NICET IBPSC study materials
NICET IBPSC study resources

NICET IBPSC cheat sheet

NICET IBPSC · Keep the key ideas within reach.

Quick reference

Project Planning, Documentation, Codes and Standards

  • Applicable model codes: NFPA 1 (Fire Code), NFPA 13/13R/13D (sprinklers), NFPA 14 (standpipes), NFPA 20 (fire pumps), NFPA 25 (ITM of water-based systems), NFPA 72 (detection/alarm), NFPA 10 (extinguishers), NFPA 2001/12/17/17A (special suppression), NFPA 92 (smoke control), NFPA 110 (emergency power).

  • NFPA 25 is the ITM baseline; the edition adopted by the AHJ governs, not necessarily the newest edition, and the system's design/installation standard governs repair criteria.

  • Frequency rule of thumb in NFPA 25: weekly/monthly for pumps and some valves, quarterly for gauges/alarm devices, semiannual for some switches, annual for most components, 5-year for internal pipe inspection and gauge replacement, 20-year for sprinkler replacement/testing.

  • Impediment vs. deficiency: an impediment prevents the system from performing as designed and requires correction and notification; a deficiency is a condition that could impair performance and is scheduled for correction.

  • Plan submittal package typically includes hydraulic calculations, shop drawings, manufacturer data sheets, and material/component listings; acceptance testing requires the contractor's test documentation and AHJ witness.

  • Record retention per NFPA 25 is typically 1 year on site for most inspection records, with records made available to the AHJ upon request; keep design/acceptance documents for the life of the system.

  • Pre-plan ITM scope by system inventory: count devices, heads, valves, pumps, and extinguishers to estimate labor and schedule frequencies against NFPA 25 Table 5.1.1.

  • Coordination documents: work order, ITM scope, AHJ permit, impairment permit, and hot work permit; each system impairment should be logged with start/end time and affected areas.

Quick reference

Inspection and Testing of Water Supplies and Fire Pumps

  • NFPA 25 ch. 7-8 governs water supply and fire pump ITM; NFPA 20 governs installation and acceptance. Weekly no-flow churn run for electric pumps; diesel pumps run weekly for at least 30 minutes.

  • Annual flow test: pump must deliver at least 100% of rated flow at 100% rated pressure, and 150% of rated flow at not less than 65% of rated pressure (NFPA 20 acceptance criteria).

  • Churn (no-flow) pressure should not exceed 140% of rated pressure; if it does, the pump or driver may need adjustment or the relief valve checked.

  • Weekly churn test records suction pressure, discharge pressure, and (for diesel) oil pressure, coolant temperature, battery voltage, and run time.

  • Diesel driver monthly/weekly checks: fuel level, oil level, coolant level, battery electrolyte and charger, and engine starting battery voltage; annual load test at 100% for at least 30 minutes (or per NFPA 25).

  • Suction supply: verify static and residual pressure, check for vortexing or air entrainment, and confirm the water supply curve meets the system demand plus hose stream allowance.

  • Flow meter test (where installed) may substitute for hose stream flow tests; verify meter calibration and compare to pump curve at multiple points.

  • Fire pump controller: verify automatic and manual start, weekly automatic start test, and annual test of the alternate power source under load.

Quick reference

Inspection and Testing of Sprinkler Systems

  • NFPA 25 Table 5.1.1 frequencies: weekly for dry-pipe/ preaction gauges and alarm valves; monthly for control valves and gauges; quarterly for alarm devices and waterflow switches; annual for main drain test and most components.

  • Main drain test: record static and residual pressure; a significant drop from baseline indicates an obstruction or supply problem. Compare to the original acceptance test values.

  • Control valves must be verified open (locked or supervised); a closed valve is an impairment requiring immediate correction and notification.

  • Sprinkler head inspection: check for corrosion, paint, damage, loading, and correct orientation; replace heads showing signs of leakage or damage. Replace dry pendent heads every 10 years and quick-response heads at 20 years or per manufacturer.

  • Spare head stock: minimum 6 spare heads for systems up to 300 heads, 12 for 300-1000, and 24 for over 1000 heads (NFPA 13/25).

  • Gauge replacement every 5 years; internal pipe inspection every 5 years (or as required by the AHJ); dry-pipe systems require internal inspection and trip testing more frequently.

  • Dry-pipe and preaction systems: trip test annually (dry pipe) and verify priming water level, air pressure, and low-point drains; check air compressor operation and air pressure maintenance.

  • Hydraulic design verification: confirm the system demand (including hose allowance) does not exceed the available water supply; re-evaluate after any modification.

Quick reference

Inspection and Testing of Standpipe and Hose Systems

  • NFPA 25 ch. 6 governs standpipe and hose system ITM; NFPA 14 governs installation and design.

  • Class I: 2.5-inch outlets for fire department use; Class II: 1.5-inch hose stations for occupant use; Class III: both.

  • Hydrostatic test at acceptance: 200 psi for 2 hours (or 50 psi above maximum pressure if higher); periodic 5-year hydrostatic testing per NFPA 25 for some systems.

