of the array to be limited to 30 V within 30 seconds of shutdown initiation, achieved with module-level electronics.
- Inverter AC output current
- Rated AC power divided by nominal AC voltage. The AC output conductor and OCPD must be sized at ≥ 1.25 × this current per NEC 690.9.
- Voltage drop formula
- VD = 2 × L × I × R / 1000 for two-wire circuits, with L in feet and R in ohms per 1000 ft. Keep total system drop typically at or below 2–3 %.
- Equipment grounding conductor sizing
- PV equipment grounding conductors are sized per NEC 250.122 based on the rating of the overcurrent device protecting the circuit.
- 120 % busbar rule
- NEC 705.12(B): the sum of the main breaker and the backfed PV breaker must not exceed 120 % of the panel busbar rating.
- String sizing window
- Minimum string length must keep Vmp above the inverter's MPPT minimum at the hottest expected cell temperature; maximum length must keep cold-corrected Voc below the inverter max DC voltage.
- Wind uplift design pressure
- p = q × (GCp − GCpi) per ASCE 7. Corner and edge roof zones have larger GCp magnitudes, so attachment density must increase there.
- Module clamp zone
- The region along the module frame where the manufacturer permits mounting clamps, typically within one-quarter of the span from each end. Clamping outside it voids the warranty.
- Rail cantilever limit
- The unsupported overhang of rail beyond the last attachment should not exceed one-third of the adjacent span unless the manufacturer's span table allows more.
- Thermal expansion of aluminum
- Aluminum expands about 23 µm per meter per °C. Long rail runs over roughly 24 m need slip joints or expansion gaps to avoid buckling.
- Roof dead load check
- Sum module, racking, and ballast weight and compare to the structural report's allowable dead load, adding snow load per ASCE 7 for the site.
- Firefighter access setback
- IRC and IBC require a clear 36 in (0.91 m) path at the ridge and eave on residential roofs; modules must stay outside these zones.
- Inter-row shading spacing
- On flat roofs, row spacing ≈ module height × (sin tilt / tan solar altitude) evaluated at the winter solstice design hour to prevent inter-row shading.
- Roof penetration sealing
- Penetrations must sit above the water line of the roof course and use EPDM or silicone flashing, or a curb/pitch pan on low-slope roofs.
- Solar window assessment
- Measure the horizon profile at the array azimuth; obstructions above roughly 15–20° elevation in the winter path indicate shading loss needing modeling.
- Solar access percentage
- The share of annual sun-path hours unobstructed at a point, reported by shade tools. Below about 70 % access, relocate or redesign the array.
- Roof remaining life rule
- If the roof covering has less than about 10 years of remaining life, re-roofing before installing PV is the standard recommendation to avoid costly removal later.
- Service panel survey data
- Record busbar rating, main breaker size, available breaker spaces, and service voltage. These drive the 120 % rule and interconnection approval.
- Typical GHI range
- A good US site receives about 4.5–6.0 kWh/m²/day of global horizontal irradiance. Apply tilt and azimuth correction factors to estimate plane-of-array energy.
- Structural survey inputs
- Collect rafter or joist size, spacing, span, and sheathing thickness. A licensed structural engineer reviews when added load exceeds prescriptive code limits.
- Soiling and snow losses
- Local dust, pollen, or agricultural sources raise soiling loss; snow cover can cut winter production 20–100 % depending on tilt and shedding behavior.
- Site survey record items
- GPS coordinates, roof pitch and azimuth, obstruction dimensions, distance to main panel, conduit or trench path, and utility meter location.
- Permit plan set contents
- Site plan, roof plan, electrical single-line diagram, grounding details, structural calculations, equipment datasheets, and a string sizing table.
- Single-line diagram contents
- Shows module model and count, string configuration, combiner, DC disconnect, inverter, AC disconnect, service panel, OCPD ratings, conductor sizes, and grounding electrode conductor.
- DC PV system label
- NEC 690.53 requires a label at the DC disconnect stating maximum system voltage and maximum circuit current, marked 'Photovoltaic System'.
- AC interconnection label
- NEC 690.54 requires a label at the point of interconnection stating the rated AC output current of the PV system.
- Commissioning test records
- Record open-circuit voltage, short-circuit current, insulation resistance by megohmmeter, and ground continuity before energizing, and retain the results in the project file.
- Fall protection threshold
- OSHA 1926.501 requires fall protection for work at heights above 6 ft (1.8 m) in construction, via anchors, guardrails, or a personal fall arrest system.