- CT calculation
- CT is disinfectant residual concentration in mg/L multiplied by contact time in minutes. Required CT depends on disinfectant, pH, temperature, and target pathogen log inactivation.
- Turbidity limit filtered water
- Filtered water turbidity must be ≤0.3 NTU in at least 95% of monthly measurements and never exceed 1 NTU. Individual filter effluent must be ≤0.3 NTU in 95% of samples.
- Jar test purpose
- A jar test simulates coagulation and flocculation to determine optimum coagulant dose and pH by comparing settled turbidity across varying chemical doses.
- Chlorine demand
- Chlorine demand is the difference between applied chlorine dose and free chlorine residual after a specified contact time. It represents chlorine consumed by oxidizable substances in water.
- Filter backwash expansion
- Backwash must expand the filter bed at least 20% to release captured particles. Typical backwash rate is 15–20 gpm/ft² for anthracite-over-sand filters.
- Lead action level
- The 90th percentile lead action level is 0.015 mg/L. Exceeding it triggers corrosion control treatment, public education, and source water monitoring requirements.
- Log removal credits
- Conventional filtration provides 2.5-log Giardia and 2-log virus credit. Disinfection must provide the remaining credit to achieve required 3-log Giardia and 4-log virus inactivation.
- Distribution chlorine residual
- Minimum free chlorine residual in distribution is 0.2 mg/L; total chlorine minimum is 0.5 mg/L. Maximum residual disinfectant level is 4.0 mg/L as Cl₂.
- Total coliform rule
- No more than 5% of monthly samples may be total coliform-positive for systems collecting 40 or more samples. Any positive requires repeat sampling within 24 hours.
- Minimum distribution pressure
- Distribution systems must maintain at least 20 psi under all conditions. Normal operating pressure is typically 50–80 psi, with maximum around 100–125 psi to avoid damage.
- Hydrant flow test
- A hydrant flow test measures static pressure, residual pressure, and pitot pressure to calculate flow. Results determine available fire flow and system capacity.
- Backflow prevention assembly
- Reduced-pressure zone (RPZ) and double-check valve assemblies prevent backflow. RPZ assemblies must be tested annually by a certified tester; air gap is the most reliable method.
- Water main disinfection
- After repair or installation, chlorinate main to 25–50 mg/L for 24 hours or 100 mg/L for 2 hours, then flush and collect bacteriological samples before service.
- Storage tank turnover
- Storage tanks should turn over every 1–3 days to prevent water age and disinfectant loss. Poor turnover requires mixing or operational cycling to maintain quality.
- BOD₅ calculation
- BOD₅ = (initial DO − final DO) × dilution factor, where dilution factor equals (sample volume + dilution water volume) divided by sample volume.
- F/M ratio
- Food-to-microorganism ratio equals BOD or COD loading in lb/day divided by MLVSS in lb. Typical conventional activated sludge F/M is 0.2–0.5 day⁻¹.
- Mean cell residence time
- MCRT equals MLSS in aeration tank in lb divided by solids leaving the system per day in lb/day. Typical conventional activated sludge MCRT is 5–15 days.
- Sludge volume index
- SVI = (settled sludge volume in mL/L after 30 minutes × 1000) / MLSS in mg/L. SVI 80–150 mL/g indicates good settling; above 200 indicates filamentous bulking.
- Nitrification oxygen demand
- Nitrification consumes 4.57 lb O₂ per lb NH₃-N oxidized and destroys 7.14 lb alkalinity as CaCO₃ per lb NH₃-N oxidized.
- Aeration tank dissolved oxygen
- Maintain 1.5–3.0 mg/L dissolved oxygen in aeration tank for nitrification. Below 1.0 mg/L nitrification slows and filamentous bacteria may proliferate.
- Anaerobic digester operation
- Mesophilic anaerobic digestion operates at 35°C with 15–30 day detention, achieving 40–50% volatile solids reduction. Maintain pH 6.8–7.4 and volatile acid/alkalinity ratio below 0.3.
- Wastewater chlorine CT
- Disinfection CT is residual chlorine in mg/L multiplied by contact time in minutes. Required CT varies with pH, temperature, and target coliform reduction.
- Minimum sewer slope
- Minimum slope is 0.005 ft/ft for 8-inch pipe, 0.0033 ft/ft for 10-inch, and 0.0025 ft/ft for 12-inch. Manning equation determines design velocity.
- Manning equation
- Q = (1.486/n) A R^(2/3) S^(1/2) in English units. Manning n is 0.013 for concrete pipe and 0.009 for PVC pipe.
- Self-cleaning velocity
- Minimum velocity to prevent solids deposition is 2 ft/s at design flow. Maximum velocity is 10 ft/s to prevent pipe scour.
- Infiltration and inflow
- Infiltration is groundwater entering through pipe defects. Inflow is direct stormwater entering through connections. Both increase treatment costs and must be reduced.
- Lift station cycle time
- Cycle time equals wet well volume between pump-on and pump-off divided by inflow rate. Pump capacity must exceed peak inflow to prevent overflow.
- Force main velocity
- Minimum velocity in force mains is 2 ft/s to prevent solids deposition. Air release valves at high points and check valves at pump discharge are required.
- Manhole spacing
- Manholes are typically spaced 300–500 ft on straight runs. A drop manhole is required when invert difference exceeds 2 ft.
- Sewer air test
- Low-pressure air test pressurizes sewer to 4 psi for 5 minutes to verify tightness. Water exfiltration test uses 2 ft of head above pipe.
- Confined space entry
- Test atmosphere for oxygen 19.5–23.5%, flammable gas below 10% LEL, and hydrogen sulfide below 10 ppm before entry. Use forced ventilation and supplied-air respirator as needed.
- Sewer design velocity
- Design velocity should be at least 2 ft/s at average daily flow to keep solids moving. Velocity at peak flow should not exceed 10 ft/s to avoid scour.
- Wet well pumping
- Wet well storage volume must accommodate pump cycling without excessive starts. Pump capacity must exceed peak inflow, and standby pumps are required for reliability.