NFPA 72
National Fire Alarm and Signaling Code; sets requirements for design, installation, testing, and maintenance of fire alarm systems in the United States.
NEC Article 760
Covers fire alarm system wiring, including power-limited and non-power-limited circuits, and requires listed cable and proper separation.
Smoke detector spacing
30 ft (9.1 m) on smooth ceilings, with the first detector within 15 ft (4.6 m) of any wall or ceiling projection.
Manual pull station height
Must be mounted 3.5 ft to 4.5 ft (1.07 m to 1.37 m) above finished floor and within 5 ft (1.5 m) of an exit door.
Photoelectric smoke detector
Uses a light source and sensor to detect scattered light from smoke particles; responds best to smoldering fires with larger particles.
Ionization smoke detector
Uses an ionization chamber to detect changes in current caused by smoke particles; responds best to flaming fires with smaller particles.
Rate-of-rise heat detector
Activates when temperature increases rapidly, typically at 15°F (8.3°C) per minute, regardless of the absolute temperature.
Duct smoke detector
Required in HVAC systems over 2,000 cfm (0.94 m³/s); detects smoke in the air stream and requires remote test stations.
Class A circuit
Initiating or notification circuit that continues to operate with a single open fault by providing a redundant return path.
Class B circuit
Circuit that does not survive a single open fault; a break in the wiring causes loss of devices beyond the break.
Notification appliance circuit
Supervised circuit that powers horns, strobes, speakers, and other notification appliances; must be designed for voltage drop.
Audible signal level
At least 15 dBA above ambient or 5 dBA above maximum ambient (whichever is greater) and at least 75 dBA at 10 ft (3 m).
Strobe synchronization
Required when multiple strobes are visible from a single location; prevents seizures and confusion by flashing simultaneously.
Strobe candela rating
15 cd for rooms up to 20 ft x 20 ft; higher candela required for larger rooms per NFPA 72 Table 18.5.5.4.1(a).
Voltage drop formula
VD = (2 x L x R x I) / 1000, where L is one-way length in feet, R is resistance in ohms per 1000 ft, and I is current in amperes.
Copper wire resistance
Approximate values: 14 AWG = 3.07 ohms/1000 ft; 12 AWG = 1.93 ohms/1000 ft; 10 AWG = 1.21 ohms/1000 ft; 16 AWG = 4.89 ohms/1000 ft.
Maximum NAC voltage drop
Typically 10% of rated voltage (2.4 V for 24 V systems) to ensure the last appliance operates properly.
Battery calculation formula
Standby current (A) x 24 h + alarm current (A) x 0.083 h (5 min) = Ah; add 20% derating for aging and temperature.
Voice system battery calculation
Use 24 hours standby plus 15 minutes (0.25 h) alarm, instead of 5 minutes, for voice evacuation systems.
Battery charger requirement
Must recharge batteries within 48 hours after full discharge; 24 hours for voice systems.
Primary power requirement
120 VAC dedicated branch circuit labeled "FIRE ALARM CIRCUIT CONTROL," protected against accidental disconnection.
Secondary power requirement
Must operate system for 24 hours standby plus 5 minutes alarm (or 15 minutes for voice) using batteries or approved source.
FPLR cable
Fire alarm cable rated for riser use; suitable for vertical runs between floors in non-plenum spaces.
FPLP cable
Fire alarm cable rated for plenum use; required in environmental air spaces such as above suspended ceilings.
Power-limited circuit separation
Must be separated from non-power-limited circuits by separate conduits or barriers; label circuits appropriately.
Record of Completion
NFPA 72 Form 1 documenting that the system has been installed and tested per design; required for acceptance.
Record of Inspection and Testing
NFPA 72 Form 2 documenting periodic inspection and testing results; must be maintained and available to the AHJ.
Smoke detector sensitivity testing
Required within one year of installation and every two years thereafter; use calibrated equipment per manufacturer instructions.
Annual inspection
All initiating devices and notification appliances must be inspected and tested annually per NFPA 72.
Oregon fire alarm contractor license
Required by the Oregon State Fire Marshal for contractors installing or servicing fire alarm systems; individuals must hold installer certificate.
Permit requirement
Must obtain permit from local AHJ before installing or modifying a fire alarm system; submit plans for review.
AHJ
Authority Having Jurisdiction; the organization or individual responsible for enforcing code requirements and approving installations.