Authority Having Jurisdiction (AHJ)

The organization, office, or individual with legal authority to approve equipment, installations, and procedures - typically the fire marshal or building official who enforces the adopted code.

Related: Plan Review, Code Modification (Variance)
Occupancy Hazard Classification

A code grouping - light hazard, ordinary hazard Groups 1 and 2, extra hazard Groups 1 and 2, or storage - based on expected fuel load and burning rate that sets design density and sprinkler rules.

Related: Commodity Classification, Design Density
Commodity Classification

A ranking of stored goods by material, packaging, and plastic content - Class I through IV plus plastics - used to select sprinkler protection for storage occupancies.

Related: Occupancy Hazard Classification, ESFR Sprinkler
Plan Review

The formal check of submitted sprinkler plans against the adopted code and standards before construction; reviewers verify hydraulics, spacing, and details, then approve or issue comments.

Related: Working Plans, Authority Having Jurisdiction (AHJ)
Code Modification (Variance)

A written, AHJ-approved alternative to a specific code requirement, backed by technical justification showing the proposed approach provides equivalent or greater safety.

Related: Authority Having Jurisdiction (AHJ), Plan Review
Working Plans

Scaled drawings submitted for approval showing piping, sprinkler locations, hangers, and hydraulic calculations; they must be complete and signed by the responsible designer before installation begins.

Related: Plan Review, Shop Drawings
Design Density

The minimum flow, in gallons per minute per square foot, applied over the design area at the most remote sprinklers; it is selected from the occupancy hazard.

Related: Design Area, Density/Area Method
Design Area

The assumed set of sprinklers flowing simultaneously for calculation, chosen at the hydraulically most demanding location; its size depends on hazard and sprinkler response type.

Related: Design Density, Density/Area Method
Density/Area Method

A design approach that pairs a chosen water density with a corresponding operating area; typically, selecting a higher density permits a smaller design area.

Related: Design Density, Design Area
Hazen-Williams Formula

An empirical equation for friction loss in water-filled pipe using flow rate, inside diameter, pipe length, and roughness coefficient; it is the basis of most sprinkler hydraulic calculations.

Related: C-Factor, Friction Loss
C-Factor

The roughness coefficient used in the Hazen-Williams equation; smoother pipe such as cement-lined or plastic has a higher C and produces less friction loss.

Related: Hazen-Williams Formula
K-Factor

A sprinkler's discharge coefficient in the relationship Q = K times the square root of pressure; it indicates how much flow a head delivers at a given pressure.

Related: Design Density, ESFR Sprinkler
Static Pressure

Pressure measured at a hydrant or supply point with no water flowing; combined with residual pressure from a flow test, it defines the water supply.

Related: Residual Pressure, Water Supply Curve
Residual Pressure

The pressure remaining at a hydrant or gauge point while water is flowing during a flow test; it shows how much the supply drops under demand.

Related: Static Pressure, Water Supply Curve
Water Supply Curve

A plotted relationship of available pressure versus flow at a reference point, derived from a flow test or pump data, used to compare supply against system demand.

Related: Static Pressure, System Demand
Safety Margin

Extra pressure deliberately kept between the available supply and the calculated demand - commonly 10 to 20 psi - to cover uncertainty, aging, and future changes.

Related: Water Supply Curve, System Demand
System Demand

The total flow and pressure the system needs at a reference point, combining sprinkler flow, friction and elevation losses, and hose allowance.

Related: Safety Margin, Hose Allowance, Friction Loss
Hose Allowance

A fixed flow added to the sprinkler demand for expected fire department hose streams; the amount is set by occupancy hazard and is not calculated hydraulically.

Related: System Demand
Friction Loss

Pressure lost as water travels through pipe, fittings, and devices due to resistance; it is calculated from flow rate, pipe size, and length.

Related: Hazen-Williams Formula, Elevation Loss
Elevation Loss

Pressure change caused by height difference, about 0.433 psi per foot of rise; it must be added when sprinklers sit above the supply point.

Related: Friction Loss, System Demand
Churn Pressure

The discharge pressure of a fire pump at zero flow, typically 100 to 140 percent of rated pressure; it is used to confirm system components can withstand it.

Related: Water Supply Curve, System Demand
Sprinkler Coverage Area

The floor area assigned to one sprinkler, equal to its spacing along the branch line times the spacing between branch lines; the code limits it by hazard.

Related: Sprinkler Spacing, Deflector Distance
Sprinkler Spacing

The maximum and minimum distances permitted between sprinklers and from sprinklers to walls; exceeding these limits can leave unprotected gaps or reduce performance.

Related: Sprinkler Coverage Area
Deflector Distance

The required clearance from a sprinkler deflector to the ceiling or roof; it lets the spray pattern form and controls how quickly hot gases reach the element.

Related: Sprinkler Spacing, Obstruction Rule
Obstruction Rule

Code provisions requiring additional sprinklers or relocation where beams, ducts, or similar items block spray, with exceptions for small or closely spaced obstructions near the ceiling.

Related: Deflector Distance
Branch Line, Cross Main, and Feed Main

The three piping tiers: branch lines carry sprinklers, cross mains supply branch lines, and feed mains carry water from the riser to the cross mains.

Related: Riser
Riser

The vertical supply pipe that brings water up to the system and holds the main control valve, check valve, alarm attachments, gauges, and test connections.

Related: Fire Department Connection (FDC), Branch Line, Cross Main, and Feed Main
Fire Department Connection (FDC)

An exterior piped connection where the fire department pumps supplemental water into the system; its size, location, and marking are code-regulated.

Related: Riser
ESFR Sprinkler

An early suppression fast response sprinkler with a large K-factor and high-momentum spray intended to suppress storage fires; strict rules govern clearance and storage height.

Related: Commodity Classification, K-Factor
Sway Bracing

Bracing that resists lateral and longitudinal pipe movement from water surge or seismic forces; required spacing and bracing types depend on pipe size and code edition.

Related: Shop Drawings
Hydraulic Placard

A sign mounted at the riser listing design density, design area, and required flows and pressures so inspectors and owners know the basis of the design.

Related: System Demand, Working Plans
Shop Drawings

Fabrication and installation drawings developed from approved working plans, showing exact pipe lengths, fittings, and support locations for the field crew.

Related: Working Plans, Clash Detection
Clash Detection

Comparing proposed sprinkler routing against structural, mechanical, and electrical drawings or models to find and resolve physical conflicts before pipe is installed.

Related: Shop Drawings
Hydrostatic Test

A pressure test of piping, commonly at 200 psi for two hours or 50 psi above working pressure, done before concealment to prove joints do not leak.

Related: Acceptance Test
Acceptance Test

The final series of on-site tests and inspections - flushing, hydrostatic, flow, alarm, and main drain tests - that show an installed system is ready for service.

Related: Hydrostatic Test, Material and Test Certificate
Material and Test Certificate

A contractor-signed record documenting flushing, hydrostatic testing, and related acceptance results, submitted to the AHJ as proof the installation met code.

Related: Acceptance Test, As-Built Drawings
As-Built Drawings

Record drawings updated after installation to show the system as actually constructed, including field changes, and turned over to the owner.

Related: Working Plans, Material and Test Certificate
Impairment

The documented process for taking a system out of service - notifying the AHJ and owner, posting a fire watch where required, and restoring service promptly.

Related: Authority Having Jurisdiction (AHJ)