Pole Handling, Setting, and Lifting Operations
What this domain tests
This domain tests planning and executing pole lifts: weight verification, rigging, chart checks, controlled movement, and setting the pole without exposing the crew.
Core rules
- Know the pole weight before lifting; confirm it from the tag or delivery documentation.
- Rig with an approved sling, choker, or pole claw; balance the pole so it hangs level and does not rotate unexpectedly.
- Check chart capacity at the working radius after deducting the claw, sling, and any attachment weight.
- Use tag lines from outside the load path. No one stands under the load, in the hole, or between the pole and the truck while the pole is moving.
- Set the pole, plumb it, and backfill or tamp in lifts before releasing the rigging. Coordinate every move with the crew.
Worked example
A pole weighs 2,600 lb, the pole claw 250 lb, and the sling 80 lb. At 16 ft the chart allows 3,200 lb. Available = 3,200 โ 250 โ 80 = 2,870 lb, which exceeds 2,600 lb, so the lift is acceptable. At 18 ft the chart allows 2,800 lb; available = 2,470 lb, which is less than the 2,600 lb pole. The operator must reposition or use a shorter radius.
Traps
Lifting at the pole tip without checking radius; using hands to guide the pole under load; ignoring wind on a long pole; and releasing rigging before the pole is stable.
Key points
- Verify pole weight before rigging.
- Deduct claw and sling weight from chart capacity.
- Use tag lines and keep personnel out of the load path.
- Never guide a suspended pole with hands.
- Backfill and tamp before releasing the rigging.