Oregon DEQ Asbestos Abatement Essentials
Oregon's asbestos program is administered by DEQ under OAR Chapter 340, Division 248; rules cover licensing of abatement contractors, certification of workers, supervisor and contractor notification, work practices, and waste handling.
A certified asbestos abatement contractor license is required before performing abatement for compensation; individual workers and supervisors must hold valid DEQ-issued certificates, and the contractor must keep certificates on file and available at the job site.
DEQ must receive a written abatement notification before work begins; the notification identifies site, scheduled dates, contractor, supervisor, scope, and abatement methods, and material changes to the schedule require an updated notification.
A regulated asbestos abatement project generally triggers notification when the amount of asbestos-containing material to be removed meets or exceeds the threshold in OAR 340-248; small projects still must follow work practice and waste disposal rules.
Abatement means removal, enclosure, or encapsulation of asbestos-containing material; a survey or inspection by an accredited inspector is the basis for determining whether material is asbestos-containing and must precede demolition or renovation planning.
Asbestos-containing material is material containing more than 1 percent asbestos by weight, determined by polarized light microscopy (PLM) under EPA Method 600 or an equivalent DEQ-accepted method; point counting may be required for certain regulated materials.
Work practices include a regulated area with signage, negative air pressure with HEPA filtration, wet methods, sealed barriers and decontamination units, and prohibition of dry sweeping, visible dust, and uncontrolled demolition of asbestos-containing material.
Asbestos waste must be wetted, bagged or wrapped in leak-tight containers labeled as asbestos waste, and transported with a DEQ waste shipment record to an approved landfill permitted to accept asbestos; friable waste handling and disposal records are retained.
Oregon requires asbestos abatement workers and supervisors to complete accredited training and refresher courses on the required schedule, and DEQ certification requires application, fee, and proof of current training; certification is not transferable between individuals.