  • Flow test: verify the hydraulically most remote outlet provides the required pressure and flow (typically 100 psi residual at the topmost outlet for Class I systems, per NFPA 14 design).

  • Hose valve and hose station inspection: check for leaks, correct caps, proper hose condition, nozzle presence, and accessibility; hose should be inspected annually and replaced per manufacturer.

  • Control valves and pressure-reducing valves: verify open position and correct downstream pressure; PRVs require annual testing and 5-year full flow testing.

  • Drains and low-point drains: verify operation and no standing water in dry standpipes; check for freezing protection in cold climates.

  • Fire department connection (FDC): check for caps, clappers, and unobstructed access; verify signage and that the FDC is not obstructed by vehicles or landscaping.

Quick reference

Inspection and Testing of Fire Detection, Alarm, and Notification Systems

  • NFPA 72 governs ITM; inspection, testing, and maintenance frequencies are in Table 14.4.3.2.

  • Smoke detectors: annual functional test (or per manufacturer); sensitivity testing within 1 year of installation and every 2 years thereafter (or per NFPA 72).

  • Heat detectors: annual test; verify alarm setpoint and response.

  • Manual pull stations: annual test; verify alarm transmission and reset.

  • Notification appliances: annual test of audibility and visibility; verify candela ratings and dB levels meet design criteria (typically 15 dBA above ambient or 75 dBA minimum).

  • Batteries: annual load test; verify voltage, charging current, and capacity; replace per manufacturer's recommended interval (often 3-5 years).

  • Supervising station and transmission: verify signal transmission to central station and correct signal handling; test both primary and backup communication paths.

  • Record of completion (NFPA 72 Form) and as-built documentation should be retained and updated after any modification.

Quick reference

Inspection and Testing of Special Suppression Systems and Portable Extinguishers

  • NFPA 10: portable extinguishers require monthly visual inspection and annual maintenance; hydrostatic testing at 5 or 12 years depending on extinguisher type (e.g., 5 years for CO2 and water, 12 years for dry chemical stored-pressure).

  • Extinguisher selection: Class A (ordinary combustibles), B (flammable liquids), C (electrical), D (combustible metals), K (cooking oils); verify correct type and size for hazard.

  • Clean agent systems (NFPA 2001): annual inspection and test; verify agent quantity, container pressure, and discharge nozzle condition; weigh containers or check pressure gauges.

  • CO2 systems (NFPA 12): annual inspection; verify agent quantity by weight or liquid level, check discharge piping and nozzles, and test alarms and interlocks.

  • Wet chemical kitchen systems (NFPA 17A): semiannual inspection and test; verify agent quantity, fusible links, and manual pull station operation.

  • Dry chemical systems (NFPA 17): semiannual inspection; verify agent quantity, expellant gas pressure, and piping condition.

  • Water mist systems (NFPA 750): annual inspection; verify pressure, nozzle condition, and pump operation.

  • Records: keep inspection tags, certificates, and maintenance reports; tag extinguishers with the month/year of last service.

Quick reference

Inspection and Testing of Smoke Control and Emergency Power Systems

  • NFPA 92 governs smoke control systems; acceptance testing includes verifying design pressure differences, airflow, and fan operation.

  • Annual testing of smoke control systems: verify fan operation, damper position, and pressure differentials; test under both normal and emergency power.

  • Stairwell pressurization: verify pressure differential (typically 0.05-0.10 in. w.c. or per design) and door opening force (max 30 lbf per ADA/NFPA 101).

  • Emergency power (NFPA 110): Level 1 systems require monthly exercise under load (at least 30 minutes) and annual load test; verify fuel, battery, and cooling system.

  • Generator testing: verify automatic start, transfer switch operation, and load acceptance; test at least monthly and annually under full load.

  • Battery systems: verify voltage, specific gravity, and charging; perform annual capacity test.

  • Documentation: maintain logs of all tests, including date, time, duration, and results; make available to the AHJ.

  • Coordination: notify the AHJ and building occupants before testing smoke control or emergency power systems; verify that testing does not create a false alarm or unsafe condition.

Quick reference

Reporting, Record Keeping, and Coordination with Authorities

  • NFPA 25 requires written reports of inspection and testing; retain records for at least 1 year on site and make available to the AHJ upon request.

  • Deficiency reports should identify the system, component, condition, and recommended corrective action; classify as impediment or deficiency.

  • Impairment procedures: notify the AHJ, building owner, and occupants; implement a fire watch or interim measures if the system is out of service.

  • Coordination with the AHJ: obtain permits for installation, modification, and impairment; schedule acceptance tests with the AHJ present.

  • Record of completion (NFPA 72) and as-built drawings should be updated after any change and retained for the life of the system.

  • ITM reports should be signed by the qualified technician and include the date, system identification, and test results.

  • Electronic record keeping is acceptable if retrievable and secure; verify the AHJ accepts electronic records.

  • Post-incident: document any fire event, system activation, or failure and provide a report to the AHJ and insurer as required.