NEBB Building Systems Commissioning Certified Professional flashcards
NEBB Building Systems Commissioning Certified Professional · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Owner's Project Requirements
- The written document defining the owner's intended use, performance criteria, schedules, and documentation needs; it is the benchmark against which all commissioning verification is measured throughout the project.
- Basis of Design
- A document recording design assumptions, system selection rationale, calculations, and sequences of operation, and explaining how the design satisfies each item in the Owner's Project Requirements.
- Commissioning Plan
- The project-specific document defining scope, team roles, schedule, documentation, test procedures, acceptance criteria, and reporting structure for the entire commissioning process from pre-design through occupancy.
- Pre-Functional Checklist
- A static verification form completed before functional testing that documents installation completeness, nameplate data, alignment, rotation, cleanliness, and sensor calibration for each component or system.
- Functional Performance Test
- A dynamic test that operates a system through its sequence of operations, including staging, safeties, interlocks, alarms, and failure modes, with calibrated instruments and recorded results against acceptance criteria.
- Commissioning Authority
- The independent party leading the commissioning process, reporting to the owner, with no conflict of interest in design or construction, responsible for findings, testing oversight, and the final report.
- Issues Log
- A tracked register of commissioning findings recording description, location, responsible party, date opened, severity, corrective action, and verified closure date for each item.
- Seasonal or Deferred Testing
- Testing that cannot be completed at acceptance because required conditions are absent, such as peak heating or cooling, scheduled for later completion and documented as an open item.
- Systems Manual
- The compiled operations and maintenance documentation delivered to the owner, including sequences of operation, setpoints, schedules, as-built controls information, and troubleshooting guidance for facility staff.
- Substantial Completion
- The project milestone at which the work is sufficiently complete for its intended use; commissioning prerequisites typically include closed critical issues, completed training, and delivered documentation.
- Retro-Commissioning
- A commissioning process applied to an existing building that was not commissioned when new, focused on identifying low-cost operational improvements and resolving deficiencies without major capital work.
- Ongoing Commissioning
- A continuous process using monitoring-based tools and periodic re-verification to sustain performance after initial commissioning, tracking trends and re-testing systems when operation drifts from intent.
- Point-to-Point Check
- A controls verification confirming each physical input and output is wired and addressed to the correct controller point, performed before functional testing of control sequences.
- Sequence of Operations
- The written control logic describing how equipment responds to setpoints, schedules, and conditions, including staging, safeties, interlocks, and alarms; it defines the expected behavior tested during functional performance.
- Test Acceptance Criteria
- Predefined measurable conditions, such as setpoint tolerance, airflow range, or response time, that a functional test must meet for the tested system to be accepted by the commissioning team.
- Readiness Review
- A construction-phase meeting confirming prerequisites are met - checklists complete, startup done, controls calibrated, test procedures approved - before functional performance testing begins.
- Design Review Finding
- A documented commissioning comment identifying a gap between the Basis of Design and Owner's Project Requirements or a constructability issue, resolved by the design engineer before construction proceeds.
- Controls Integration Test
- A functional test verifying communication and coordinated operation between separate control systems, such as BAS-to-fire-alarm shutdown, BAS-to-generator start, or chiller plant-to-BAS staging.
- Calibrated Test Instrument
- Measuring equipment with documented calibration traceable to a recognized standard, required for functional testing so recorded data are defensible and acceptance decisions are reliable.
- Commissioning Specification
- The contract language in Division 01 and technical sections defining contractor commissioning responsibilities, submittal requirements, test participation, training obligations, and schedule impacts.
- Contractor Self-Test
- Startup and checkout performed by the installing contractor and documented on pre-functional checklists, establishing that equipment is ready for independent functional performance testing by the commissioning team.
- Final Commissioning Report
- The closing deliverable summarizing scope, tests performed, results, issues and their resolution, deferred items, training completed, and a statement of systems verified against the Owner's Project Requirements.
- Owner Training Verification
- Documented confirmation that facility staff received instruction on operation, maintenance, and troubleshooting, with attendance records and agenda tied to the systems manual content.
- Warranty Review
- A near-end-of-warranty inspection and interview confirming systems still operate as commissioned, identifying failures or drift, and documenting corrective actions before warranty coverage expires.
- Lessons Learned Session
- A closing review with the project team capturing what worked and what did not in design, construction, and commissioning, producing recommendations for future projects and ongoing operation.
- Airflow Measurement Station
- A duct-mounted array of total and static pressure sensors producing an averaged flow signal; commissioning verifies its accuracy against a pitot-tube traverse and corrects the flow coefficient.
- Pitot-Tube Traverse
- A duct airflow measurement using a grid of velocity pressure readings across the duct cross-section, averaged to compute velocity and volume; used to verify installed airflow stations and fan capacity.
- Economizer Functional Test
- A test driving the economizer through changeover conditions to verify damper modulation, minimum position, actuator stroke, and lockout, confirming free cooling engages and disengages per the sequence.
- Chiller Plant Staging Test
- A functional test verifying automatic sequencing of chillers, pumps, and towers, including lead-lag rotation, capacity addition and removal, and safeties, with recorded flows, temperatures, and power.
- VAV Box Functional Test
- A test verifying airflow setpoint tracking, damper and reheat response, minimum and maximum airflow limits, and calibration of the airflow sensor at each terminal unit.
- Trend Log Verification
- Review of BAS trend data to confirm sequences operated as intended over time, capturing conditions that a short functional test cannot, such as cycling, staging, and night setback behavior.
- Deferred Test Log
- A register listing functional tests postponed for missing conditions, with the required condition, responsible party, planned date, and closure evidence, tracked until completed and reported.