NABCEP PVDS study materials
NABCEP PVDS study resources

NABCEP PVDS study plan

NABCEP PVDS · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

PV system electrical design

  • Trace a complete PV circuit from array through inverter to point of interconnection, labeling every conductor, overcurrent device, and disconnect on a one-line diagram

  • Compute string open-circuit voltage at the coldest expected design temperature and confirm it stays below the inverter maximum input voltage

  • Compute string operating voltage at the hottest expected cell temperature and confirm it stays above the inverter minimum MPPT voltage

  • Apply NEC 690.7 temperature correction factors to module Voc and record the source of each correction value

Your checkpoint

A one-line diagram of a 10 kW residential system with a table showing cold-temperature Voc, hot-temperature Vmp, and pass/fail against inverter voltage window

Week 2

PV system electrical design

  • Size string conductors and the dc equipment grounding conductor using NEC 690.8 current calculations and 310.16 ampacity tables

  • Select and justify overcurrent protection for source circuits, output circuits, and the inverter output using 690.8 and 690.9

  • Calculate maximum PV system voltage and verify 690.7 compliance for a bipolar or ungrounded array configuration

  • Explain how rapid shutdown requirements in 690.12 constrain conductor routing and combiner placement

Your checkpoint

A conductor and OCPD sizing worksheet for the same 10 kW system showing every calculation step and the governing NEC article

Week 3

PV system mechanical design

  • Compute roof dead load and wind uplift pressure for a flush-mounted array using ASCE 7 load combinations and module datasheet values

  • Determine minimum setback and access pathway dimensions required by the International Fire Code and local amendments

  • Specify rail spans, attachment spacing, and lag screw embedment for a given rafter spacing and module dimension

  • Identify when structural stamped engineering is required versus prescriptive attachment per code

Your checkpoint

A racking layout drawing with attachment spacing schedule, load assumptions, and a written justification for whether stamped engineering is needed

Week 4

PV system mechanical design & Project site assessment

  • Perform a shade analysis and translate the result into row spacing and minimum inter-row pitch for a ground-mount array

  • Evaluate roof condition, age, and covering type to determine whether re-roofing must precede installation

  • Document structural framing observed in the attic and flag deficiencies that affect attachment strategy

  • Compare flush mount, tilt mount, and ballasted options for a low-slope commercial roof against waterproofing and load constraints

Your checkpoint

A site structural and mounting feasibility memo covering two candidate roof surfaces with a recommended mounting method for each

Week 5

Project site assessment

  • Measure and record service entrance parameters including main breaker rating, busbar rating, and available panel spaces for a 120 percent busbar rule check

  • Conduct a shade study at multiple times of day and season and convert results into an annual production estimate

  • Assess utility interconnection options by reading a sample interconnection application and identifying the applicable review tier

  • Identify obstructions, clearances, and working space constraints at the proposed point of interconnection

Your checkpoint

A completed site assessment form for a real or simulated property including service panel photos-equivalent data, shade results, and interconnection tier determination

Week 6

Design documentation, permitting, and safety

  • Assemble a permit package checklist covering structural, electrical, and zoning submittal requirements for a typical jurisdiction

  • Produce a bill of materials and a labeling schedule matching NEC 690 and 705 marking requirements

  • Write a lockout/tagout and fall protection plan for a rooftop installation day

  • Draft a commissioning checklist covering insulation resistance, polarity, ground continuity, and IV curve tracing

Your checkpoint

A complete permit submittal package index with a labeling schedule and a one-page site safety plan

Week 7

PV system electrical design & Design documentation, permitting, and safety

  • Perform a full design review of a sample plan set and log every code deficiency found with the governing article

  • Verify the 120 percent busbar rule and supply-side versus load-side connection math for a service panel upgrade scenario

  • Reconcile as-built documentation against the approved plan set and describe the change order process

  • Explain inspection checkpoints a plan reviewer or field inspector will verify for the electrical portion

Your checkpoint

A redline review of a sample plan set listing at least ten findings with code citations and recommended corrections

Week 8

PV system mechanical design & Project site assessment & Design documentation, permitting, and safety

  • Complete two timed full-length practice exams and score each domain separately to find weak areas

  • Re-derive the ten calculations you missed most often without reference material

  • Build a one-page formula and reference sheet from memory covering voltage correction, ampacity, and load calculations

  • Review missed items across all four domains and confirm you can state the reasoning, not just the answer

Your checkpoint

A scored practice exam log with per-domain percentages and a personal formula sheet demonstrating closed-book recall

Milestones

Week 2: Can complete a full dc and ac conductor and OCPD sizing calculation for an unfamiliar system in under 20 minutes with correct NEC citations

Week 4: Can justify a mounting method and attachment spacing for an unfamiliar roof with reference to load calculations and fire code setbacks

Week 6: Can assemble a permit-ready package index and labeling schedule without referring to a template

Week 8: Scores at least 80 percent overall with no domain below 70 percent on a timed practice exam