NCCCO Service Truck Crane · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Operations

  • Map the Operations domain (44% of the exam) into its sub-areas: pre-lift setup, signal communication, load control, travel with a load, and shutdown/securing, and allocate study blocks to each by weight.

  • Define and write out, in your own words, the roles and stop-work authority of the operator, signalperson, rigger, and lift director on a service truck crane pick.

  • List the conditions that require a lift plan or a qualified person's involvement before lifting, and state at least five concrete examples for a boom truck or service crane.

  • Build a one-page pre-lift checklist covering ground bearing, outrigger/stabilizer deployment, utility clearance, load weight verification, and rigging inspection.

Your checkpoint

A completed one-page pre-lift checklist plus a written role/responsibility summary that you can recite from memory.

Week 2

Operations

  • Explain how capacity changes with radius, boom angle, boom length, and quadrant, and demonstrate the relationship using a sample load chart without relying on memory.

  • Describe the standard hand signals used for hoisting, lowering, stopping, emergency stop, and boom motions, and match each signal to its meaning.

  • Identify the hazards of side loading, shock loading, and rapid swing/stop inputs, and state the operator response for each.

  • Outline the procedure for traveling a service truck crane with a load, including when travel with a load is prohibited by the load chart notes.

Your checkpoint

A hand-signal and hazard-response flashcard set of at least 20 cards, self-quizzed to 90% accuracy.

Week 3

Operations & Technical Knowledge

  • Trace the flow of hydraulic pressure from pump through control valve to hoist, boom, and outrigger circuits, and explain what a holding valve or counterbalance valve does.

  • Describe the function of the rated capacity limiter/load moment indicator, boom angle and length sensors, and anti-two-block devices, and state how to verify they are functioning before a lift.

  • Explain wire rope construction, lay, and the removal criteria for broken wires, kinking, crushing, and corrosion, and apply those criteria to a described rope condition.

  • Identify the purpose and inspection points of hooks, latches, sheaves, and boom wear pads.

Your checkpoint

A labeled system diagram (pump-to-actuator) with a written explanation of each safety device and its pre-lift check.

Week 4

Technical Knowledge & Manufacturers' Load Charts

  • Read a manufacturer's load chart and correctly locate capacity for a given boom length, radius, quadrant, and outrigger configuration, including the effect of a jib or stowed attachment.

  • Apply the chart notes and deductions for load-handling devices, rigging weight, and optional equipment to compute net allowable load.

  • Explain stability versus structural capacity and identify which chart limits govern a given configuration.

  • Calculate gross load by summing the load, rigging, and hook block, and compare it to the chart value for at least five practice scenarios.

Your checkpoint

A worked problem set of 10 load-chart capacity calculations with correct answers and a short note on the governing limit for each.

Week 5

Manufacturers' Load Charts & Operations

  • Practice using range diagrams and area-of-operation charts to determine whether a proposed pick position is within the working range.

  • Compute deductions and interpolate between chart values where permitted, and identify when interpolation is not allowed.

  • Apply the two-block, boom deflection, and wind/weather notes to realistic lift scenarios.

  • Rehearse the sequence of a full lift from setup to secure, applying chart limits at each step.

Your checkpoint

A timed 20-question load-chart quiz completed at 80% or better, with errors reviewed and corrected in writing.

Week 6

Site & Operations

  • Assess ground conditions and calculate/estimate bearing pressure under outrigger floats, and select cribbing based on soil type and float size.

  • Identify site hazards including overhead and underground utilities, slope, excavation edges, traffic, and pedestrian control, and state the control for each.

  • Describe proper setup: leveling, full outrigger extension, float placement, barricades, and exclusion zones.

  • Explain the requirements for working near power lines, including minimum approach distances and the role of the spotter/utility owner.

Your checkpoint

A site-setup hazard assessment for a described job scenario, listing at least 10 hazards with a specific control for each.

Week 7

Site & Operations & Technical Knowledge & Manufacturers' Load Charts

  • Integrate all four domains into full scenario walkthroughs: setup, chart check, rigging, signal, lift, and secure.

  • Review and correct every missed item from prior quizzes and problem sets, writing the correct reasoning for each.

  • Practice explaining your decisions aloud as you would to an examiner, using precise terminology.

  • Identify your three weakest sub-areas and drill them with targeted questions.

Your checkpoint

Three complete written lift scenarios with setup rationale, chart calculations, hazard controls, and signal plan.

Week 8

Operations & Manufacturers' Load Charts

  • Take two full-length timed practice exams weighted 17/44/21/17 across the domains and record scores by domain.

  • Re-drill any domain scoring below 80% until it reaches that threshold.

  • Memorize the key chart-reading steps and safety-device checks so they can be performed without reference.

  • Finalize a one-page personal reference sheet of formulas, chart steps, and hazard controls for last-minute review.

Your checkpoint

Two completed timed practice exams with domain scores of 80% or higher in every domain, plus the final one-page reference sheet.

Milestones

Week 2: Can state the hand signals and the radius/angle/length/quadrant capacity relationship without notes, and score 90% on the flashcard set.

Week 4: Correctly solve 8 of 10 load-chart capacity problems, including rigging deductions and identification of the governing limit.

Week 6: Score 80% or better on the timed load-chart quiz and produce a 10-hazard site assessment with specific controls.

Week 8: Score 80% or higher in each of the four domains on two full-length timed practice exams.