- R stamp authority
- The National Board issues the R stamp, which authorizes a qualified holder to repair or alter boilers and pressure vessels under the NBIC rather than to construct new items.
- Prerequisite ASME authorization
- Before receiving an R certificate, an applicant normally must hold an appropriate ASME Code certificate of authorization for the scope of work, or an equivalent National Board authorization.
- Joint review
- Accreditation requires an on-site review conducted jointly by the National Board and the jurisdiction where the shop is located, covering the QC manual and actual work practices.
- Certificate term and renewal
- The R certificate is issued for a defined term, commonly three years, and must be renewed before it expires; work after expiration is not valid R-stamp work.
- Scope of authorization
- The certificate states which types of items the holder may repair or alter; performing work outside that scope requires a scope change or additional authorization.
- Notification of changes
- Changes in name, address, ownership, or shop location must be reported to the National Board and typically require a new review before the certificate is reissued.
- Suspension or withdrawal
- Failure to correct nonconformities found at review, or loss of the underlying ASME authorization, can lead to suspension or withdrawal of the R certificate.
- Holder directory
- The National Board publishes a directory of current R stamp holders, which owners and jurisdictions use to confirm that a shop's authorization is active.
- Repair versus alteration
- A repair restores an item to a safe and sound condition without changing design parameters; an alteration changes pressure, temperature, capacity, or configuration.
- Governing code for repairs
- Repairs and alterations follow the NBIC and, where the NBIC refers to it, the original code of construction for materials, design, and examination requirements.
- Welding procedure qualification
- Welded repairs require a written welding procedure supported by a procedure qualification record, and welders must be performance-qualified under ASME Section IX.
- Post-weld heat treatment
- When the original construction code would require post-weld heat treatment for the material and thickness involved, the repair must receive equivalent heat treatment.
- Alteration re-rating
- An alteration that changes design conditions requires new calculations and approval by the Authorized Inspector, and often by the jurisdiction, before the work is accepted.
- Authorized Inspector notification
- The Authorized Inspector must be notified before repair work starts and must verify required examinations before the R stamp is applied to the item.
- R stamp marking content
- The R stamp is applied with the National Board registration number, the date, and identifying data required by the NBIC, typically on the nameplate or an attached plate.
- Material traceability
- Repair materials must be traceable through mill test reports or equivalent documentation, and any substitution must be evaluated against the original design requirements.
- Record retention
- The R stamp holder retains repair and alteration records, including procedures, material documentation, and inspection results, and makes them available to the inspector and National Board.
- QC manual control
- The quality control manual must be written, dated, and controlled, and it defines the organization, authority, and responsibilities for performing and verifying repair work.
- Organization chart requirement
- The manual must include a current organization chart and identify the individual with overall quality authority and the person responsible for code compliance.
- Required manual elements
- Manual content covers design inputs for alterations, material control, welding, NDE, heat treatment, equipment calibration, nonconformance control, and records.
- Personnel qualification program
- A documented program must qualify welders, welding operators, NDE personnel, and inspectors, with current records retained and available for review.
- Inspector access and hold points
- The manual must describe how the Authorized Inspector gains access to the shop, work in progress, and records, and where inspection hold points are established.
- Nonconformance control
- Nonconforming items must be identified, segregated where practical, evaluated, and dispositioned by qualified personnel, with corrective actions documented and tracked.
- Internal audits
- The quality program requires periodic internal audits performed by personnel independent of the activity audited, with findings and corrective actions recorded.
- Calibration traceability
- Measuring and test equipment must be calibrated traceably to recognized standards with a recorded next-due date; instruments found out of calibration require evaluation of prior results.
- Document control at the worksite
- Only current, approved procedures may be used at the point of work, and superseded documents must be removed or clearly marked to prevent inadvertent use.
- R-1 data report
- The R-1 form documents a repair or alteration, including item identification, scope of work, code editions used, materials, and examination results, signed by holder and inspector.
- National Board registration number
- Each repair or alteration receives a National Board registration number that appears on the R-1 form and in the stamping applied to the item.
- R-1 distribution
- The completed R-1 report goes to the owner or user, the Authorized Inspector, and the National Board, with a copy retained by the R stamp holder.
- Supporting records
- NDE reports, heat treatment charts, and material certifications must be traceable to the specific R-1 report and retained together with it.
- Revision of a data report
- A revision to a submitted R-1 report must be documented with the reason stated and distributed to the same recipients as the original report.
- Meaning of inspector signature
- The Authorized Inspector's signature attests that the repair or alteration complied with the applicable code and NBIC, not that the item is suitable for a specific service.