NV General Contractor study materials
NV General Contractor study resources

NV General Contractor cheat sheet

NV General Contractor · Keep the key ideas within reach.

Quick reference

Business Management and Financial Responsibility

  • Working capital = current assets - current liabilities; it measures the funds available to meet near-term obligations.

  • Current ratio = current assets / current liabilities; a value below 1.0 indicates current liabilities exceed current assets.

  • Quick ratio = (cash + marketable securities + receivables) / current liabilities; inventory and prepaid items are excluded.

  • Gross profit = revenue - direct job costs; gross profit margin = gross profit / revenue.

  • Break-even revenue = fixed overhead / gross margin percentage; this is the revenue at which overhead is exactly covered.

  • Overhead allocation rate = total indirect overhead / selected direct cost base, such as direct labor dollars or direct labor hours.

  • Retainage is a percentage withheld from progress payments until completion or acceptance; it reduces cash received during the job.

  • Profit and cash flow differ: a profitable project can have negative cash flow because of retainage, slow payments, or front-loaded costs.

Quick reference

Nevada Contractor Licensing Law and Regulations (NRS 624 / NAC 624)

  • The Nevada State Contractors Board administers contractor licensing, investigates complaints, and enforces NRS 624 and NAC 624.

  • A qualifying party must meet experience requirements, pass the required examination, and be responsible for the licensee's construction work.

  • Nevada contractor licenses include Class A general engineering, Class B general building, and Class C specialty classifications.

  • The NSCB sets a licensee's monetary limit based on demonstrated financial responsibility; work may not be bid or contracted above that limit.

  • A contractor license bond and workers' compensation coverage are conditions of active licensure unless an exemption applies.

  • Contractor license numbers must appear in contracts, bids, and advertising so the public can verify licensure with the NSCB.

  • A licensee must notify the NSCB of changes in ownership, qualifying party, business address, or financial condition as required by regulation.

  • Unlicensed contracting is prohibited and may result in NSCB citations, administrative penalties, stop-work orders, or referral for prosecution.

Quick reference

Construction Practices, Estimating, and Project Management

  • A quantity takeoff measures materials and labor quantities from plans and specifications before unit prices are applied.

  • Labor cost = labor hours x wage rate x labor burden factor; burden includes payroll taxes, insurance, benefits, and paid time off.

  • Material cost estimate = net quantity x unit price x (1 + waste factor); waste varies by material and installation method.

  • Total float = late start - early start = late finish - early finish; critical-path activities have zero total float.

  • Cost Performance Index (CPI) = earned value / actual cost; CPI below 1.0 indicates cost overrun for work performed.

  • Schedule Performance Index (SPI) = earned value / planned value; SPI below 1.0 indicates work is behind schedule.

  • A change order must be written and authorized before performing changed work to preserve entitlement to payment and time.

  • A punch list records incomplete or defective work that must be corrected before final acceptance and final payment.

Quick reference

Jobsite Safety and Environmental Compliance

  • OSHA construction focus four hazards are falls, struck-by, caught-in or between, and electrical hazards.

  • OSHA generally requires fall protection at 6 feet for construction work; scaffold fall protection is required above 10 feet.

  • Excavations 5 feet or deeper require a protective system unless the excavation is entirely in stable rock.

  • Trenches 4 feet or deeper require a ladder, stair, or ramp so lateral travel to an exit is no more than 25 feet.

  • The Hazard Communication Standard requires chemical labels and Safety Data Sheets for hazardous chemicals on site.

  • Respirable crystalline silica controls include wet cutting, dust collection, ventilation, work practices, and respirators when needed.

  • A Stormwater Pollution Prevention Plan describes erosion, sediment, and pollution controls for construction stormwater discharges.

  • Nevada NDEP administers stormwater and environmental permits; concrete washout and fuel storage must be managed to prevent releases.

Quick reference

Jobsite Safety and Environmental Compliance

  • OSHA construction focus four hazards are falls, struck-by, caught-in or between, and electrical hazards.

  • OSHA generally requires fall protection at 6 feet for construction work; scaffold fall protection is required above 10 feet.

  • Excavations 5 feet or deeper require a protective system unless the excavation is entirely in stable rock.

  • Trenches 4 feet or deeper require a ladder, stair, or ramp so lateral travel to an exit is no more than 25 feet.

  • The Hazard Communication Standard requires chemical labels and Safety Data Sheets for hazardous chemicals on site.

  • Respirable crystalline silica controls include wet cutting, dust collection, ventilation, work practices, and respirators when needed.

  • A Stormwater Pollution Prevention Plan describes erosion, sediment, and pollution controls for construction stormwater discharges.

  • Nevada NDEP administers stormwater and environmental permits; concrete washout and fuel storage must be managed to prevent releases.