Tax-season rumination in a small accountancy practice

NEBOSH Working with Wellbeing · Put your knowledge to work in context.

All case studies

Tax-season rumination in a small accountancy practice

You are office manager in a nine-person accountancy practice. From January to March, staff work 55–60 hours a week, including Saturdays. Two staff have disclosed anxiety; one had a panic attack in the toilet last week. Sickness absence has risen from 2% to 6%, and two clients have moved deadlines forward. The senior partner has emailed all staff saying mindfulness apps are a waste of time and the deadline is the issue. Staff say they cannot switch off, replay client calls at night and average 5.5 hours' sleep. There is no quiet room; the only meeting room is used for client calls. The practice has no HR function. You have £300 and 30 minutes at the next team meeting. What do you do?

1. Is mindfulness an appropriate response here? Justify your answer, including what it can and cannot address.

Read the worked answer

Partly. Mindfulness can help with the rumination the staff describe: replaying client calls at night and being unable to switch off. Brief practices can reduce physiological arousal and give people a way to notice thoughts without being pulled into them. But it cannot fix 55–60-hour weeks, two moved client deadlines, a 6% sickness rate, or a senior partner who dismisses the issue. If it is offered as the main answer, it becomes a way of putting responsibility on individuals and may increase cynicism. The panic attack and disclosed anxiety need a different response: confidential support, occupational health, reasonable adjustments and a workload conversation. The reason to be careful is that mindfulness is most useful as an adjunct to work design, not a substitute. So I would support a small, voluntary practice, but only alongside a deadline triage, overtime limits and rest breaks.

2. Design a 30-minute session and a four-week follow-up that fit the constraints, and explain how you would avoid it becoming a tick-box exercise.

Read the worked answer

Use the 30 minutes for a practical, optional session, not a lecture. Five minutes: explain the aim and the limit, namely that this is not a cure for workload. Ten minutes: a three-minute breathing space, practised twice, with eyes open if anyone prefers. Ten minutes: a noticing exercise using a routine task such as making a drink, to show how attention can be anchored. Five minutes: agree one realistic practice each person will try, such as a one-minute pause before opening email or a short walk without a phone. Do not use an app as the main delivery; the senior partner has already dismissed that. Find a quiet space: the meeting room before 09:00 or a screened corner, not the toilet. Four-week follow-up: a 10-minute check-in at the start of an existing meeting, a voluntary buddy pair, and a simple rating of sleep and switching off. To avoid a tick-box, keep attendance voluntary, do not collect individual disclosures, have the senior partner attend at least once, and report only aggregate feedback. If the partner refuses, run it as a pilot with six volunteers and share the results.

3. The senior partner says the deadline is the issue. How do you respond and what organisational actions do you recommend?

Read the worked answer

Agree with the diagnosis and use it. The deadline is the issue, so the response has to include workload: triage the two moved deadlines, agree with clients what can move, cap Saturday working for four weeks, and enforce a minimum break. The senior partner's own behaviour is a control: if they email at 23:00, staff will match it. Recommend a daily 15-minute stand-up to prioritise, a named person for client escalations, and a confidential route to occupational health. For the two staff with anxiety, offer a private conversation and reasonable adjustments; do not require them to disclose to the whole team. Mindfulness can sit alongside as a short, voluntary practice, but the primary measures should be hours worked, breaks taken, sickness absence and sleep. Report these to the partner weekly. If the partner will not reduce workload, document the risk and escalate to whoever has responsibility for health and safety, because the current pattern is not sustainable.