- Design density
- The minimum water flow rate in gpm per square foot applied over the hydraulically most demanding area; determined by hazard classification and used in hydraulic calculations.
- K-factor
- Sprinkler discharge coefficient equal to Q divided by the square root of pressure; a K-5.6 sprinkler at 7 psi flows about 14.8 gpm.
- Quick-response sprinkler
- Sprinkler with a Response Time Index of 50 or less, using a thin glass bulb or fusible link that activates faster than standard-response heads.
- Dry pipe system
- A sprinkler system with air or nitrogen under pressure in the piping and water held back by a dry pipe valve; used in spaces subject to freezing.
- Pendant sprinkler deflector
- Must be positioned at least 1 inch below a noncombustible ceiling and 2 to 12 inches below a combustible ceiling to allow the spray pattern to develop.
- Residential sprinkler
- Sprinkler listed for dwelling units with a lower design density and faster response, installed per NFPA 13R or 13D criteria.
- Class I standpipe
- Standpipe with 2½ inch outlets for fire department use, requiring 100 psi residual at the topmost outlet and 250 gpm per riser.
- Class II standpipe
- Standpipe with 1½ inch hose stations for occupant use, designed for 100 gpm at 65 psi residual pressure at the most remote outlet.
- Class III standpipe
- Combined system with both 2½ inch fire department outlets and 1½ inch occupant hose stations, sized to Class I hydraulic requirements.
- Standpipe hose travel
- All portions of a floor must be within 30 feet of a nozzle attached to 100 feet of 1½ inch hose, giving 130 feet total travel.
- Fire department connection
- Siamese connection allowing pumper apparatus to supplement the system; 3 inch for standpipe-only, 4 inch or larger when combined with sprinklers.
- Standpipe pressure regulation
- Pressure-reducing valves are required where residual pressure at an outlet exceeds 100 psi or static pressure exceeds 175 psi to protect occupants and equipment.
- Manual standpipe
- A standpipe system without a permanent water supply, permitted only in limited cases such as buildings under construction; must still deliver 100 psi at the top outlet.
- NFPA 13
- The standard for installation of sprinkler systems, covering hazard classification, design density, spacing, hydraulic calculation, and acceptance testing.
- NFPA 14
- The standard for installation of standpipe and hose systems, defining Class I, II, and III systems and their hydraulic requirements.
- NFPA 25
- The standard for inspection, testing, and maintenance of water-based fire protection systems, establishing intervals for valves, pumps, and gauges.
- NYC construction permit
- A Department of Buildings permit is required before installing or altering sprinkler or standpipe systems; final sign-off follows witnessed testing.
- NYC high-rise sprinkler rule
- Buildings 75 feet or more in height require automatic sprinkler protection throughout and a Class I standpipe with fire pump where pressure is insufficient.
- Fire pump acceptance test
- Test at churn, 100% rated flow, and 150% rated flow to verify the pump curve, suction conditions, and controller operation.
- Annual sprinkler inspection
- NFPA 25 requires annual inspection of sprinkler heads, pipe, and gauges, with records retained on site and available to the fire department.
- Hydrostatic test
- New systems are tested at 200 psi for 2 hours, or 50 psi above working pressure when that exceeds 150 psi, witnessed by the authority.
- Main drain test
- Comparing static and residual pressure at the main drain; a drop greater than 10 percent indicates a closed valve or obstruction in the supply.
- Underground flushing
- Underground mains are flushed at a velocity of at least 10 feet per second to remove debris before connection to the aboveground system.
- Control valve supervision
- Sprinkler control valves must be supervised open and inspected monthly, with tamper switches or locks to prevent unauthorized closure.
- Obstruction investigation
- Required every 5 years or when evidence suggests, by flushing the system and examining a representative pipe section for debris or tuberculation.
- Spare sprinkler cabinet
- Must contain spare heads of each type and temperature rating plus a wrench, kept in an accessible location per NFPA 13 requirements.
- Deflector clearance
- A minimum 18 inch clearance must be maintained below sprinkler deflectors to avoid obstruction of the spray pattern by stored materials.
- Flow switch test
- Annual test confirming the switch activates on water flow and sends an alarm signal to the fire alarm panel within the required time.
- Dry pipe valve trip test
- Annual test confirming the dry pipe valve opens and water reaches the test outlet within 60 seconds for systems of 750 gallons or less.
- Ordinary hazard Group 1
- Hazard classification with design density of 0.15 gpm per square foot over 1,500 square feet, covering occupancies such as parking garages.
- Extra hazard Group 2
- Highest hazard classification, requiring 0.40 gpm per square foot over 2,500 square feet, for occupancies with flammable liquids or severe combustibles.
- Sprinkler temperature rating
- Color-coded rating: ordinary 135 to 170°F, intermediate 175 to 225°F, high 250 to 300°F, selected to match the ambient ceiling temperature.