NCCER Carpenter · Put your knowledge to work in context.

All case studies

Diagonals That Do Not Match, One Day Before the Pour

A crew is laying out a 32 ft x 48 ft detached garage slab-on-grade with an 8 in. stem wall. Batter boards and string lines are set, and the crew checked one corner with a 3-4-5 triangle. The two diagonal measurements read 57'-8" and 57'-9 1/2". A surveyor set a benchmark at the curb three days ago, but the lead wants to set form height by measuring up 6 in. from the existing driveway because "it drains away from the house." The concrete truck is scheduled for 7 a.m. tomorrow, the forms are staked, and the rebar is tied. The owner asks the crew to confirm the layout is ready before the dispatcher is called.

1. Are the corners square? Show the check and the correction.

Read the worked answer

Check: For a 32 ft x 48 ft rectangle the diagonals are equal to the square root of (32² + 48²) = the square root of (1024 + 2304) = the square root of 3328 = 57.69 ft, which is 57'-8 1/4". Both measured diagonals are close to that length, but they differ from each other by 1 1/2" - and equal diagonals, not equal to a calculated number, is the real test. A 1 1/2" split means the layout is a parallelogram, not a rectangle.

Why the 3-4-5 did not catch it: a 3-4-5 at one corner only proves that one corner is 90 degrees. A parallelogram can have one square corner and still be skewed.

Correction:

  1. Check the strings for sag and for being knocked off the batter boards.
  2. Move the corners against the long side in the direction that equalizes the diagonals - roughly half of the 1 1/2" error, about 3/4" at each of two opposite corners.
  3. Re-measure both diagonals and repeat until they agree within 1/4 in. (many crews hold 1/8 in.).
  4. Re-verify all four corners, then re-string and re-mark the stakes.

2. Evaluate the proposal to set form height from the existing driveway.

Read the worked answer

That is the wrong datum. The driveway is not a surveyed elevation - it may pond, heave, or have been poured to a slope - so tying the finished floor to it can put the slab below the plan elevation or below grade, which is a drainage and code problem that cannot be fixed after the pour.

Correct approach:

  • Work from the surveyor's benchmark, which is a known elevation, not a convenient surface.
  • Transfer the elevation with a level or transit and mark a permanent reference on a stable object (a stake set well outside the work, a foundation corner, a tree with a nail and flag).
  • Compute stem wall height from the plan: top of stem wall = slab thickness + finished floor elevation above the benchmark.
  • Re-shoot and record the elevations of all four corners; a slab that is out of level shows up later as squeaky floors and door problems above.
  • Note that a benchmark set three days ago in active construction should be re-verified - protect it and confirm it has not been disturbed.

3. The error is confirmed 45 minutes before the crew needs to leave, and the truck is booked. What do you recommend, and why?

Read the worked answer

Push the pour. A 1 1/2" skew is small in absolute terms, but it is systematic: every wall, every roof plane, and every sheet of drywall above carries it. Out-of-square buildings show up as tapered rooms, siding that will not close, roof planes that do not meet, and cabinets and doors that never fit right. None of that is fixable later for the price of one day.

Reasoning:

  • The fix is a few hours of layout work plus re-inspection of the rebar and forms; the cost of a rescheduled truck and a lost day is far less than the cost of a skewed building.
  • The crew should also use the delay to re-verify the benchmark and the form elevations, since the datum is already in question.
  • Call the dispatcher immediately rather than after the truck rolls, and record the reason. Do not pour and "fix it with the plates."
  • If the owner pushes back, frame the decision in terms of cost and schedule for the whole job, not just the foundation.