Minimum septic tank setback
The well casing must be at least 50 feet horizontally from a septic tank. Distance is measured from the well head to the nearest edge of the tank.
Minimum drainfield setback
The well casing must be at least 100 feet horizontally from a septic absorption field or drainfield. Local rules may require a greater separation distance.
Sewer line setback
A well must be at least 50 feet from a sanitary sewer line. Where the line is a force main under pressure, the required separation is larger.
Setback measurement point
Setbacks are measured horizontally from the well casing to the nearest edge of the facility, not to a building centerline or the middle of a drainfield.
Well head grading
Ground around the casing must slope away from the well so surface water drains off. The well head must not sit in a swale or low spot.
Floodway well siting
A well should not be placed in a floodway or frequently flooded area unless the casing is extended and sealed to keep floodwater out of the well.
Animal feedlot setback
Barnyards, feedlots, and chemical storage areas must be at least 100 feet from a well. Fuel tanks and lines have separate required distances.
Neat cement grout mix
Neat cement grout uses no more than 6 gallons of clean water per 94-pound sack of cement. Excess water weakens the seal and causes shrinkage.
Tremie grouting method
Grout is placed from the bottom of the annular space upward through a tremie pipe using a positive displacement pump. Free-fall dumping is not acceptable.
Bentonite grout density
Bentonite slurry grout is mixed to the manufacturer's density, typically about 9.4 pounds per gallon or heavier, so the seal sets properly.
Grout volume formula
Volume equals 0.7854 times the difference of borehole diameter squared minus casing diameter squared, times length. Add margin for washouts.
Grout seal extent
The grout seal runs from the top of the screen or open interval to land surface or the well house floor, with no unsealed gap.
Well abandonment sealing
An abandoned well must be filled with grout or approved sealing material, the casing removed or perforated as specified, and the top capped.
Granular bentonite use
Granular bentonite may be used in a dry, stable annulus. Below the water table or in caving ground, a slurry or cement grout is required.
Casing height above grade
Casing must extend at least 12 inches above finished grade or above the well house floor, and be fitted with a sanitary, vermin-proof cap.
Annular clearance minimum
The space between borehole wall and casing should be about 2 inches nominal. Too small blocks grout; too large risks bridging.
Casing material requirement
New wells require new steel or NSF/ANSI 61-certified plastic casing. Used casing is generally prohibited for new potable water wells.
Screen slot sizing
Screen openings are chosen to retain about 90 percent or more of the formation sample, based on sieve analysis of the aquifer material.
Rotary versus cable tool
Rotary air or mud drilling suits unconsolidated sediments. Cable tool is preferred where boulders, hard rock, or caving formations hinder hole cleaning.
Well log filing
The well log records total depth, casing and grout depths, and yield. It is filed with the state and is the legal record of construction.
Confining layer penetration
Do not drill through a confining layer deeper than needed. Each extra aquifer tapped raises the risk of cross-contamination between water zones.
Well development purpose
Development removes drilling fines and mud cake to raise yield. Methods include surging, jetting, bailing, and air-lift pumping until discharge clears.
Development stopping point
Stop development when turbidity stabilizes at a low level. Overdevelopment can destabilize the formation or pull fines into the gravel pack.
Pump setting depth
The pump intake must stay above the screen and above expected drawdown, so the pump does not cavitate or run dry during normal use.
Total dynamic head
TDH equals static lift plus drawdown plus friction loss plus discharge pressure head. It is used to size the submersible pump.
Specific capacity
Specific capacity is yield divided by drawdown, in gallons per minute per foot. It indicates how productive the well is per foot of drawdown.
Pitless adapter function
A pitless adapter makes a below-frost, sanitary connection through the casing. The casing top is still sealed with a cap and vent.
Pressure tank role
The pressure tank maintains system pressure and limits pump cycling. A check valve on the discharge prevents backflow and protects the pump.
Permit before construction
A well permit must be obtained before construction begins. The application includes proposed location, depth, casing, and intended use.
Certified contractor requirement
Well construction in North Carolina requires a certified well contractor whose certification is current and in good standing when the work is done.
Well log submission
The completion report and well log must be filed with the state within the required time after construction, with a copy given to the owner.
Grounds for revocation
Certification may be suspended or revoked for violations such as building without a permit, failing to grout, or falsifying a well log.