NCCCO LBT study materials
NCCCO LBT study resources

NCCCO LBT study plan

NCCCO LBT · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Lift Planning

  • Define load weight, center of gravity, and rigging weight, and compute total suspended load for three worked examples

  • Identify the information required on a lift plan and explain why each item matters to the lift director

  • Calculate net capacity for a simple configuration using a load chart with deductions for block, ball, and rigging

  • List the site and configuration factors that reduce capacity: radius, boom length, quadrant, outrigger extension, and ground bearing

Your checkpoint

A one-page lift plan template plus three completed sample load calculations showing total load, gross capacity, and net utilization percentage

Week 2

Lift Planning & Site Preparation and Hazard Assessment

  • Classify lifts as ordinary or critical using defined criteria such as personnel exposure, multiple cranes, or proximity to power lines

  • Determine ground bearing pressure for outrigger floats and compare it to assumed soil capacity for two soil types

  • Draft a rigging selection for a multi-leg sling lift including sling angle effect on tension

  • Identify hazards along the crane's full travel path and swing radius and assign a control to each

Your checkpoint

A hazard register for a hypothetical site listing at least 12 hazards, each with a control measure and an owner

Week 3

Site Preparation and Hazard Assessment

  • Evaluate a site layout for crane positioning, access roads, laydown areas, and exclusion zones

  • Explain the requirements for barricades, accessible swing-radius control, and tag lines

  • Assess wind, weather, and visibility conditions against a stop-work threshold you define

  • Describe the process for verifying utility locations and establishing approach distances near power lines

Your checkpoint

An annotated site sketch showing crane position, swing radius, exclusion zone, laydown area, and utility clearances with dimensions

Week 4

Lift Planning & Site Preparation and Hazard Assessment

  • Complete a full written lift plan for a non-routine lift from pre-lift meeting through post-lift review

  • Match rigging hardware to load and configuration and justify each selection

  • Identify the roles of lift director, signal person, operator, and rigger and describe handoffs between them

  • Self-score your lift plan against a checklist you build from the standards you are studying

Your checkpoint

A complete lift plan package with rigging plan, load calculations, hazard controls, and a pre-lift meeting agenda

Week 5

Lift Execution and Supervision

  • Sequence the steps of a lift from pre-lift meeting to load securement and explain the stop criteria at each step

  • Describe standard hand signals and the fallback communication plan when radios fail or line of sight is lost

  • Explain how to conduct a trial lift and what observations justify stopping

  • Identify the conditions that require stopping work immediately and who has authority to stop the lift

Your checkpoint

A written lift execution checklist with at least 20 sequenced checkpoints and a defined stop-work trigger for each

Week 6

Lift Execution and Supervision & Regulations, Standards, and Documentation

  • Outline the inspection and maintenance documentation required before a crane is placed in service

  • Describe the recordkeeping for operator certification, rigging inspection, and lift plan retention

  • Explain the supervisor's role during a multi-crane or tandem lift and the added planning requirements

  • Draft an incident-response sequence from load drop through notification, scene control, and reporting

Your checkpoint

A documentation binder index listing every record type, who maintains it, and how long it is retained

Week 7

Regulations, Standards, and Documentation & Lift Planning

  • Summarize the scope of the applicable OSHA crane standard and the consensus standards governing lift planning and rigging

  • Explain employer and employee responsibilities for qualified and competent persons in lifting operations

  • Re-derive a load chart calculation and a ground bearing calculation without notes

  • Review your week 4 lift plan and correct every gap you now see

Your checkpoint

A corrected lift plan plus a one-page summary of the regulatory requirements that apply to planning and documentation

Week 8

Regulations, Standards, and Documentation & Lift Execution and Supervision & Site Preparation and Hazard Assessment & Lift Planning

  • Answer at least 100 practice questions across all four domains and log every miss by domain and cause

  • Re-teach your three weakest topics aloud in under five minutes each without notes

  • Rehearse the full sequence of a lift from site assessment to post-lift documentation in one continuous walkthrough

  • Build a final one-page reference sheet of formulas, thresholds, and stop criteria

Your checkpoint

A scored practice test log with at least 80 percent overall and a written remediation note for each missed item

Milestones

Week 2: Can compute total suspended load, net capacity, and ground bearing pressure unaided and explain each result

Week 4: Produce a complete lift plan package that passes your own checklist with no unresolved gaps

Week 6: Explain lift execution sequencing and documentation requirements from memory in under ten minutes

Week 8: Score at least 80 percent on a 100-question mixed practice set with no domain below 70 percent