NCCCO Digger Derrick: Pole Handling, Setting, and Lifting Operations

NCCCO Digger Derrick ยท Work through your exam, one topic at a time.

All guide sections

Pole Handling, Setting, and Lifting Operations

What this domain tests

This domain tests planning and executing pole lifts: weight verification, rigging, chart checks, controlled movement, and setting the pole without exposing the crew.

Core rules

  • Know the pole weight before lifting; confirm it from the tag or delivery documentation.
  • Rig with an approved sling, choker, or pole claw; balance the pole so it hangs level and does not rotate unexpectedly.
  • Check chart capacity at the working radius after deducting the claw, sling, and any attachment weight.
  • Use tag lines from outside the load path. No one stands under the load, in the hole, or between the pole and the truck while the pole is moving.
  • Set the pole, plumb it, and backfill or tamp in lifts before releasing the rigging. Coordinate every move with the crew.

Worked example

A pole weighs 2,600 lb, the pole claw 250 lb, and the sling 80 lb. At 16 ft the chart allows 3,200 lb. Available = 3,200 โˆ’ 250 โˆ’ 80 = 2,870 lb, which exceeds 2,600 lb, so the lift is acceptable. At 18 ft the chart allows 2,800 lb; available = 2,470 lb, which is less than the 2,600 lb pole. The operator must reposition or use a shorter radius.

Traps

Lifting at the pole tip without checking radius; using hands to guide the pole under load; ignoring wind on a long pole; and releasing rigging before the pole is stable.

Key points

  • Verify pole weight before rigging.
  • Deduct claw and sling weight from chart capacity.
  • Use tag lines and keep personnel out of the load path.
  • Never guide a suspended pole with hands.
  • Backfill and tamp before releasing the rigging.