NCCER Carpenter study materials
NCCER Carpenter study resources

NCCER Carpenter cheat sheet

NCCER Carpenter · Keep the key ideas within reach.

Quick reference

Carpentry Safety, Tools, and Trade Fundamentals

  • OSHA construction rules require fall protection (guardrail system, safety net, or personal fall arrest) whenever a worker is 6 ft or more above a lower level.

  • Ladder setup rule: the base sits 1 ft out for every 4 ft of height (4:1), and an extension ladder must extend at least 3 ft above the landing surface.

  • Supported scaffold guardrails: top rail 42 in above the platform, midrail approximately 21 in, plus toe boards where workers or materials below are exposed.

  • Nominal vs. actual dressed sizes: 2x4 = 1-1/2 x 3-1/2 in; 2x6 = 1-1/2 x 5-1/2 in; 2x8 = 1-1/2 x 7-1/4 in; 2x10 = 1-1/2 x 9-1/4 in; 2x12 = 1-1/2 x 11-1/4 in.

  • Board feet = nominal thickness (in) x nominal width (in) x length (ft) divided by 12; a nominal 2x6 10 ft long contains 10 board feet.

  • All temporary 120-volt receptacles on a construction site require GFCI protection, which trips when current leaks to ground.

  • Before changing a blade, adjusting a guard, or clearing a jam, disconnect the power source (unplug the cord or remove the battery) on any power tool.

  • Never carry a pneumatic nailer with a finger on the trigger, and always disconnect the air hose before clearing a jam or making adjustments.

  • A lumber grade stamp shows species group, grade, moisture content, grading agency, and mill; span tables for joists and rafters depend on those values.

Quick reference

Site Layout, Print Reading, and Concrete Forms

  • Square a corner with the 3-4-5 method (or multiples such as 6-8-10): 3 ft one way, 4 ft on the perpendicular, and adjust until the diagonal reads 5 ft; verify by comparing both diagonals of the rectangle.

  • Batter boards are set about 2 to 3 ft outside the building corners so the string lines marking the building lines can be restrung after excavation.

  • Footings must bear on undisturbed soil below the local frost depth and be sized for the soil bearing capacity and the wall load.

  • Minimum rebar cover: 3 in for concrete cast directly against the earth, 2 in for concrete exposed to weather.

  • Vertical wall forms are typically stripped 24 to 48 hours after placement; slab forms and shores stay until the concrete reaches the strength assumed in design, commonly about 7 days.

  • Saw-cut control joints are spaced about 2 to 3 times the slab thickness in feet, so a 4-in slab gets joints roughly 8 to 12 ft apart.

  • Read written dimensions rather than scaling the drawing; the title block gives the scale, date, and revision status of the sheet.

  • Concrete weighs about 145 to 150 lb per cubic foot, and 1 cubic yard equals 27 cubic feet.

Quick reference

Floor, Wall, and Ceiling Framing

  • An 8-ft wall framed with a 92-5/8 in precut stud, one bottom plate, and a double top plate measures about 97-1/8 in from subfloor to top of plate.

  • Common studs are spaced 16 in or 24 in on center; every rough opening gets king studs, jack (trimmer) studs, a header, and cripple studs at the common spacing.

  • Double top plates must lap at corners and at intersecting partitions so the wall line is tied together.

  • Header size is determined by span and load; jack studs transfer the header ends to the sole plate and king studs run full height.

  • Floor joists are installed crown up, and their maximum span comes from tables keyed to species, grade, size, spacing, and load.

  • The rim joist caps the joist ends, squares the floor system, and supports the subfloor edge and exterior wall plates; joist hangers are used where joists frame into headers.

  • Subfloor panels of 3/4 in tongue-and-groove plywood or OSB are glued and screwed, with ends staggered and about a 1/8 in gap left at panel edges.

  • Solid blocking or cross bridging is installed between joists at midspan and bearing lines to stop twisting and reduce floor bounce.

  • Walls are plumbed, aligned to the chalk line, and braced before the temporary braces are removed or sheathing is completed.

Quick reference

Roof Framing and Exterior Finish

  • Roof pitch is stated as rise over 12 in of run; a 6/12 roof rises 6 in per foot of run, an angle of about 26.6 degrees.

  • Common rafter length = the square root of (run squared + total rise squared); the rafter table on a framing square gives unit lengths per foot of run.

  • Ridge height above the plate = run x (pitch/12); for a gable roof the run is half the building width.

  • The ridge board should be at least 1 in thicker than the rafters it receives, and its top edge establishes the ridge height.

  • The birdsmouth consists of a plumb cut and a seat cut; the seat cut depth should not exceed one-third of the rafter depth.

  • Roof sheathing panels are laid with the long dimension perpendicular to the rafters, with panel edges supported and fastened to the rafter spacing shown on the panel rating.

  • Drip edge is installed under the underlayment at the eaves and over the underlayment at the rakes.

  • Lap siding is fastened about 1 in above the bottom edge so the nail is covered by the next course and does not pass through both pieces.

Quick reference

Interior Finish, Millwork, and Door/Window Installation

  • Drywall thickness: 1/2 in for walls, 5/8 in for ceilings on 24 in framing, and 5/8 in Type X where a fire-resistance rating is required.

  • Drywall screws are placed 12 in on center in the field and 8 in on center at panel edges, about 3/8 in back from the edges.

  • Door rough opening = door slab width plus about 2 in and slab height plus about 2-1/2 in, allowing room for the prehung frame and shims.

  • Standard interior and exterior door height is 6 ft 8 in; a common exterior door width is 3 ft 0 in.

  • When hanging a prehung door, plumb and shim the hinge side first, level the head jamb, then adjust the latch side to an even gap of about 1/8 in.

  • Window installation sequence: sill pan flashing first, then set and level the unit, then side flashing and head flashing lapped so water sheds outward.

  • Trim joints: cope inside corners and miter outside corners; baseboard is commonly 1/2 to 3/4 in thick.

  • Drywall finishing requires a tape coat followed by two progressively wider finish coats with feathered edges.