CPE II study materials
CPE II study resources

CPE II: Engineering Economics, Costing, and Contracts

CPE II · Work through your exam, one topic at a time.

All guide sections

Engineering Economics, Costing, and Contracts

This domain tests economic comparison, cost estimating, and contract risk. Expect cash-flow, NPV, payback, depreciation, lifecycle cost, and contract-type questions tied to project decisions.

Core rules and concepts

  • Convert cash flows to a common time basis using present worth, future worth, or equivalent annual worth at the MARR.
  • NPV = PV benefits − PV costs; accept independent projects with NPV>0; for mutually exclusive alternatives, choose the highest NPV or equivalent annual worth when lives differ.
  • IRR is the rate making NPV zero; do not rank mutually exclusive projects by IRR alone.
  • Payback ignores time value and cash flows after payback; use it as a screening measure, not the sole decision rule.
  • Contract types allocate risk: fixed-price shifts cost risk to the contractor; cost-reimbursable shifts it to the owner; T&M is suited to uncertain scope.
  • Include escalation, taxes, salvage, and lifecycle costs only when they are relevant and consistent.

Worked example

Invest $100,000; savings $30,000/year for 5 years; MARR 10%. Annuity factor=(1−1.1^−5)/0.10=3.7908. PV savings=30,000×3.7908=$113,724. NPV=113,724−100,000=$13,724>0, so accept. Reasoning: compare all cash flows at the same discount rate; undiscounted savings of $150,000 overstates value.

Traps that cost marks

  • Comparing alternatives with unequal lives by total NPV without annualizing.
  • Including sunk costs in the decision.
  • Mixing escalation rates with the discount rate.
  • Treating IRR ranking as valid for mutually exclusive projects.
  • Ignoring contract risk allocation.