NV General Contractor · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Nevada Contractor Licensing Law and Regulations (NRS 624 / NAC 624)

  • Map the Nevada State Contractors Board licensing lifecycle by outlining each step from application to renewal in your own words

  • Define the roles of licensee, qualifying party, and responsible managing employee, and list the duties attached to each

  • Distinguish contractor license classifications and explain what each classification authorizes you to bid and perform

  • Identify the disciplinary grounds and penalties framework under NRS 624 and rank them by how often they appear in enforcement actions

Your checkpoint

A one-page licensing lifecycle flowchart plus a 30-term Nevada law glossary written from memory and then corrected against source text.

Week 2

Nevada Contractor Licensing Law and Regulations (NRS 624 / NAC 624) & Business Management and Financial Responsibility

  • Explain how a contractor's monetary limit is established and what triggers a change to it

  • Outline advertising, bidding, and contracting requirements that apply before work begins

  • Compare sole proprietorship, partnership, LLC, and corporation structures for licensing and liability consequences in Nevada

  • Draft the core clauses of a residential and a commercial prime contract from a blank page

Your checkpoint

Two complete sample contract outlines (residential and commercial) with a 15-item compliance checklist for pre-contract requirements.

Week 3

Business Management and Financial Responsibility

  • Build a chart of accounts and classify 40 sample transactions into correct cost codes

  • Compute overhead, markup, and break-even volume for two sample companies and explain why markup and margin differ

  • Prepare a simple balance sheet, income statement, and cash-flow statement from a supplied scenario

  • Trace the mechanics lien and payment-bond process from notice through resolution, listing each deadline as a trigger date

Your checkpoint

A completed financial workbook for one sample contracting company, including three statements, a break-even calculation, and a lien deadline timeline.

Week 4

Business Management and Financial Responsibility & Nevada Contractor Licensing Law and Regulations (NRS 624 / NAC 624)

  • Re-solve every missed item from Weeks 1-3 without notes and record the reason for each original error

  • Recite from memory the sequence of events that leads to license suspension or revocation and the appeal path

  • Calculate payroll burden, workers' compensation cost, and equipment ownership cost for three scenarios

  • Explain trust-fund and project-fund handling duties owed by a licensee to owners and subcontractors

Your checkpoint

A 50-question self-written practice test on Domains 1 and 2 with an answer key and citation for each question, scored at 80% or better on a retake.

Week 5

Construction Practices, Estimating, and Project Management

  • Perform a full quantity takeoff from a written scope description for concrete, framing, and finishes

  • Build a unit-price estimate and a lump-sum estimate for the same project and reconcile the difference

  • Sequence a 20-activity project into a critical-path schedule with durations, predecessors, and float identified

  • Write a project submittal, RFI, and change-order log procedure with defined approval thresholds

Your checkpoint

A complete estimate and CPM schedule for one small commercial project, with the takeoff quantities shown and float labeled on every activity.

Week 6

Construction Practices, Estimating, and Project Management & Jobsite Safety and Environmental Compliance

  • Evaluate soil, concrete, and structural steel quality-control test requirements and state the acceptance criteria for each

  • Explain inspection and testing responsibilities for the contractor versus the owner's representative

  • Identify the leading causes of struck-by, fall, electrical, and caught-in incidents and match each to a control measure

  • Draft a site-specific safety plan outline for a multi-employer site

Your checkpoint

A 12-page project management and safety binder section containing the schedule narrative, QC/inspection matrix, and a written site-specific safety plan outline.

Week 7

Jobsite Safety and Environmental Compliance

  • Outline the hierarchy of safety obligations: employer duty, competent-person role, training, recordkeeping, and reporting

  • Describe fall protection, scaffold, excavation, and confined-space requirements well enough to audit a scenario and cite the violation

  • Build a stormwater pollution prevention outline covering best management practices, inspections, and recordkeeping

  • Classify hazardous and regulated waste streams and state handling, storage, and disposal requirements for each

Your checkpoint

A one-page jobsite inspection checklist with 25 items across fall protection, excavation, electrical, and environmental controls, plus a corrected answer rationale for each.

Week 8

Business Management and Financial Responsibility & Nevada Contractor Licensing Law and Regulations (NRS 624 / NAC 624) & Construction Practices, Estimating, and Project Management & Jobsite Safety and Environmental Compliance

  • Complete two full-length timed practice exams under test conditions and log the domain of every missed item

  • Re-drill the 40 highest-missed concepts using spaced repetition across three separate days

  • Reconstruct the Nevada licensing, lien, and safety deadline timelines from memory on blank paper

  • Finalize a one-page formula and definition sheet you can review in the 48 hours before the exam

Your checkpoint

A final scorecard showing both practice exam scores, a ranked weak-area list with a fix for each, and the completed one-page formula sheet.

Milestones

Week 2: Explain the Nevada licensing lifecycle, classification system, and monetary limit aloud in under ten minutes with no notes and no factual gaps.

Week 4: Score 80% or higher on a closed-book 50-question test covering Domains 1 and 2, with every miss traced to a specific source provision.

Week 6: Produce a defensible estimate, CPM schedule, and safety plan outline for one project in a single sitting without reference material.

Week 8: Score 85% or higher on two consecutive full-length timed practice exams, with no single domain below 75%.