OK Boiler Operator · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Boiler Construction, Design, and Fittings

  • Sketch and label the main pressure-boundary parts of a firetube boiler and a watertube boiler from memory, then correct the sketch against a textbook diagram.

  • Describe how shell thickness, tube sheet thickness, and stayed-surface spacing are determined, and explain why the Oklahoma rules set minimum thickness and stay requirements.

  • List the required fittings on a boiler (safety valve, safety relief valve, water column, gauge glass, pressure gauge, blowdown, low-water fuel cutoff) and state the purpose and mounting rule for each.

  • Explain the difference between a boiler proper fitting and an external piping connection, giving three examples of each.

  • Define MAWP, design pressure, hydrostatic test pressure, and accumulation test pressure and state how they relate to one another.

Your checkpoint

A one-page hand-drawn and labeled cross-section of one firetube and one watertube boiler with every required fitting called out and its rule of location written beside it.

Week 2

Boiler Construction, Design, and Fittings & Boiler Accessories and Instrumentation

  • Identify the function of each accessory: feedwater pump, injector, economizer, air preheater, superheater, deaerator, and blowdown separator, and state where each sits in the flow path.

  • Trace the path of steam and water through a typical packaged boiler from feedwater inlet to steam header, naming each component in order.

  • Interpret a gauge glass reading and explain how a water column plus gauge glass assembly resists false level indications from foaming or carryover.

  • Explain how a pressure gauge, pressure transmitter, and pressure control switch differ in function and where each is used.

  • Read a simple P&ID symbol set and match ten symbols to the equipment they represent.

Your checkpoint

A flow diagram of a packaged boiler system with all accessories labeled and a written legend of at least ten P&ID symbols used in the diagram.

Week 3

Boiler Accessories and Instrumentation & Safety Devices, Controls, and Interlocks

  • Describe the operating sequence of a low-water fuel cutoff, including the difference between a float type and a probe or conductance type, and explain the manual reset requirement.

  • Explain how a high-pressure limit control, operating pressure control, and safety valve work together to protect the pressure boundary, and identify which is the last line of defense.

  • Describe flame safeguard programming: prepurge, pilot trial for ignition, main flame trial for ignition, run period, and postpurge, with the consequence of a failure at each step.

  • Explain the purpose of a burner management system interlock for low water, high pressure, low fuel pressure, and combustion air proving.

  • State the test method and recommended frequency for a low-water fuel cutoff and for a flame scanner response check.

Your checkpoint

A written step-by-step startup interlock checklist listing each permissive that must be proven before the main fuel valve opens, plus the test procedure and pass criteria for the low-water cutoff.

Week 4

Feedwater Systems and Water Treatment & Combustion, Fuels, and Burner Systems

  • Explain the four main problems feedwater treatment addresses (scale, corrosion, carryover, and deposits) and name the test used to monitor each.

  • Describe external treatment (softening, demineralization, deaeration) versus internal treatment (oxygen scavengers, scale inhibitors, pH and alkalinity control) and state when each is appropriate.

  • Interpret results for hardness, alkalinity, pH, conductivity, dissolved oxygen, and sulfite, and state a corrective action for an out-of-range value of each.

  • Explain the combustion triangle and the three T's, and describe how excess air, stack temperature, and CO relate to combustion efficiency.

  • Compare natural gas, propane, and fuel oil No. 2 in terms of stoichiometric air requirement, typical excess air, and handling hazards.

  • Describe the purpose of a draft fan, an air/fuel ratio linkage, and a stack damper, and explain what happens if they fall out of calibration.

Your checkpoint

A feedwater log sheet with target ranges for six tests plus a combustion analysis worksheet showing how you would calculate excess air from measured oxygen.

Week 5

Boiler Operation, Startup, and Shutdown

  • Write the cold startup sequence for a packaged boiler from pre-start inspection through online operation, including warm-up rate limits and why they matter.

  • Write the normal shutdown and emergency shutdown sequences and state the conditions that require an immediate emergency shutdown.

  • Explain bottom blowdown and surface blowdown: purpose, procedure, frequency, and the safety precautions for each.

  • Describe how to respond to low water, high water, carryover, and a safety valve that is simmering or lifting below set pressure.

  • Explain the warm-up and cooling rate limits for a boiler and the damage caused by thermal shock to tube sheets and refractory.

Your checkpoint

A complete one-page startup and shutdown procedure card for a packaged boiler, written from memory and then verified line by line against reference material, with every discrepancy noted.

Week 6

Boiler Operation, Startup, and Shutdown & Safety Devices, Controls, and Interlocks

  • Perform and document a safety valve pop test procedure, including the precautions, the required test pressure, and the records to keep.

  • Explain the difference between a try lever test and a pop test and state when each is acceptable.

  • Describe the checks a boiler operator must make at the start of each shift and record in a log.

  • Explain how to verify a flame scanner, a low-water cutoff, and a high-pressure limit without defeating the protection they provide.

  • Describe the lockout/tagout steps for taking a boiler out of service for internal work.

Your checkpoint

A shift round sheet covering at least twelve inspection points with the normal reading, alarm point, and action to take for each.

Week 7

Inspection, Maintenance, and Repairs

  • Describe the preparation for an internal inspection: cool-down, drain, isolation, opening, cleaning, and safe entry.

  • List the typical defects found on firetube and watertube boilers (scale, pitting, cracking, bulging, tube leaks, caustic embrittlement, refractory spalling) and the cause of each.

  • Explain hydrostatic testing: purpose, test pressure, hold time, and what a passing result looks like.

  • Describe how tubes are rolled or welded, how a staybolt is replaced, and what repair work requires a certified welder and an authorized inspector's approval.

  • Explain the role of the authorized inspector, the jurisdiction, and the owner in the inspection and repair process.

Your checkpoint

A defect identification table of at least ten boiler defects with location, probable cause, and recommended repair or monitoring action.

Week 8

Oklahoma Boiler Safety Rules and Regulations

  • State the Oklahoma Boiler Safety Rules requirements for operator certification or licensing, inspection frequency by boiler type, and the consequences of operating an uninspected boiler.

  • List the records an owner must keep and make available, including inspection certificates, repair reports, and operator logs.

  • Explain the Oklahoma requirements for reporting an accident or an unsafe condition and the process for returning a boiler to service after a repair.

  • Review all prior weeks' deliverables and re-test yourself on the weakest two domains with timed practice questions.

  • Build a personal reference sheet of the ten rules and formulas you are most likely to forget under exam pressure.

Your checkpoint

A two-page Oklahoma rules summary covering inspection intervals, recordkeeping, accident reporting, and operator requirements, plus a scored 40-question self-test with a written review of every missed item.

Milestones

Week 2: Can name every required boiler fitting and every major accessory, state its purpose, and draw the packaged boiler flow path from memory without notes.

Week 4: Scores at least 80 percent on a mixed 30-question set drawn from domains 1, 2, 3, and 6, and can explain each wrong answer in writing.

Week 6: Can recite the startup sequence, the emergency shutdown triggers, and the interlock permissives from memory, and has a completed shift round sheet ready for use.

Week 8: Scores at least 85 percent on a full-length timed practice exam weighted per the official domain percentages, with no domain below 70 percent.