- NFPA 13 scope
- NFPA 13 applies to commercial, industrial, and residential occupancies with 5 or more sprinklers. It does not cover one- and two-family dwellings, which fall under NFPA 13D.
- Light hazard density
- The minimum design density for light hazard occupancies is 0.10 gpm/ft² over a 1,500 ft² design area, with a maximum sprinkler spacing of 15 ft and 225 ft² per sprinkler.
- Ordinary hazard Group 2
- Ordinary Hazard Group 2 requires a design density of 0.20 gpm/ft² over 1,500 ft², with a maximum sprinkler spacing of 15 ft and a maximum protection area of 130 ft² per sprinkler.
- Deflector distance
- Sprinkler deflectors must be at least 1 in and no more than 12 in below a noncombustible ceiling, and at least 1 in and no more than 6 in below a combustible ceiling.
- Dry system design area
- The design area for a dry pipe system must be increased by 30% over the wet pipe design area to account for the delay in water delivery after the valve opens.
- Residential sprinkler spacing
- Under NFPA 13R, residential sprinklers must be listed for residential use, with a maximum spacing of 12 ft for 1/2 in sprinklers and 15 ft for 3/4 in sprinklers.
- Concealed space protection
- Combustible concealed spaces must be protected by sprinklers unless the space is filled with noncombustible material or is less than 6 in high with a noncombustible ceiling.
- Wet alarm check valve
- A wet alarm check valve at the riser opens on water flow to sound the alarm and must be provided with a main drain, pressure gauge, and waterflow alarm.
- Sprinkler temperature color codes
- Ordinary sprinklers (135-170°F) are orange, intermediate (175-225°F) are red, high (250-300°F) are yellow, and very high (325-375°F) are green.
- Hanger spacing
- Maximum hanger spacing is 12 ft for 1 in and 1¼ in pipe, 15 ft for 1½ in through 4 in pipe, and the first hanger must be within 3 ft of a sprinkler.
- Sway bracing requirement
- Sway bracing is required for systems with 2½ in and larger pipe and for pipe subject to seismic loads, with lateral bracing at intervals not exceeding 40 ft.
- Dry pipe valve air pressure
- A dry pipe valve must be listed and maintain air pressure of 20-40 psi, with a maximum of 60 psi; the air supply must restore system pressure within 30 minutes.
- Inspector's test valve
- The inspector's test valve is located at the most remote sprinkler and has a 5/8 in orifice; it is used to test the waterflow alarm and must sound within 90 seconds.
- Fire department connection
- The FDC must be located within 100 ft of a hydrant, be visible and accessible, be equipped with a check valve and drain, and be marked with system type and pressure.
- Hazen-Williams formula
- Friction loss per foot = 4.52 × Q^1.85 / (C^1.85 × d^4.87), where Q is gpm, d is inside diameter in inches, and C is the roughness coefficient (120 for steel).
- Elevation pressure loss
- Elevation loss is 0.433 psi per foot of rise; a 10 ft rise reduces pressure by 4.33 psi, and this loss is added to friction loss in the calculation.
- Density/area method
- Flow per sprinkler equals density (gpm/ft²) multiplied by the area protected by the sprinkler; the design area is the remote area with the most unfavorable hydraulics.
- Hose stream allowance
- The hose stream allowance is typically 100-250 gpm and is added to the sprinkler flow to determine total system demand, which must be less than the available supply.
- Minimum sprinkler pressure
- The minimum pressure at the most remote sprinkler is 7 psi for wet systems and 15 psi for dry systems; the maximum pressure at any sprinkler is 175 psi unless listed otherwise.
- Water supply duration
- Required water supply duration is 30 minutes for light hazard, 60-90 minutes for ordinary hazard, and 90-120 minutes for extra hazard occupancies per NFPA 13.
- Standpipe classes
- Class I standpipes serve the fire department, Class II serve occupants with 1½ in hose, and Class III serve both; residual pressure at the top outlet must be at least 100 psi.
- Fire pump churn pressure
- Churn pressure is the pump discharge pressure at zero flow; it must not exceed 140% of the rated pressure to protect the system from overpressure.
- G.S. 87-13 license requirement
- G.S. 87-13 defines a fire sprinkler contractor as a person engaged in installing, maintaining, or repairing sprinkler systems; a license is required to contract for this work.
- State Board authority
- G.S. 87-14 establishes the State Board of Examiners of Plumbing, Heating, and Fire Sprinkler Contractors, which examines applicants, issues licenses, and adopts rules.
- Experience requirement
- G.S. 87-15 requires an applicant for a fire sprinkler license to have at least 2 years of experience in the trade and to pass the Board's examination.
- License renewal
- G.S. 87-16 provides for annual license renewal; a license may be revoked or suspended for fraud, incompetence, or violation of the Board's rules.
- 21 NCAC Chapter 50
- 21 NCAC Chapter 50 sets the Board's fire sprinkler contractor rules, including examination content, experience documentation, continuing education, and disciplinary procedures.
- Plan submittal
- Before installation, the contractor must submit plans and specifications to the local fire marshal or code official showing design density, area of operation, pipe sizes, and water supply.
- Permit requirement
- A permit must be obtained from the local jurisdiction before installation begins; the permit must be posted on the job site and inspections requested at required stages.
- Hydrostatic test
- The system must be hydrostatically tested at 200 psi for 2 hours, or 50 psi above the maximum working pressure if greater; dry systems are tested at 13 psi air for 24 hours.
- Underground flushing
- Underground mains must be flushed at a velocity of at least 10 ft/s before connection to the sprinkler system, and the flush must be witnessed by the code official.
- As-built documentation
- At completion, the contractor must provide the owner with as-built drawings, hydraulic calculations, the owner's manual, and maintenance instructions for the system.