S+SNZ Spatial Measurement study materials
S+SNZ Spatial Measurement study resources

S+SNZ Spatial Measurement cheat sheet

S+SNZ Spatial Measurement · Keep the key ideas within reach.

Quick reference

Land development and urban design

  • Net residential density = dwellings ÷ net developable area (excludes roads, reserves, stormwater land); gross density includes all site land.

  • Movement hierarchy: arterial roads carry through traffic, collectors distribute, local roads give access; design speed and carriageway width decrease down the hierarchy.

  • Intersection sight triangles are measured along each approach and kept clear of obstructions above about 1.0 m; required leg length increases with approach speed.

  • Earthworks balance: compare cut volume × bulking factor against fill volume × compaction factor; an unbalanced site needs import, disposal or a re-graded design.

  • Finished floor levels are set above the design flood level plus freeboard (commonly 0.3–0.5 m) and above surrounding ground with fall away from the building.

  • Accessible routes: maximum longitudinal gradient 1:20, ramps no steeper than 1:14 with landings and handrails, cross-fall limited to about 1:40.

  • Street enclosure is described by the building-height-to-street-width ratio; ratios between about 1:1 and 1:3 give comfortable pedestrian-scale enclosure.

  • Post-development stormwater peak flows are controlled to pre-development rates using detention, with first-flush treatment for contaminant removal.

  • Tight kerb radii and short crossing distances reduce vehicle turn speeds and pedestrian exposure at local road intersections.

Quick reference

Resource management

  • Section 5 RMA 1991 purpose: enabling people and communities to provide for wellbeing while sustaining resources to meet the foreseeable needs of future generations.

  • Activity classes run permitted, controlled, restricted discretionary, discretionary, non-complying, prohibited; each class carries different consent and assessment tests.

  • Section 104D gateway for non-complying activities: consent may be granted only if adverse effects are minor, or the activity is not contrary to objectives and policies.

  • Consent types include land use, subdivision, water permit, discharge permit and coastal permit; applications require an assessment of environmental effects under Schedule 4.

  • National direction (National Policy Statements, National Environmental Standards, National Planning Standards) must be given effect to in regional and district plans.

  • Designations under sections 168–189 give requiring authorities rights to use land for public works; an outline plan may be required before construction.

  • Archaeological sites (generally pre-1900) require an authority from Heritage New Zealand Pouhere Taonga before modification or destruction.

  • Effects assessment covers actual, potential, temporary and cumulative effects; the mitigation hierarchy runs avoid, remedy, mitigate, then offset or compensate.

  • Notification decisions follow sections 95A–95G: public, limited or no notification, with affected-person and trade-competition tests.

Quick reference

Civil engineering surveying

  • Average end area volume: V = (A1 + A2)/2 × L, where A1 and A2 are cross-sectional areas at chainages separated by distance L.

  • Prismoidal formula: V = L/6 × (A1 + 4Am + A2), used where sections change in shape as well as area.

  • Level book check: sum of backsights minus sum of foresights equals last reduced level minus first reduced level.

  • Grade percentage = (rise or fall ÷ horizontal distance) × 100; a 2 per cent grade rises 2 m in 100 m.

  • Total station setting out converts slope distance to horizontal using the vertical angle, then pegs by angle-and-distance from control or by offsets from a string line.

  • Batter slopes are stated as vertical:horizontal; the batter-ground intersection is found by trial along successive cross-sections from the design formation.

  • Pipe setting out controls invert level, grade and cover: minimum cover, design gradient and manhole invert levels are checked at each structure.

  • Cross-section areas over irregular ground are computed by the trapezoidal rule, summing strip widths multiplied by average heights.

  • As-built surveys compare constructed position and level with design, checked against specified tolerances such as ±25 mm for pipe inverts.

Quick reference

Positioning and measurement

  • GNSS needs at least four satellites for a 3D position plus receiver clock; five or more improves ambiguity resolution and reliability.

  • Dilution of precision: lower is better; PDOP below about 6 is commonly required for RTK, with HDOP governing horizontal quality.

  • GNSS error sources include ionosphere, troposphere, multipath, orbit and clock errors; differencing between receivers and satellites removes most common-mode error.

