- Minimum sewer gradient DN100
- The minimum fall for a 100 mm nominal diameter sewer is 1:60 (1.67%), which provides self-cleansing velocity of about 0.6 m/s at full flow.
- Trap seal depth
- A water seal of 25–50 mm for fixtures and 50 mm minimum for floor wastes prevents sewer gas entry; 75 mm for gully traps.
- Vent stack termination
- A vent stack must extend at least 150 mm above the roof surface and be at least 3 m from any openable window or air intake.
- Fixture unit (FU)
- One fixture unit equals 0.03 L/s discharge; a WC is 6 FU, a basin 1 FU, used to size drainage pipes and vents.
- Inspection opening location
- Inspection openings are required at the base of each stack, at changes of direction greater than 45 degrees, and at intervals not exceeding 15 m.
- Minimum fixture pressure
- Potable water supply must deliver at least 50 kPa at taps, 100 kPa at showers, and 150 kPa at flush valves under flow conditions.
- Backflow prevention device selection
- High hazard requires a reduced pressure zone (RPZ) device; medium hazard a double check valve; low hazard a single check valve.
- RPZ annual test
- Test the reduced pressure zone device annually: check valve tightness, relief valve opens at 14–21 kPa differential, and air inlet functions.
- Maximum water velocity
- Design cold water pipes for maximum 1.5 m/s and hot water pipes for 1.0 m/s to limit noise, erosion, and pressure surge.
- Air gap requirement
- A physical air gap of at least twice the pipe diameter (minimum 25 mm) is the only acceptable high-hazard protection for potable supply.
- Gas pipe pressure test
- Natural gas and LPG piping must be pressure tested at 7 kPa for 10 minutes with no pressure drop, using air or inert gas.
- Gas appliance flue clearance
- Flue terminals must be at least 500 mm from openable windows, 300 mm from non-openable, 1000 mm from boundaries, and 1500 mm from mechanical air intakes.
- Combustion air requirement
- Provide 1 m² free area per 250 MJ/h for natural gas appliances and 1 m² per 125 MJ/h for LPG appliances, adjusted for louvre free area.
- Gas regulator outlet pressure
- Set natural gas regulator outlet to 1.0–1.5 kPa and LPG to 2.75 kPa; lock-up pressure must not exceed 1.25 times set pressure.
- Gas leak detection method
- Use soap solution or an electronic gas detector to locate leaks; never use a flame. Isolate and repair if leak rate exceeds 0.5 L/h.
- Minimum roof slope metal
- Metal sheet roofing requires a minimum slope of 5 degrees (1:12); tiles require 15 degrees (1:4); membrane roofs 1.5 degrees (1:40).
- Rainfall design intensity
- Design stormwater systems using the 1% annual exceedance probability (1 in 100 year) rainfall intensity for the critical duration.
- Stormwater pipe gradient
- Stormwater pipes must have a minimum gradient of 1:100, providing self-cleansing velocity of at least 0.6 m/s and maximum 3 m/s.
- Box gutter overflow
- Box gutters require overflow provisions sized for 1.5 times the design flow to handle blockage or extreme rainfall events.
- Downpipe capacity DN100
- A 100 mm round downpipe can drain approximately 0.20 L/s per square metre of roof area at 100 mm/h rainfall intensity.
- Drawing scale conventions
- Use 1:100 for floor plans, 1:50 for details, and 1:20 for assemblies; always note the scale and units in millimetres.
- Plumbing symbol floor waste
- A circle with a cross inside represents a floor waste on plumbing drawings; a triangle indicates a vent.
- As-built drawing delivery
- As-built drawings must be updated with all changes, invert levels, coordinates, and material types, and delivered within 10 business days of completion.
- Specification standard references
- Plumbing specifications must reference AS/NZS 3500 series, AS 5601 for gas, AS 2200 for drawing practice, and the NCC.
- Notifiable work inspection
- Notifiable plumbing work must be inspected by the regulator before concealment; provide at least 48 hours notice before covering.
- Certificate of Compliance
- A Certificate of Compliance is issued for all regulated plumbing work, includes test results and defects, and must be retained for 7 years.
- Continuing professional development
- Licensed plumbers must complete 12 hours of CPD per year, including at least 4 hours on regulatory updates and standards changes.
- Confined space entry testing
- Before entry, test for oxygen 19.5–23.5%, flammable gas below 5% LEL, hydrogen sulphide below 10 ppm, and carbon monoxide below 30 ppm.
- Trench shoring requirement
- Trenches deeper than 1.5 m require shoring or benching; provide a ladder every 9 m and keep spoil at least 0.5 m from the edge.
- Sediment runoff control
- Install silt fences and sediment basins to prevent runoff entering stormwater; manage waste segregation and never discharge trade waste to stormwater.
- Progress payment timing
- Under security of payment legislation, progress payment claims must be paid within 15 business days of the claim being made.
- Retention percentage
- Retention is typically 5% of contract value held for 12 months, reducing to 2.5% at practical completion to secure defects liability.
- Supervision ratio apprentices
- One licensed plumber may supervise a maximum of two apprentices on site; direct supervision is required for all notifiable work.
- Quality assurance hold point
- A hold point in an inspection and test plan requires sign-off by the supervisor or inspector before the next stage of work proceeds.