Fast-Track Tenant Improvement: RFI, Substitution, and Owner Direct Purchase

A tenant improvement project is in construction with a fixed-fee architect's contract that ends at permit issuance; construction administration is not included. In week 6, the contractor submits an RFI noting that the reflected ceiling plan shows a 9 ft ceiling in the corridor but the mechanical drawings require 8 ft 6 in for ductwork. The same week, the contractor requests a substitution for the specified luxury vinyl tile with a product that has a thicker wear layer but a different fire rating. The owner separately tells the architect that it will purchase the reception desk directly from a furniture vendor to save money. The contractor is pressuring for a response because the ceiling grid is scheduled for delivery in five days. The architect has not visited the site since permit issuance.

1. How should the architect respond to the RFI, given that construction administration is not in the contract?

Read the worked answer

The architect should first check the contract and the request for information against the scope of services. If construction administration is excluded, the architect is not obligated to provide field review, but the RFI concerns a design conflict between the ceiling plan and the mechanical drawings, which is the architect's design responsibility. The architect should not give an oral direction or let the contractor proceed on an assumption. The proper step is to notify the owner in writing that responding to the RFI is beyond the basic scope and request authorization for the additional service. If authorized, the architect reviews the drawings, determines whether the 9 ft corridor ceiling can be maintained by rerouting or resizing ductwork, and issues a written response. If the ceiling must drop to 8 ft 6 in, the architect evaluates code height, door heights, sprinkler coverage, and light-fixture layout, then issues a supplemental instruction or sketch. The five-day pressure does not justify skipping the written record. The architect should also recommend a site visit if field conditions are part of the conflict.

2. Evaluate the substitution request. What information would you require, and what recommendation would you make?

Read the worked answer

A substitution request is not just a product comparison; it is a change to the contract documents. I would require a formal substitution request with product data, fire test reports, wear-layer and warranty information, maintenance requirements, VOC or indoor-air-quality data, and a sample. The critical issue is the different fire rating. If the specified tile is part of a rated floor assembly or is required to meet a flame-spread limit, a product with a different rating cannot be approved without checking the assembly and the code path. The thicker wear layer may be an advantage in durability, but it does not compensate for a life-safety difference. I would also compare schedule, cost, and availability, because the contractor may be using the substitution to solve a lead-time problem. My recommendation would be to reject the substitution as not equivalent unless the manufacturer provides a listed assembly or test report showing the required rating, and the owner accepts any change in appearance, maintenance, and warranty. If the product is equivalent or better and the fire rating is documented, I would recommend approval to the owner in writing, with the condition that the contractor accepts responsibility for coordination and warranty.

3. The owner wants to buy the reception desk directly. What professional-practice issues should the architect raise, and how should the architect document the decision?

Read the worked answer

The architect should explain that direct owner purchase changes the contractual chain. The owner will hold the purchase contract with the furniture vendor, while the contractor may be asked to receive, store, and install the desk. That arrangement creates gaps in responsibility for damage, delay, warranty, and insurance. If the desk is damaged after delivery, the contractor may deny responsibility because it did not purchase the item; the vendor may blame the site. The architect should recommend a written responsibilities matrix: who buys, who receives, who inspects, who stores, who installs, who insures, and who warrants. The owner should also confirm that the desk meets the specification and the fire code, especially if it is in an egress path or a rated corridor. The architect should document the owner's decision in a letter or meeting minutes, state that the architect is not providing procurement or installation services, and note that the contractor's schedule and coordination obligations must be adjusted. If the owner wants the architect to coordinate the vendor, that is an additional service. The architect should not simply accept a verbal instruction, because the decision affects cost, schedule, and liability.