Construction Payment Condition, Suspension, and Liquidated Damages

NALA ACP Contracts · Put your knowledge to work in context.

All case studies

Construction Payment Condition, Suspension, and Liquidated Damages

Lakeside Hospitality hires Summit Builders to renovate a hotel lobby for $480,000, with completion by May 1. The contract says time is of the essence and imposes $1,000 per day liquidated damages for delay. Progress payments are due 'upon the architect's certificate that the work is complete.' On April 20, Summit has finished 95% of the work. The punch list includes missing outlet covers, two misaligned tiles, and touch-up paint. The architect refuses to certify until every punch-list item is closed. Lakeside withholds a $90,000 progress payment. Summit stops work on April 25, saying it cannot pay subcontractors. Lakeside terminates, hires another contractor for $40,000 extra, and claims liquidated damages through June 15. Summit claims Lakeside breached first. The contract has no suspension clause.

1. Was Lakeside entitled to withhold the $90,000 progress payment based on the architect's refusal to certify?

Read the worked answer

The architect's certificate is a condition precedent to Lakeside's payment obligation. A condition must occur before the duty to pay arises, but courts do not enforce conditions mechanically when doing so would cause disproportionate forfeiture. Restatement (Second) of Contracts § 229 allows a condition to be excused if its nonoccurrence is not a material part of the exchange and enforcement would cause extreme forfeiture.

Summit has completed 95% of the work. The open items-outlet covers, two misaligned tiles, and touch-up paint-are minor and easily cured. Withholding $90,000 for those items is disproportionate to the harm Lakeside suffers. The architect's refusal to certify also raises a good-faith issue: if the architect is acting arbitrarily or as Lakeside's agent to pressure Summit, the refusal may itself breach the implied duty of good faith. A court would likely find substantial performance and excuse the certificate condition, at least as to the bulk of the payment.

Lakeside could withhold a reasonable amount to cover the punch-list work, but not the entire $90,000. Because it withheld the full payment, Lakeside probably breached the payment term. That matters for the next question: Summit's suspension may be justified if Lakeside's breach was material.

2. Did Summit's decision to stop work constitute a material breach, or was it justified by Lakeside's nonpayment?

Read the worked answer

This is a materiality contest. Summit stopped all work on April 25 after Lakeside withheld $90,000-a large portion of the contract price-while Summit was 95% complete. If Lakeside's withholding was unjustified, Summit had a strong argument that Lakeside committed a material breach going to the heart of the exchange. A contractor cannot be expected to finance a project when the owner withholds a substantial progress payment without a reasonable basis.

But Summit's remedy is not automatic. The contract has no suspension clause, and stopping work entirely is risky. A court will ask whether Lakeside's breach was material, whether Summit gave notice and an opportunity to cure, and whether Summit's stoppage was proportionate. If the only dispute was minor punch-list work, Summit might have been required to continue and sue for the withheld payment rather than walk off the job. If Lakeside's nonpayment made it impossible for Summit to pay subcontractors, the suspension looks more like a justified response to a material breach.

Lakeside's termination may therefore be wrongful if Summit was justified. Conversely, if a court finds Lakeside's withholding reasonable because the certificate condition was enforceable, Summit's stoppage could be the first material breach. The outcome turns on the materiality of the withheld payment and the good faith of the architect's refusal.

3. Are the $1,000-per-day liquidated damages enforceable, and for what period can Lakeside recover them?

Read the worked answer

The clause is enforceable only if it is a reasonable forecast of anticipated harm at the time of contracting, not a penalty. $1,000 per day on a $480,000 contract is roughly 0.21% per day. That is within a range courts often accept for hotel renovation delays, where lost room revenue and disruption are hard to estimate. Lakeside should be prepared to show its anticipated daily loss from a delayed lobby reopening. If the actual loss is far lower, or if the clause is a blunt punishment, Summit may argue penalty.

Even if enforceable, liquidated damages require causation. Lakeside cannot recover for delay it caused. If Lakeside's wrongful withholding of the $90,000 caused Summit's stoppage, the resulting delay is owner-caused and cannot be charged to Summit. The same is true for delay caused by the architect's unreasonable refusal to certify. Lakeside also cannot recover liquidated damages after it terminated Summit and hired a replacement unless the contract clearly makes Summit liable for the replacement period.

Lakeside's best recovery is limited to delay actually caused by Summit before the wrongful withholding, if any. It must also credit the $40,000 extra cost only if Summit's breach caused that cost. If Lakeside breached first, Summit may recover the unpaid progress payment and lost profits, and Lakeside's liquidated-damages claim may fail entirely.