CPE II flashcards
CPE II · Build recall with a focused review session.
31 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Design factor (safety factor)
- Ratio of failure strength to allowable stress. It accounts for uncertainty in loads, material properties, and analysis methods; higher values are used where consequences of failure are severe.
- Critical path
- The longest-duration sequence of dependent activities through a project network. Its total float is zero, so any delay on it delays the project completion date.
- Total float
- Late start minus early start, or late finish minus early finish, for an activity. It is the time an activity can slip without delaying the project finish date.
- Cost Performance Index
- CPI equals earned value divided by actual cost. A value below 1.0 means work is costing more than planned; it can forecast estimate at completion.
- Euler buckling load
- P_cr = pi squared times E times I divided by (K times L) squared. It predicts elastic instability of a slender column; K depends on end restraint conditions.
- Reynolds number
- Re = density times velocity times diameter divided by viscosity. It indicates flow regime: laminar below about 2300 in pipes, transitional to turbulent above about 4000.
- Poisson's ratio
- Negative ratio of lateral strain to axial strain in uniaxial loading. For isotropic materials it relates shear modulus and bulk modulus to elastic modulus.
- Bernoulli equation
- For steady incompressible flow along a streamline, pressure head plus velocity head plus elevation head is constant, minus losses. It supports pitot and orifice calculations.
- Process capability Cpk
- Cpk is the minimum of the upper and lower specification distances divided by three sigma. Unlike Cp, it penalizes a process whose mean is off-center.
- PDCA cycle
- Plan-Do-Check-Act, the Deming improvement cycle. Improvements are standardized only after the Act stage confirms results; it underlies most quality management systems.
- FMEA RPN
- Risk Priority Number equals Severity times Occurrence times Detection, each scored on a defined scale. Higher RPN values prioritize corrective actions in failure mode analysis.
- Pareto analysis
- Ranking causes in descending frequency shows that a small number of causes produce most effects. Teams target the vital few causes first rather than the trivial many.
- Hierarchy of controls
- Risk control ranked by effectiveness: elimination, substitution, engineering controls, administrative controls, then personal protective equipment as the least reliable barrier.
- Lockout tagout
- Hazardous energy control procedure: isolate all energy sources, apply locks and tags, then verify zero energy before work. Only the applying worker removes their lock.
- Confined space entry
- Entry into a space with limited egress and hazardous atmosphere potential requires testing, a permit, an attendant, and a rescue plan before entry begins.
- ALARP principle
- Reduce risk to as low as reasonably practicable. Residual risk is documented and accepted after comparing control cost against risk reduction benefit.
- Capital recovery factor
- Converts present worth to equivalent uniform annual cost: A = P times i(1+i)^n divided by [(1+i)^n minus 1]. Used in annual cost comparisons of alternatives.
- Net present value
- Sum of discounted cash flows at the hurdle rate. Independent projects with positive NPV are economically acceptable; higher NPV is preferred among mutually exclusive options.
- Internal rate of return
- Discount rate at which project net present value equals zero. Accept when IRR exceeds the minimum attractive rate of return, subject to project comparability.
- Lump-sum contract
- Fixed-price agreement for defined scope. The contractor bears most cost-overrun risk, so the owner pays a premium for scope certainty and low change volume.
- Paramountcy obligation
- The duty to hold public health, safety, and welfare paramount over employer, client, and personal interest when professional judgment conflicts with commercial pressure.
- Conflict of interest disclosure
- Reveal financial or personal interests that could impair objectivity, then recuse from decisions where judgment is compromised. Undisclosed conflicts breach professional conduct rules.
- Whistleblowing escalation
- Report concerns internally first through defined channels. External disclosure is justified when imminent public safety risk persists and internal remedies have failed.
- Closed-loop communication
- Sender transmits instruction, receiver repeats it back, sender confirms accuracy. It prevents error in high-consequence handoffs such as field instructions and shift changes.
- As-built documentation
- Records actual installed geometry, materials, and deviations from design drawings. It supports operations, maintenance, and future modification work after handover.
- Document control revision codes
- Unique document numbers plus revision identifiers track changes. Controlled distribution retrieves or voids superseded copies so obsolete information cannot be used.
- ALCOA+ data integrity
- Records must be attributable, legible, contemporaneous, original, and accurate, plus complete, consistent, enduring, and available. It underpins regulated engineering records.
- Digital twin
- A virtual model linked to asset data and real-time condition. It supports maintenance planning, performance analysis, and lifecycle decisions for physical systems.
- Tolerance stack-up
- Worst-case assembly variation is the sum of component tolerances. Statistical stack-up uses the root-sum-square of independent tolerances for a more realistic variation estimate.
- Verification versus validation
- Verification confirms the design meets stated requirements. Validation confirms the delivered system meets the user's actual intended use in its operating environment.
- Three-phase power
- Real power P equals square root of three times line voltage times line current times power factor. Power factor is the cosine of the voltage-current phase angle.