  • RTK accuracy degrades as baseline length increases; network RTK (VRS) extends effective coverage by modelling atmospheric delay.

  • Total station reduction: horizontal distance = S·sin z and vertical component = S·cos z, where S is slope distance and z the zenith angle.

  • Traverse angular misclosure is compared with an allowable value (often proportional to the square root of the number of angles) before distribution.

  • Compass (Bowditch) rule distributes traverse misclosure proportionally to leg length for both coordinates.

  • Curvature and refraction combined correction is about 0.067 D² metres with D in kilometres, subtracted from the staff reading; refraction is roughly one-seventh of curvature.

  • Ground distance = grid distance ÷ combined scale factor, where the combined factor is the projection scale factor multiplied by the elevation factor.

Quick reference

Cadastral surveying

  • Parcels are defined by survey marks and the cadastral survey dataset lodged with LINZ; the title diagram depicts, but does not itself define, the boundary.

  • Reinstatement evidence hierarchy: original marks, then undisturbed marks, then occupation consistent with the record, then record measurements, then uncoordinated position.

  • The Rules for Cadastral Survey 2010 set accuracy standards, mark requirements, and the content and form of cadastral survey datasets.

  • Horizontal datum is NZGD2000; vertical datum is NZVD2016; NZTM2000 is used for projected mapping coordinates.

  • Boundaries are defined by bearing (azimuth) and distance vectors from the record; permitted misclose depends on survey class and location, with urban tolerances tighter than rural.

  • Easements, covenants and encumbrances are registered against titles and shown on plans; they burden or benefit land without transferring ownership.

  • Unit title boundaries are defined by a unit plan under the Unit Titles Act 2010; cross-lease boundaries derive from a lease of part of the fee simple with a flat plan.

  • Marks may be geodetic (PRN) or cadastral (pins, pipes, plaques); disturbed marks must be checked, reinstated or reported with supporting evidence.

  • Stated parcel area is indicative only; where area and boundary dimensions conflict, the dimensions and marks govern.

Quick reference

Hydrographic surveying

  • Soundings are reduced to chart datum, normally Lowest Astronomical Tide in New Zealand, so charted depths are rarely less than actual depth.

  • Reduced depth = measured depth below transducer + transducer draft + height of tide above chart datum.

  • Tide corrections come from a tide gauge or predicted model; bar checks before and after survey verify draft and sounder calibration.

  • Multibeam swath width = 2 × depth × tan(θ/2); a 120-degree system covers roughly 3.5 times the water depth.

  • Sound speed in seawater is about 1500 m/s and varies with temperature, salinity and pressure; sound velocity profiles correct refraction of the beams.

  • IHO S-44 defines survey orders (Exclusive, Special, 1a, 1b, 2) with corresponding total horizontal and vertical uncertainty limits.

  • Positioning uses GNSS RTK or PPK for the vessel and USBL or LBL acoustic systems for ROV, towed body and diver positions.

  • Full multibeam coverage is required for navigational surveys; single beam lines are spaced to give 10–20 per cent overlap between adjacent lines along the seabed.

  • Vertical uncertainty budget includes tide, draft, sound velocity, and residual heave, roll and pitch errors.

Quick reference

Spatial / GIS

  • NZTM2000 is EPSG:2193, a Transverse Mercator projection with central meridian 173°E, scale factor 0.9996, false easting 1600000 and false northing 10000000.

  • NZGD2000 geographic coordinates are EPSG:4167; WGS84 geographic is EPSG:4326; transformations between them are handled by PROJ pipelines.

  • Vector topology rules include must not overlap, must not have gaps, must not self-intersect and must be covered by; validation checks enforce these before analysis.

  • Raster cell size sets the spatial resolution and area precision; each cell value represents the whole cell, so areas are quantised.

  • Common overlay operations are clip, intersect, union and erase; buffer and dissolve operate on single layers by proximity or attribute.

  • A relational join matches records on a shared key; a spatial join matches records by geometric predicate such as intersects, within or contains.

  • DEM stores ground surface elevation; DSM includes buildings and vegetation; DTM is a bare-earth model produced by classifying and removing above-ground LiDAR returns.

  • Positional accuracy is reported as RMSE in horizontal and vertical components, and dataset quality is documented in metadata following ISO 19115.