NZ Certificate in Carpentry flashcards
NZ Certificate in Carpentry · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Hierarchy of control
- Ranking of hazard controls from most to least effective: eliminate, substitute, isolate or engineer controls, administrative controls, and finally personal protective equipment. PPE is the last line of defence, never the first choice.
- Notifiable work threshold
- Under NZ health and safety rules, construction work over 5 metres deep, or where a person could fall 5 metres or more, must be notified to WorkSafe before starting.
- Fall protection trigger height
- Where a person could fall 3 metres or more, fall protection such as guardrails, scaffolds or a harness system must be provided. Ladders are access, not work platforms.
- Silica dust control
- Cutting concrete, brick or fibre cement releases respirable crystalline silica. Use water suppression or on-tool extraction plus a P2/P3 respirator. Dry sweeping spreads dust and is not acceptable.
- Sediment control on site
- Silt fences, stabilised entry and exit, covered stockpiles and contained washout water prevent sediment and slurry entering stormwater. Stormwater drains discharge untreated to waterways.
- Drawing scale conversion
- At 1:100, one millimetre on the drawing equals 100 millimetres on site. At 1:50 it equals 50 millimetres; at 1:20 it equals 20 millimetres. Always confirm the stated scale.
- 3-4-5 right angle method
- A triangle with sides of 3, 4 and 5 units (or multiples such as 6-8-10) has a right angle between the short sides. Used with a string line to set out square corners.
- Checking a rectangle square
- Measure both diagonals of the set-out rectangle. If the diagonals are equal, the corners are square. Any difference indicates the corners must be adjusted.
- Datum and level transfer
- A datum is a fixed reference level. Transfer levels with a dumpy or rotary level or total station rather than measuring up from the ground, which accumulates error.
- Stair riser and tread limits
- For common residential stairs under NZS 3604, riser height is typically 150-190 millimetres and tread depth 250-300 millimetres. Total rise divided by riser height gives the number of risers.
- Stud spacing under NZS 3604
- Timber wall studs are commonly spaced at 300, 400 or 600 millimetres centres. Closer spacing is required as wind zone, load and bracing demand increase.
- Notching and holes in members
- Under NZS 3604, notches must not exceed one quarter of member depth. Holes must not exceed one quarter of depth and must sit within the middle third of the depth.
- Bracing units (BU)
- NZS 3604 rates braced wall elements in bracing units. The total BU required depends on wind zone and floor area, and is distributed across the building's walls.
- Truss installation rule
- Roof trusses must be installed to the manufacturer's layout and fixing schedule. Top and bottom chords must never be cut or notched without specific engineering approval.
- Four Ds of weathertightness
- Deflection keeps water off the building, drainage removes water that gets in, drying allows moisture to escape, and durability ensures materials last in the designed exposure.
- Cladding cavity requirement
- E2/AS1 requires a drained and ventilated cavity, typically 20 millimetres deep, behind most cladding types. Cavity battens create this space and allow water to drain out.
- Cladding ground clearance
- Under E2/AS1, cladding must finish at least 100 millimetres above paved ground and 175 millimetres above unpaved ground to prevent moisture uptake and capillary rise.
- Flashing lap direction
- Flashings are lapped shingle-style: the upper flashing laps over the lower one so water runs outward and downward. Head flashings need a minimum 10 millimetre upstand.
- Building wrap installation
- Wall underlay is installed with laps per the manufacturer, typically 75-150 millimetres, and lapped over flashings so any water drains outward, not into the frame.
- Lining fixing centres
- Thirteen millimetre plasterboard on walls is fixed to studs at 600 millimetres maximum centres. Ceiling battens are typically at 400-600 millimetres depending on sheet thickness and span.
- Level 4 plasterboard finish
- Level 4 is the New Zealand standard finish for painted interior walls. Level 5 adds a skim coat over the whole surface for critical lighting or gloss paints.
- Wet area lining requirements
- Bathrooms and laundries use moisture-resistant plasterboard. Showers require a waterproof membrane under E3/AS1, installed before tiling and turned up walls and over curbs.
- Timber treatment classes
- H1.2 suits interior dry use, H3.1 and H3.2 exterior above ground, H4 ground contact, and H5 in-ground or marine. Treatment must match the exposure and hazard.
- SG8 timber grade
- SG8 is the common New Zealand structural grade for radiata pine, with a characteristic bending stress of 8 megapascals. MSG8 and VSG8 denote machine and visual stress grading.
- Circular saw blade depth
- Set blade depth so the teeth protrude no more than about 5 millimetres below the timber. The retracting guard must return freely before use.
- RCD protection on site
- Portable electrical tools on construction sites require residual current device protection. 230 volt tools must be RCD-protected, or use 110 volt (SELV) equipment.
- Ladder 1 in 4 rule
- Set the ladder base one unit out for every four units of height. Secure top and bottom, and maintain three points of contact while climbing.
- Site induction purpose
- Induction covers site hazards, emergency procedures, first aid arrangements and site rules. Every worker and visitor must be inducted before entering the work area.
- Toolbox talk
- A short pre-task briefing, usually 5-15 minutes, covering the hazards, controls and any changes to the plan for the work about to start.
- Written variation
- A variation changes the agreed scope, price or programme. It must be recorded in writing and signed before the work proceeds; verbal instructions should be confirmed by email.
- Durability periods under B2
- Building Code clause B2 sets durability at 50 years for structural and inaccessible items, 15 years for accessible but not easily replaced items, and 5 years for easily replaced items.
- Producer statements
- PS1 covers design, PS2 design review, PS3 construction and PS4 construction review. They are issued by suitably qualified people as evidence of compliance with the Building Code.