- Ground bearing pressure
- The pressure a crane's outrigger or track exerts on the soil, calculated as total weight divided by bearing area; it must not exceed the soil's allowable capacity.
- Load chart net capacity
- The chart's gross capacity minus the weight of hook block, slings, shackles, and other attachments below the boom tip; the result is the maximum allowable load.
- Outrigger float mat
- A pad placed under an outrigger float to spread load over a larger area, reducing ground bearing pressure to within the soil's allowable capacity.
- Minimum approach distance
- The regulated clearance that must be maintained between any part of the crane or load and an energized power line, set by the applicable electrical safety standard.
- Sling angle factor
- For bridle and basket legs, the capacity multiplier equals the cosine of the angle from horizontal; flatter angles reduce usable capacity sharply.
- Choker hitch capacity
- A hitch where the sling passes around the load and through itself; capacity is reduced, commonly to about 75 to 80 percent of the vertical rating.
- Shackle working load limit
- The maximum load a shackle is rated to carry; it must equal or exceed the calculated tension in the leg it connects and be marked by the manufacturer.
- Center of gravity
- The point where the load's weight is balanced; the lifting point must be above it or multiple points used so the load stays level.
- Anti-two-block device
- A safety device that stops hoisting when the hook block approaches the boom tip, preventing rope damage and load loss; it must be tested before each shift.
- Load moment indicator
- An instrument that measures load and radius, computes load moment, and warns or stops operation when the chart's allowable moment is approached or exceeded.
- Frequent inspection
- A documented inspection at intervals set by the manufacturer or standard, covering items not visible in the daily walkaround, performed by a qualified person.
- Wire rope removal criteria
- Published limits on broken wires per lay length, diameter reduction, and corrosion; exceeding any criterion requires removing the rope from service.
- Designated signal person
- The single qualified person assigned to direct the operator; anyone may give a stop signal, but only the designated person gives other commands.
- Emergency stop signal
- A signal any person may give at any time to halt crane motion immediately; the operator must obey it without question and resume only when safe.
- Lift plan briefing
- A pre-lift meeting covering load weight, rigging, radius, path, set-down, signals, and emergency stop, attended by operator, rigger, and signal person.
- Suspended load rule
- A load must never be carried over personnel and must be kept as low as practical; the operator never leaves the station with a load suspended.
- Load moment
- The product of load weight and radius from the center of rotation; it is compared against the chart's allowable moment for the crane's configuration.
- Dynamic load factor
- The increase in effective load caused by acceleration, deceleration, or swing; smooth operation keeps it low, while sudden stops amplify it.
- Actual operating radius
- The horizontal distance from the center of rotation to the load's center, which grows with boom deflection and must be measured, not assumed.
- Trial lift
- Raising the load a few inches to verify stability, brake holding, rigging balance, and chart compliance before committing to the full lift path.
- Quadrant rating
- A load chart limit that depends on which side of the crane the load is over, such as over the front, rear, or side; the lower applicable rating governs.
- Power line contact response
- Stay in the cab, warn others away, and avoid touching the crane and ground together; if exit is necessary, jump clear and shuffle away.
- Emergency lowering procedure
- The manufacturer's documented method for lowering a boom or load without engine power, using emergency controls or a controlled bleed-down.
- Incident scene preservation
- Securing the area and recording conditions after an incident so investigators can determine cause; equipment is not moved unless needed to prevent harm.
- Near-miss reporting
- Documenting an event that did not cause harm but could have; it is a leading indicator used to correct hazards before a serious incident occurs.
- Operator qualification
- Documented training and competency for the specific crane type, including load chart use, inspection, and safe operation, required before operating.
- Refusal of unsafe lift
- The operator's responsibility to stop a lift when the plan, signals, or conditions are unsafe, and to escalate rather than proceed.
- Load test certificate
- A record showing the crane and its safety devices were tested at the required interval and met the standard; it must be available for inspection.
- Manufacturer's manual authority
- The operator manual and load charts govern capacity and configuration; site rules may be stricter but cannot authorize exceeding the manufacturer's limits.
- Smooth control inputs
- Feathering the controls and avoiding simultaneous opposing motions reduces swing, dynamic amplification, and the risk of losing control of the load.
- Blind lift requirement
- When the operator cannot see the load, a signal person with a clear view or a documented alternative is required; otherwise the lift stops.
- Swing lead and brake